Airport Capital Improvement Project Guide: Funding, Formulation, and Implementation
E N D
Presentation Transcript
Overview • Proposed Project • Funding • Formulation • Project Justification • Eligibility • Priority Ranking • Funding Sources • Recommendations • Project Contents • Schedule • Potential Issues
Project Justification • Advance FAA policy? • Actual need? • Appropriate scope? Source: Draft AIP Handbook Order 5100.38D
Ineligible Projects • Does not directly serve airport operations • Maintenance and training costs • Exclusive use • Doing something more than once
Priority Ranking National Priority Rating (NPR) = (k5*P)*[(k1*A)+(k2*P)+(k3*C)+(k4*T)] Source: FAA Order 5100.39A
Priority Ranking Project Purpose (P) Project Component (C) Project Type (T) Airport Type (A) Source: FAA Order 5100.39A
March Inland Port • Joint Use Airport: 1997 (NPIAS Category: Reliever) • Project: GA facilities • FAA requirement: “open to the public” • Project description ($7.5 million) • 150,000-square-foot apron (segregated) • 5,000-square-foot terminal • 10,000-gallon-above ground fuel storage tank (AVGAS)
Caltrans Match • FAA Airport Improvement Program • Primary Entitlements • Non-Primary Entitlements • State Apportionment • Discretionary 5% Local Match 5% 90%
$3.45 b Source: Airport Improvement Program (AIP) Grant and Apportionment/Entitlement Data
$178.4 m $65.6 m Source: Airport Improvement Program (AIP) Grant and Apportionment/Entitlement Data
Project Funding • Know your bank account • Budget for match • Accurate cost estimating • Other sources of funding
March GA Development • Project eligibility/funding • MAP—fuel facility/hangars/utilities ($7m annually) • Discretionary—apron, taxiway, lighting, signage • Entitlements—terminal (and MAP) • Funding Challenges • Environmental • Local match requirements • Carrying cost
Process • Project purpose • Contents of the project • Cost estimating • Duration of project • Other considerations • Construct • Design • Environmental • Planning
Planning • ALP/Exhibit A approval • Master Plan/ALP Update • Sustainability, AGIS, public outreach • CEQA
Environmental • NEPA approval • CatEx/EA/EIS • Technical studies/CEQA • New FAA regulations
Design/Construction • Specify design only design/construct • Clear project description/justification in data sheets • Clearly defined exhibit of project location • Solid preliminary cost estimates
Lesson Learned • Lessons Learned • NPR/ADO directives • Funding sources • ACIP to accommodate FAA ADO • Adjustments • Understanding funding dynamics • Meet with ADO staff regularly • ACIP formulation by priority
Importance of ACIP • Critical path to airport development • Awards airport for hard work • Relationship builder Made me a better airport manager