html5-img
1 / 7

July 2007

Gas Interconnection between Spain and France Comments to the TSO’s document on the analysis of the future interconnection infrastructures needed between France and Spain until 2015. July 2007. Index. General Comments Interconnection projects

errol
Télécharger la présentation

July 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gas Interconnection between Spain and France Comments to the TSO’s document on the analysis of the future interconnection infrastructures needed between France and Spain until 2015 July 2007

  2. Index • General Comments • Interconnection projects • Actual and future Interconnection capacity benchmarking • Advantages of increasing the interconnections

  3. 1. General Comments • Gas Natural thanks the TSOs both Spanish and French for their work and effort made in the South Regional Initiatives. • We believe that the Midcat interconnection project is needed. • However, we believe that the discussion of this project at this moment (without having taken a decision to invest in the other projects of the period 2007-20011: Larrau and Biriatou) might distort the real situation as we do not have any certainty whether these investments, Larrau and Biriatou, would be built. • The efforts of the S-GRI should be concentrated, in the first place, in the investments planned for 2007-2011. Afterwards (once a decision is taken), we would be in a better position to analyse and decide on the MidCat project.

  4. CHAZELLES ETREZ LAPRADE CASTILLON SAUVETERRE GUYENNE CAPTIEUX ARCANGUES COUDURES BIRIATOU LUSSAGNET LEMONA LACQ VERGARA MONT HARO SAINT MARTIN BARBAIRA VILLAR DE ARNEDO ZARAGOZA LE PERTHUS FIGUERAS MARTORELL CASTELNOU ARBÓS ZARZA DE TAJO BARCELONA TIVISSA PATERNA 2. Interconnection projects 2.1 Infrastructures (Compulsory Planning and ERGEG documents) Future Infrastructures in Spain (Compulsory Planning 2002-2011) Spanish Infrastructures (Priority B: under certain conditions. Compulsory Planning2002-2011) Future Infrastructures in France (ERGEG 2010-2011 and CRE’s Deliberation) Infrastructures under study in France (ERGEG 2010-2011 and CRE’s Deliberation) Infrastructures under study (ERGEG 2013-2015)

  5. 2. Interconnection projects 2.2 Capacity and investments (*) The Midcat investment in France includes 235 M€ in order to reinforce the Artére du Rhône to allow the flow of gas in the South-North direction. It should be noted that the costs to increase the capacity in Larrau and Biriatou are low, specially it is compared to the benefits it provides. Fostering the development of the MidCat project, should not be an obstacle for achieving the planned increase of capacity in Larrau and Biriatou on time.

  6. 3. Actual and future Interconnection capacity benchmarking 2006 2013, considering that investments mentioned in chapter 1.2 are built.

  7. 4. Advantages of increasing the interconnections • Security of supply • Diversification of supplies. • “Back up” among infrastructures in case one of them fails. • Competition among suppliers. Competition between suppliers of the north and south Europe will develop. At the moment the areas of influence are limited to national markets in most of the cases. • Balancing • Optimizes gas infrastructures’ utilization • Facilitates trades and the creation of a regional market in the South of Europe.

More Related