1 / 17

CONSTRUCTION PROJECT SEQUENCING

CONSTRUCTION PROJECT SEQUENCING. The Sequence of a Project. Every project has a progression of activities that transform the initial ideas for the project into the reality of a structure that is usable to the client (owner). Owner Input. Project Initiation

esargent
Télécharger la présentation

CONSTRUCTION PROJECT SEQUENCING

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CONSTRUCTION PROJECT SEQUENCING

  2. The Sequence of a Project Every project has a progression of activities that transform the initial ideas for the project into the reality of a structure that is usable to the client (owner)

  3. Owner Input • Project Initiation • Something provides the driving force to decide to build something • Financing must be considered • Design and construction specifics are still very broad at this point • Selection of Design Professional • Little real progress can be made until ideas are developed

  4. Design Professional

  5. Design Professional Input • Programming – Gathering of data that will govern design. Requires a two-way exchange of information. • Owner desires • Regulation and code search • Site selection and feasibility (optional) • Zoning • Municipal codes • Easements • Drainage and other land features • Covenants

  6. City Ordinances/Covenants Gone Bad

  7. City Ordinances/Covenants Gone Bad

  8. Design Professional Input (cont.) • Development of Preliminary Design • Revisions, Changes, and Additions • Approval of Design Scheme – usually approval of the floor plan is adequate • Revisions, Changes: Design Refinement • Final Approval of Design Concept • Design Development • Production of Construction (Contract) Documents • Regulatory Review and Permitting

  9. Owner and Design Professional Input • Contractor Selection • Bidding • Awarding of Contract/Notice to Proceed • Pre-Construction Meeting

  10. Initial On-Site Operations Mobilization On-Site Mobilization & Staging Project Organization/Progress Meetings Create/Review/Finalize Project Schedule Initial Purchase/Ordering of Materials/Systems Construction Phase – Contractor Input, Management and Administration

  11. Construction Phase – Contractor Input, Actual Construction Work Process • Earthwork, Grading, Fillings, Excavation • Install Foundation System (Substructure) • Install Underground Utilities • Erect Structural Frame System (Superstructure) • Install Floor Framing System • Extend Utility Lines/Systems

  12. Construction Phase – Contractor Input, Actual Construction Work Process (Cont.) • Build/Install Envelope (Exterior Walls) • Install Mechanical Systems • Install Interior Walls/Partitions & Accessories • Connect Branch Systems to Mechanical Equipment • Install/Apply Finishes • Install Specialties/Equipment/Furnishes • Energize Mechanical Systems; Troubleshoot/Adjust

  13. Wrap-Up/Close Out Contractor/Design Professional/Owner Input • Substantial Completion; Final Inspection; Punch List • Partial use/occupancy by owner • Resolve punch list/Occupancy by Owner • Certificate of Occupancy; Operating Manuals; Training • Final Completion and Payment

  14. RESIDENTIAL PROJECT SEQUENCE • Develop a step by step sequence for a typical 2000 sf ranch style home. The home is to be built on a vacant field. • Team up with a partner to develop your work sequence. * List Sub-Contractors needed in your sequence * Remember Utilities.

  15. COMMERCIAL PROJECT SEQUENCE • Develop a step by step sequence for a 10,000 sf addition to your school. • Team up with a partner to develop your work sequence. • Submit list and compare to other groups • Are you missing anything?

  16. ROAD PROJECT SEQUENCE • Develop a step by step sequence for a typical city street and curb project. • Team up with a partner to develop your work sequence. • Submit list and compare to other groups • Are you missing anything?

More Related