Introduction • Project Overview • Scorecard • Problems and Progress • Current Work • Concerns
Overview • Ferrofluid Visualizer • Separate and audio signal into 3 ranges • Low: 20 -400 Hz • Mid: 400 – 5.2kHz • High: 5.2k – 20kHz • Magnitude of the signal is shown in the ferrofluid
Scorecard • Order all the parts: 12/1/13 • Build base & get audio input: • Base: X Audio Input: 1/20 (Goal: 1/17) • Finish building one display: X (Goal: 1/24) • Digital signal processing – In progress (1/31) • Test signal with Ferro fluid display: X (Goal: 2/3) • Testing and debugging first display: X (Goal: 2/7)
Problems • Problem 1: The Electromagnets • Problem 2: The Display and Case • Problem 3: Signal Processing
Progress • Electromagnets are being built • Display won’t take long to build • With Jared’s help we estimate under 3 days • Signal is being processed • Just not fast enough – Not real time
Current Signal Processing • Video
Concerns • Electromagnets • Speed of Signal Processing