An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WP 09MONITORING & FORECASTINGCENTRE for IBI MyOcean2 First Annual Meeting – Cork /16-17 April 2013 MyOcean2 First Annual Meeting – 17-18 April 2013

  2. Work Package Main Objectives 1/14 • To ensure and improve the reliable and accurate provision of a regional ocean forecast service on the IBI region • To ensure management of service and products, update on new IBI products (i.e. Re-analysis) • To provide a back-up capability: • A nominal system IBI-NOM operated by Puertos del Estado • A Back-up system IBI-BUP, operated by Mercator. • The system will include modeling improvements and advances derived from R&D when demonstrated. • A robust Tier 1 R&D activity is planned in order to address specific demands of improvement in the operational system • To contribute to enhance IBI users community MyOcean2 First Annual Meeting – 17-18 April 2013

  3. Partnership 2/14 Interface with Exec, Board, PMO, external representation, Cross-cutting Activ. 4 partners: PdE, CLS, CNRS & Mercator Oriented short-term R&D to improve IBI system & Service Product Quality (WP17) Develop IBI-Vn+1, n+2… Coordination R&D Operations & Service Daily operations & Service Interface with ServiceDesk, CIS, TACs & MFCs, Crosscutting WPs… MyOcean2 First Annual Meeting – 17-18 April 2013

  4. System & Production Evolution 3/14 • Objectives for V3 were • Make evolve IBI numerical solution • Upgrade IBI operational suites in Production Lines • Enhance Back-Up Services (exchange between PCs) • Improve CAL/VAL capabilities MyOcean2 First Annual Meeting – 17-18 April 2013

  5. System & Production Evolution 4/14 • Main achievements for V3 are • IBI-V3 solution includes improved river discharge data • A more robust & efficient operational suite: • Some sources of IBI incidents minimized with • incorporation of some extra QC procedures • Noticeable upgrade of IBI-MFC Validation capabilities: • Launch of NARVAL (north Atlantic Regional VALidation) Tool MyOcean2 First Annual Meeting – 17-18 April 2013

  6. System & Production Evolution 5/14 • Main difficulties encountered • Changes in computational environment in both Production lines: • Significant changes in Production hardware • environments both in NOM (PdE-CESGA for V3) • & BUP (MO-MF for V4) •  Open issue: Risk for operational V3 & V4 services ? MyOcean2 First Annual Meeting – 17-18 April 2013

  7. System & Production Evolution 6/14 • Main difficulties encountered: Back up issue 1st senario USERS CIS IBI-NOM IBI-BUP DU (PdE) DU (CLS) If IBI-NOM pb PU (PdE) PU (Mercator) MyOcean2 First Annual Meeting – 17-18 April 2013

  8. System & Production Evolution 7/14 • Main difficulties encountered • Results from Test of internal BUP production services: • Slightly difference in final products format (i.e. netcdf file format) has an unexpected impact on the download of mixed IBI (NOM & BUP production origin) data through subsetter service (PdEMisGW) ... OK FOR HOURLY PRODUCTS NOK FOR DAILY PRODUCTS MyOcean2 First Annual Meeting – 17-18 April 2013

  9. Improvements, results, illustrations 8/14 • IBI solution upgrades: • IBI-V3 will have a more realistic inputs for river discharge runoff data used. (More details on QuID) IBI River inputs locations. In green: daily runoffs hindcasts from E-HYPE model (SMHI) In red: daily runoffs obs data from PREVIMER (FCs from E-HYPE only ) River runoffs of Adour (on the left) and Garonne (on the right). Red line: monthly climatology runoffs used inIBI-V1, blue line daily runoffs used in IBI-V2and green line daily runoffs which take into account tributaries and used in IBI-V3. MyOcean2 First Annual Meeting – 17-18 April 2013

  10. IBI CAL/VAL improvements 9/14 • IBI Improved CalVal capabilities • Noticeable upgrade of the IBI-MFC Validation capabilities: Launch of NARVAL Tool (On-line & Delayed Mode) • Statistics covering longer periods (monthly, seasonal and annual reviews)  MyO Quarterly Validation Reports • Validation of daily IBI FC cycle. MyOcean2 V3 Acceptance & V4 Product Design Workshops – Madrid 28,29th January 2013

  11. Spanish Marine GMES User group 10/14 To enhance the downstream service Conceptual organization Kick-off Meeting Spanish Marine GMES UG (Madrid, Oct 18th 2012) Kick-off Meeting Iberian MyO IBI-MFC Users (Madrid, Nov 13th 2012)

  12. The Spanish IBI User Group: Institutions… 11/14 • 13 Groups articulates (by now) the Spanish Users Network: • 11 Intermediate/end user. • 2 Institutions related to MyO MCS. • Number of people implicated: • 25 technical contacts (already members of the mailing list) • 23 attendees to the Spanish IBI User Group Kick-off Meeting

  13. First period summary and next steps 12/14 • Objectivesfor V3 accomplished • Amelioration axis: • Operationalaspects: • Reduction of execution times associatedtomodel and computerchanges • IncreaseRobustness, preventing new risksidentifiedbefore V4 • Complete the full B.U. solution • R&D aspects • Improvement of engineering procedures to validate and include R&D tier 1 developments • Complete IBI R&D plan as established in PMP • Service and user outreach • Enhance user feedback (i.e. bug detection in current IBI products, new taylored user-oriented products) MyOcean2 First Annual Meeting – 17-18 April 2013

  14. First period summary and next steps 13/14 Evolutions scheduled for V4 • V4 R&D works mainly focus on improve IBI NEMO solution • New IBI V4 Products: • IBI RE-ANALYSIS • PHY • BGC Main DEV: PdE Main DEV: MO Main DEV: MO Main DEV: MO MyOcean2 First Annual Meeting – 17-18 April 2013

  15. First period summary and next steps 14/14 THANK YOU! MyOcean2 First Annual Meeting – 17-18 April 2013