1 / 17

Facilities, Planning, and Construction November 16, 2015 – Monthly Construction Report Report

Stay informed about the latest construction progress on V.R. Eaton High School Outdoor Learning Center, Steele HVAC and Roof Renovation, and other facilities projects. Get insights into planning, bidding, and completion dates.

eboehm
Télécharger la présentation

Facilities, Planning, and Construction November 16, 2015 – Monthly Construction Report Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities, Planning, and Construction November 16, 2015 – Monthly Construction Report Report

  2. Area Currently Under Construction/ Planning Facilities Under Construction: V.R. Eaton High School Outdoor Learning Center Facilities in Planning/Bidding Stage: Transportation Complex Steele HVAC and Roof Renovation

  3. Remaining Work at Eaton High School • Landscape • Weather Pending • Pond C is the last area to be finished (behind baseball and softball fields) • 3rd Floor Academic Wing • Finish up this area

  4. Outdoor Learning Center Architect: Stantec Architects Contractor: Northstar Builders Const. Start Date: February 2015 Completion Date: August 2016 Status: • Piers Completed: • 100% completed excluding the Overlook B • Geo wells 100% completed • Large Pavilion Moisture Conditioning is 75% Complete (12’) • Anticipation wall grade beams are poured • Septic Demo is 80% Complete

  5. Great Hall and Front Drive

  6. Great Hall

  7. Large Pavilion

  8. Large Pavilion

  9. Wetland Pavilion and Restroom Building

  10. Wetland Pavilion

  11. Restroom Building

  12. Creekside Pavilion

  13. Creekside Pavilion

  14. Transportation Complex Contractor: Const. Start Date: January 2015 Completion Date: June 2015 Program: • Central Bus Complex Update: • Advertising begins November 17th • Presented Contractor with cost in December • Durham School Services, L.P. agrees to contribute $745,000 to the Paving Project

  15. Steele HVAC and Roof Replacement Engineer: MetCo Roof Consultant: Amtech Const. Start Date: June 2016 Completion Date: August 2016 Status: • Working with consultants on design • Method of Delivery to the Board in December • Drawings to be completed at the beginning of 2016 • Bid out project beginning of 2016

  16. Facilities, Planning, and Construction November 16, 2015 – Monthly Construction Report Report

More Related