Ctclink Minutes – Approval • April 9, 2019
Ctclink program status • Remediation (CCS, TCC Updates) • Deployment Group 2 (Training, Testing, Deployment) • Deployment Group 3 (BPFG, Data Validation) • Deployment Group 4 (Initiation) • Deployment Group 5 (Early Visits/Reporting) • PM Summit: • 2 Days - Focused on College Implementation Activities • 1/2 Day - Focused on College Initiation Activities
Pilot remediation overview & status *FirstLink (pilot) colleges are validating open and closed items/numbers
Deployment Group 2 Self-Reported Status – April 1 to 12, 2019 Y
Deployment Group 3 Self-Reported Status – April 1 to 12, 2019
PM summit • Agenda Prep (Collaboration with College from each DG) • Dates: • May 6 & 7 – All Colleges (Implementation Activities) • May 8 - DG5 & DG6 (DG4 optional) focused on Getting Ready for Implementation (Initiation Activities) • Location: Wenatchee Valley College
DEPLOYMENT GROUPS AND TIMELINE Deployment Changes: • Bellevue: DG4 to DG5 • Columbia Basin: DG4 to DG6 • Shoreline: DG5 to DG6 requested
INITIATION schedule highlights Revised 2/20/2019 This chart shows when each deployment group (DG) begins its first phase (initiation) and estimated Go-Live date. Dates subject to adjustment.
DEPLOYMENT GROUP ALIGNMENT Background • Shoreline Community College requests to move from Deployment Group 5 to Deployment Group 6. • Discuss the impacts of adding a college to DG6 or leaving DG5 as is. Recommendations • The ctcLink Project Management Office recommends granting Shoreline Community College’s request in order to minimize impact to both DG5 and DG6. • To ensure college readiness, no further college movements are recommended within the deployment groups.
Online Admissions (OAA) Update • OAA Quick Wins (Current Improvements to Application in Production for FLC’s) • Final Interviews with Colleges and Universities • OAA Work Group feedback • OAA Work Group Recommendation
Continuing Education Update • Negotiations Update • Questions • Global Approach for consistent student experience • Pricing aligned based upon college size and enrollment • Integration for ctcLink CampusCE baseline
ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018
Other Discussion Items • -Executive Sponsor Engagement • -cELC/President Engagement • -SC Charter – Executive Sponsor Role • Subgroup to review Steering Committee Charter • Recommendations for addressing colleges in post-production that may no longer have an Executive Sponsor • Executive Sponsor title is currently a requirement for nominee to serve on ctcLink Steering Committee