1 / 43

SKA Pre Construction Phase Infrastructure

SKA Pre Construction Phase Infrastructure. Tracy Cheetham Carel van der Merwe General Manager: Infra & Site Ops Infrastructure System Engineer tcheetham@ska.ac.za carel@ska.ac.za . Michelle Storey Rebecca Wheadon

Télécharger la présentation

SKA Pre Construction Phase Infrastructure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SKA Pre Construction PhaseInfrastructure Tracy CheethamCarel van der Merwe General Manager: Infra & Site Ops Infrastructure System Engineer tcheetham@ska.ac.za carel@ska.ac.za Michelle Storey Rebecca Wheadon CSIRO SKA Executive Officer Project Manager michelle.storey@csiro.au rebecca.wheadon@aurecongroup.com

  2. Requirements Allocation

  3. Construction sequence

  4. Flow of Requirements

  5. SE Process for INFRA

  6. ICD – 3 Iterations

  7. ICD – 3 Iterations • Iteration 1 (DRAFT1) • Part of Requirement Definition (by RR) • Concept Driving IF requirements • Iteration 2 (DRAFT2) • Agreed ICD between INFRA and other elements • Part of Preliminary Design (Part of PDR pack) • Iteration 3 (FINAL) • Signed Off at conclusion of PDR process • Formal change control for detailed design

  8. Vessel and Payload

  9. INFRA ICDs with other elements

  10. ICD INFRA and DSH • IF Lead = INFRA • IF Boundaries • Array Layouts (SKA1-MID, Survey) • Dish construction Facilities • Antenna Foundations • IF Types • Foundations Physical (Structural, cables) • Dish Electrical Power Budget (Electrical) • Power Backup & UPS (or not) (Reliability) • Earthing and LP • Staff requirements (ILS)

  11. ICD INFRA and DSH... • Issues • Final Array Layouts • Loadings and Mechanical Interface • Responsibility for Bolt cage assembly (DISH?) • Power per antenna • Fibre / sleeve IF to DISH (INFRA or SaDT) • UPS for stowing (Dish or INFRA?) • Separate enclosure for Survey (RFI shielded) • Assume 10% of array can fail?

  12. Dish - Bilateral • ICD lead =

  13. ICD INFRA and LFAA • ICD Lead = LFAA / INFRA (AUS)? • IF Boundaries • Array Layout • Array Foundations • On site Bunker • IF Types • Physical • Antenna Electrical Power (Electrical) • Cooling • Power Backup (Reliability) • Local infrastructure

  14. ICD INFRA and LFAA.... • Issues: • Power system design • Compatible array config between DSH and LFAA • Power requirements per antenna • Solar Power • Impact on buildings

  15. LFAA - Bilateral • Lead = • Bunker, 256 racks + a few • Fibre management (RF over Fibre) • Integrate correlator ? Maser? MGR? In bldg • 500 000 Fibres (2 per antenna) • Fibre design = LFAA, who supplies? • Cable buried ? Or conduit vs phase stability (MRO tests)

  16. LFAA-INFA • Solar power for each 25k antenna , Battery tech? • Total 2-3 MW • MRO = 80 racks (Double screen),80 single screen • ICD doc

  17. ICD INFRA and SaDT • ICD Lead = INFRA • IF Boundaries • Racks in Processing Facilities / containers • Fibre buried / cables • Fibre on Power Lines? (Physical) • IF Types • Space if facilities (No racks, size) • Power & Cooling • LAN / Data Interface (Data) • Staff requirements (ILS)

  18. ICD INFRA and SaDT..... Issues • Location of Super computer centre (RSA) • IRD or ICD for SaDT and INFRA • Use of existing Fibre links (Buried & Overhead) • IF / cut over from Integrated LAN (RSA) • Environmental Data Document (SKAO?) • Special requirements for Masers? • Telephone data responsibility? • BMS data over network

  19. ICD INFRA and CSP • ICD Lead = CSP? • IF Boundaries • Racks in Processing Facilities / containers • IF Types • Racks (Qty, Space, Mass) • RFI screening • Power Type and Load • Power Usage and Backup / UPS (Reliability) • Cooling type • Cooling redundancy (Reliability)

  20. ICD INFRA and CSP..... • IF Types.... • LAN / Data interface (Data) • Access control / BMS (Functional) • Staff Requirements (ILS) • Issues • 250 racks for Pulsar search (RSA) • Rack requirements for LFAA/Survey (AUS)

  21. CSP – Bi Lateral • Space, Power, Cooling • Survey ~ 100kW,MID ~ 100kW, LFAA ~ 50kW • Confirm UPS requirement (AUS) • 3phase AC 400V interface • P search = 1MW = 50 racks (100m distance, spigot) • Air or Liquid cooling for P search ? • AUS = Liquid, RSA = Air • Fibre racks (overhead 400mm) • RFI spec TBC (100dB)

  22. CSP - Bilateral • Process • AIV to spec • growth path • Cable marking etc • Doc of what we have (INFRA) – Before T0 • Space, power, cooling • RFI screening (RFI ITT) • Smoke, gas, access/CCTV, ESD (interlock?) • Standards • ICD Doc (CSP) – T0-12W • Limits (Power) Agreed doc • RR to PDR (update via CM) • PDR to CDR (update via CM)

  23. ICD INFRA and SDP • IF Boundaries • Racks in Processing Facilities • IF Types • No Racks in facility (Qty, Size & mass) • RFI screening • Power Type AC/DC/Voltage/1 or 3 Phase • Power Usage & Backup / UPS (Reliability) • Cooling type • Cooling redundancy (Reliability)

  24. ICD INFRA and SDP • IF Types • LAN / Data interface (Data) • Access control / BMS (Functional) • Staff Requirements (ILS/Con Ops) • Issues: • Space requirements for LFAA/Survey (AUS), • User supplied equipment space • Location of SDP (On site, off site)

  25. ICD INFRA and MGR (TM) • ICD lead = INFRA • IF Boundaries • Racks in Processing Facilities / containers • IF Types • Racks (space, size, mass) • Power Type & Quality • Power Backup / UPS (Reliability) • Cooling redundancy (Reliability) • LAN / Data interface (Data)

  26. ICD INFRA and MGR..... • IF Types..... • Access control / BMS (Functional) • Staff Requirements (ILS) • Issues

  27. Existing facilities – SA Site • KAPB • 130 racks in screened facility • 640kW cooling • 5kVA average per rack • Flexible feed to rack (1,3 ph A and B bus) • 40 Fibre cables entering building • 150 Fibre penetrate RFI screened room

  28. Existing – SA Site • Overall Power • 2.5 MVA fitted • 5 MVA with full UPS (N+1) • 6-7.5 MVA from current grid • Sheds • Size of shed vs dish size • Support base / workshops • Derived from Con Ops

  29. KAPB

  30. KAPB Nov 2012 June 2013

  31. KAPB Rack Layout

  32. Rack Growth

  33. Limitation – Grid Power

  34. Support base

  35. MRO – AUS Site

  36. MRO – AUS Site

  37. MRO – AUS Site

  38. MRO – AUS Site

  39. MRO – AUS Site

  40. MSF – AUS Site

  41. Pawsey Centre – AUS Site

  42. Pawsey Centre – AUS Site

  43. Pawsey Centre – AUS Site

More Related