An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Western Area Power Administration Transmission System Partnering Opportunities (FAQs) Anthony Montoya Assistant Regional Manager for Power System Operations September 14, 2004

  2. Introduction

  3. Desert Southwest Region • Markets and delivers Federal power • Nearly 70 municipalities, cooperatives, tribal authorities, federal and state agencies. • 3,100 miles of transmission lines • more than 40 substations • NERC load control area

  4. We get many questions… • Transmission construction capabilities • Transmission O&M capabilities • Use of ROW

  5. DSW Transmission FAQ 1 How has Western traditionally financed construction for transmission used to meet its Federal Hydropower mission? • Federal Appropriations • Repaid with interest • Excess capacity offered under OATT • Example: Liberty – Mead 345-kV

  6. DSW Transmission FAQ 2 Can another party participate with Western in a new transmission construction project? • Yes, Joint Participation Project • Joint ownership by special legislative authority • Example: Mead-Phoenix 500-kV

  7. DSW Transmission FAQ 3 Can a customer work with Western to fund either individual or Joint Participation Project transmission construction? • Yes, Contributed Funds • Net Billing • Example: Griffith-Peacock 230-kV line

  8. DSW Transmission FAQ 4 Does contributed funding give the funding party unique advantages when taking OATT service? • No

  9. DSW Transmission FAQ 5 Why would anyone want to contribute funds, rather than getting ownership-like rights through a Joint Participation Project? • Ownership-like rights over new segment not always sufficient to meet customer’s total needs. • Customer needs transmission service beyond the limits of the new transmission segment.

  10. DSW Transmission FAQ 6 How can a customer work with Western to get transmission constructed? • Talk to us • Joint Planning Agreement (JPA) • Ten Year Planning

  11. DSW Transmission FAQ 7 How has Western traditionally funded transmission operating and maintenance expenses? • Federal Appropriations

  12. DSW Transmission FAQ 8 Can another party work with Western to help fund O&M needs? • Yes, Advanced Funding • Example: Arizona Power Authority

  13. DSW Transmission FAQ 9 Will Western share easements or consolidate circuits? • Yes, essential to optimize scarce land. • Maintain reliability • Consistent with underlying land rights. • Recognize the value of the ROW. • Example: TEP, SEV, ED-3

  14. DSW Transmission FAQ 10 Are there any other options for working with Western on transmission? • Yes, transmission exchange • Mutually compatible needs • Equitable • Example:

  15. DSW Transmission FAQ 11 Any other transmission questions?

  16. DSW Transmission FAQ 12 Who can we contact for more information? • Ron Moulton (602) 352-2668 moulton@wapa.gov • Tony Montoya (602) 352-2780 tmontoya@wapa.gov