1 / 40

Distribution System Efficiency Voltage Optimization

Distribution System Efficiency Voltage Optimization. Application to Rural Feeders Case Study 2010 Robert Fletcher, PhD, P.E. Utility Planning Solutions (425) 330-0628 fletcher.ups@comcast.net. V3. Rural Feeders. Overhead Rural Feeder. Rural Distribution Substation.

evan
Télécharger la présentation

Distribution System Efficiency Voltage Optimization

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Distribution System Efficiency Voltage Optimization Application to Rural Feeders Case Study 2010 Robert Fletcher, PhD, P.E. Utility Planning Solutions (425) 330-0628 fletcher.ups@comcast.net Robert H Fletcher V3

  2. Rural Feeders Overhead Rural Feeder Rural Distribution Substation Long Feeders (5 to 15 miles) Long single phase laterals Low voltage (<114V) at end of feeders Large neutral currents Large Ampere Phase unbalance Low Customer Density (<1000 kW per sq mi) Line Regulators are typically applied Feeder wire sizes are small compared to urban 2

  3. Rural Feeder Considerations • Rural feeder service infrastructure costs per customer are high compared with urban feeders. • Rural feeder voltage drops are typically higher than urban feeders and typically require line regulators. • Line Regulators are used to establish both non-VO or VO voltage-control-zones. Energy savings are not determined for non-VO control zones. • Significant system reconfiguration, phase upgrade, load balance, capacitors and line regulators are typically needed for VO on rural feeders. • All minimum system thresholds must be applied for all rural feeder VO voltage-control-zones. 3

  4. Allowed ANSI Service Voltage Range 126 – 114 V (120 V ± 5%) Volts 126 National Average 120 114 Rural and Urban FeedersAverage Customer Service Voltage Non CVR ± 2.5% With CVR • DSE and VO System Objectives • Reduce End-Use energy Consumption (reduce average service voltage) • Increase Distribution System Efficiency (lower losses) • Improve Service Reliability and Voltage Quality (increase backup capability) 4

  5. Rural Feeder DSE & VO Design Process • Gather Substation Area Data • Substation Annual MWh delivered • Feeder Peak KW and kVAr hourly load patterns • Feeder connected kVA and locations • Feeder phase ampere demands. • Voltage Control settings for Substation, Line Regulators, and Capacitors • Establish System Modeling • Feeder conductor characteristics (OH & UG) and locations • Feeder connected kVA and locations • Line phase configuration locations (i.e. single phase, two phase, three phase) • Line voltage regulator and shunt capacitor locations • Determine System Characteristics • Indentify system load factor LDF and loss factor LSF • Determine minimum allowed primary volts (on 120 V base) 5

  6. Perform Peak Load Flow Simulation – Existing System • Perform peak load flow simulation for existing system • Determine maximum voltage drops for all feeders and voltage-control-zones • Identify VO system non-compliance with operation thresholds (bal, pf, volt drop) • Determine existing system peak line loss • Perform Average Load Flow Simulation(s) – Existing System • Perform average load flow iterative simulations to determine solutions to meet (bal and pf) thresholds: • Perform Peak Load Flow Simulation(s) – with Improvements • Perform peak load flow iterative simulations to determine solution(s) to meet (volt-drop) thresholds and optimal VO design: • Determine maximum volt-drop for each VO voltage-control-zone • Determine system peak line loss with improvements (Pre-VO) • Revised lateral taps • Var Compensation (Capacitors) • Load balancing • Phase upgrades • Reconductoring • Voltage-Control-Zones (new or modified) • Switching • Load Transfers 6

  7. Perform Pre-VO Operation Assessment • Identify kVA connected for each voltage-control-zone • Determine kW load for each VO voltage-control-zone • Identify feeder volt-drop % variance for VO substation feeders • Indentify Pre-VO voltage control settings for each VO voltage-control-zone • Calculate Pre-VO Weighted Average Voltage • Perform Post-VO Operation Assessment • Indentify Pre-VO voltage control settings for each VO voltage-control-zone • Calculate Post-VO Weighted Average Voltage • Determine average change in customer voltage • Determine System VO Factor • Identify % of customers with electric space heating for substation area • Identify % of commercial load for substation area • Identify climate zone for substation area • Using ESUE Calculator, determine VO Factor 7

  8. Determine Expected DSE & VO Energy Savings • Distribution System line loss change (MWh/yr) • Connected kV A no-load loss reduction (MWh/yr) • VO Energy Savings (MWh/yr) • Perform Economic Life-Cycle Cost Evaluation • Estimate Costs • Identify Financial Factors • Determine Economic Impacts • Identify Metering and Engineering Analysis Recommendations • Installation Costs • Annual O&M Costs • Marginal cost of Energy • BPA Incentive Payment • Inflation Rates • Present Worth Factors • Utility Net Revenue Requirements • Life Cycle Cost of Energy Saved • Benefit Cost Ratio • NPV Benefits & Costs 8

  9. Rural Feeders DSE & VO Case Study • 1-15/20/25 MVA Power Transformers with four feeders • Mix of Rural and Urban Feeders in Climate Zone H2 and C2 • Average customer % electric heat is 50% • Substation LTC provides only voltage regulation – Reg Volt Set is 125 V • No Line Voltage Regulators are installed, mix of existing capacitors • Power Factor is poor due to lack of capacitors 9

  10. Perform Peak Load Flow Simulations – Existing System FDR 1 • Substation Service Area: • 3806 customers • Four Feeders • Mix of Rural and Urban Load • Service area 10 mile x 7 mile • Average 300 kW per sq mi FDR 2 Legend: FDR 1 FDR 2 FDR 3 FDR 4 FDR 4 FDR 3 10

  11. Perform Peak Load Flow Simulations – Existing System Urban Area • FDR 1 – Rural • FDR 2 – Urban & Rural • FDR 3 – Urban & Rural • FDR 4 – Urban & Rural Legend: FDR 1 FDR 2 FDR 3 FDR 4 11

  12. Perform Peak Load Flow Simulations – Existing System FDR 1 • Rural Feeders have mostly 336 kCM AAC • Urban Areas have 795 kCM AAC conductor as substation get-a-ways • Laterals are 2/0AA FDR 2 • Legend: • 795 kCM AAC • 336 kCM AAC FDR 4 FDR 3 2/0 AA 12

  13. Perform Peak Load Flow Simulations – Existing System Urban Area • Rural Feeders have mostly 336 kCM AAC • Urban Areas have 795 kCM AAC conductor as substation get-a-ways • Laterals are 2/0AA • Legend: • 795 kCM AAC • 336 kCM AAC 2/0 AA 13

  14. 120.2 4.01 13.3 117.0 6.64 10.9 Perform Peak Load Flow Simulations – Existing System 118.7 5.26 8.4 117.7 6.12 9.6 FDR 1 • Identify Non-Compliance Issues: • High Load Unbalance • Poor power factor • Low primary voltage • High voltage drops • Poor Voltage Variance • Determine peak line loss (191 kW) 121.0 3.33 6.5 FDR 2 120.3 2.24 6.8 • Legend: • 117.0Volts (lowest phase) • 6.64%Volt drop % Accum • 10.9Miles from 3ource FDR 4 FDR 3 14

  15. Perform Peak Load Flow Simulations – Existing System Urban Area • Power Factors at Peak • FDR 1 95.0% • FDR 2 95.0% • FDR 3 94.9% • FDR 4 94.9% 122.6 1.74 2.3 123.6 1.2 1.4 123.4 1.31 2.7 124.1 0.67 2.8 • Legend: • 117.0Volts (lowest phase) • 6.64%Volt drop % Accum • 10.9Miles from 3ource 15

  16. 117.0 6.64 10.9 120.2 4.01 13.3 Perform Peak Load Flow Simulations – Existing System 118.7 5.26 8.4 117.7 6.12 9.6 FDR 1 • Determine Minimum Primary Volts FDR 2 FDR 4 FDR 3 Legend: Voltages below 119.8 V 16

  17. 5. Perform Average Load Flow Simulation(s) – Existing System • Perform average load flow iterative solution(s) to identify upgrades to meet thresholds (bal, pf): • Load balancing • Phase upgrades • Revised lateral taps • Var compensation (Caps) Fixed Capacitors needed to achieve 100% power factor for average kW load conditions Average Load Flow Scenario P =41% Q = 60% Average_kVAr_Demand = Annual_kVArh / 8760 hr 17

  18. Plan New 119.1 4.93 13.1 119.0 4.99 13.3 Perform Peak Load Flow Simulations – with Improvements 2 to 3ph 1 to 2ph 121.6 2.82 8.4 119.7 4.44 9.6 3 to 2ph • Perform peak load flow to assess (volt drop): • After Balance, Phase, and Capacitor Upgrades 1 to 3ph 122.0 2.50 6.5 18 Lat Taps 122.9 1.5 6.8 Legend: OAdded 11-300 kVAr Capacitors 3 phase 18

  19. Perform Peak Load Flow Simulations – with Improvements Urban Area • Perform peak load flow to assess (volt drop): • After Balance and Capacitor Upgrades 123.0 1.33 2.3 124.1 0.73 1.4 124.1 0.79 2.7 Legend: OAdded 300 kVAr Capacitors 3 phase 124.5 0.45 2.8 19

  20. Perform Peak Load Flow Simulations – with Improvements • After adding Balanced and Capacitor upgrades, next identify system reconfigurations to meet (volt drop) thresholds • Switching • Load transfers • Reconductoring • New feeders • New voltage control zones • Consider Switching to add load to FDR 4 from FDR 2 and FDR 3 20

  21. Perform Peak Load Flow Simulations – with Improvements The Pre-VO system is how the system looks before initiating VO • Determine distribution of connected kVA • After Switching Determine peak line loss (161 kW) and power factors 21

  22. 119.1 4.93 13.1 119.0 4.99 13.3 Perform Peak Load Flow Simulations – with Improvements 121.8 2.66 8.6 119.7 4.44 9.6 • Perform peak load flow to assess (volt drop): • After Switching Upgrades 122.3 2.25 6.5 • Maximum Feeder Volt drops • FDR 1 4.99% • FDR 2 2.66% • FDR 3 1.85% 122.4 1.85 6.8 22

  23. Perform Peak Load Flow Simulations – with Improvements Urban Area • Perform peak load flow to assess (volt drop): • After Switching Upgrades 123.6 1.18 1.6 123.7 1.1 1.4 • Maximum Feeder Volt drops • FDR 4 1.57% 123.9 0.95 2.2 123.1 1.57 3.1 23

  24. Perform Peak Load Flow Simulations – with Improvements • After adding Balanced and Capacitor upgrades, next identify system reconfigurations to meet (volt drop) thresholds • Switching • Load transfers • Reconductoring • New feeders • New voltage control zones • Consider Additional Voltage Control Zones • Add VO voltage control zone to FDR 1A at 1.86% • Add VO voltage control zone to FDR 1B at 2.05% • Add VO voltage control zone to FDR 2 at 1.55% 24

  25. 119.1 4.93 10.9 119.0 4.99 13.3 Perform Peak Load Flow Simulations – with Improvements FDR 1B 121.8 2.66 8.6 119.7 4.44 9.6 • Perform peak load flow to assess (volt drop): • Identify possible locations of voltage control zones FDR 2 122.3 2.25 6.5 2.05% FDR 1A 1.55% 122.4 1.85 6.8 Legend: Accumulated volt drop% 0.0 to 1.5% 1.5 to 2.5% 2.5 to 3.5% 3.5 to 5.0% 1.85% SUB LTC 25

  26. 123.0 1.60 10.9 123.0 1.68 13.3 Perform Peak Load Flow Simulations – with Improvements 122.6 2.00 8.6 • Simulate system with new control zones for volt drop improvements • Added three New Voltage Control Zones 123.6 1.15 9.6 122.3 2.25 6.5 122.7 2.05 6.0 123.3 1.55 3.1 Legend: New Voltage Regulators Accumulated volt drop% 0.0 to 1.5% 1.5 to 2.5% 2.5 to 3.5% 3.5 to 5.0% 122.7 1.86 3.2 123.2 1.85 6.8 123.1 1.57 3.1 26

  27. Perform Peak Load Flow Simulations – with Improvements Urban Area • No Line Regulators added for in urban area 123.6 1.18 1.6 123.7 1.10 1.4 124.1 0.79 2.7 123.1 1.57 3.1 27

  28. Summary of DSE & VO Improvements 1ph to 2ph 2/0AA 1.3 mi 2ph to 3ph 2/0AA 1.3 mi • $375,000 2ph to 3ph 2/0AA 1.6 mi 1ph to 3ph 2/0AA 0.3 mi Reg & EOL Metering 11-300 kVAr Capacitors • Legend: • 795 kCM • 336 kCM 3-219A Line Regulators 18 lateral tap revisions 2/0 AA 28

  29. 7. Perform Pre-VO Operation Assessment Determine kW load for each voltage-control-zone 29

  30. 7. Perform Pre-VO Operation Assessment Determine Post-VO Weighted Average Voltage After Capacitors, Reconfiguration, and Regulators Added Assign a fixed 124 V for all new voltage control zones regulation sources 30 Reg_Set_Volt – ½ * A * LDF

  31. Determine Post-VO Weighted Adjusted Voltage After Capacitors, Reconfiguration, and Regulators Added 8. Perform Post-VO Operation Assessment Assign LDC set voltage of 120 V for all voltage control zones regulation sources Reg_Set_Volt + LDF * (½ * A + (B – A)) 31

  32. Determine System VO Factor • Identify % of customers with electric space heating for substation area 50% • Identify % of commercial load for substation area 20% • Identify climate zone for substation area H2 & C2 • Using ESUE Calculator, determine VO Factor (pu) 0.450 Change in Energy = VO Factor(pu) * Total MWh Load * Average Voltage Change (pu) 32

  33. 10. Determine Expected DSE & VO Energy Savings Distribution System Efficiency Savings Distribution System Energy Savings from VO improvements (1-(1/(1.030))2) * 1159 33

  34. 10. Determine Expected DSE & VO Energy Savings Distribution System VO Energy Savings 34

  35. 10. Determine Expected DSE & VO Energy Savings Distribution System DSE & VO Total Energy Savings 35

  36. 11. Perform Economic Life-Cycle Cost Evaluation Distribution System DSE & VO Economic Evaluation Utility Inputs 36

  37. 11. Perform Economic Life-Cycle Cost Evaluation Distribution System DSE & VO Economic Evaluation BPA Costs 37

  38. 11. Perform Economic Life-Cycle Cost Evaluation Distribution System DSE & VO Economic Evaluation Utility Benefits and Costs 38

  39. 11. Perform Economic Life-Cycle Cost Evaluation Distribution System DSE & VO Economic Evaluation Customer Benefits and Costs 39

  40. CommentsandQuestions 40 Robert H Fletcher, PLLC

More Related