1 / 27

Welcome to SNS The Next Large EPICS Project

Welcome to SNS The Next Large EPICS Project. A Partnership between Six National Laboratories: Argonne National Lab Brookhaven National Lab Lawrence Berkeley National Lab Los Alamos National Lab Oak Ridge National Lab Thomas Jefferson National Lab. The SNS Controls Team at ORNL.

faunia
Télécharger la présentation

Welcome to SNS The Next Large EPICS Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to SNSThe Next Large EPICS Project A Partnership between Six National Laboratories: Argonne National Lab Brookhaven National Lab Lawrence Berkeley National Lab Los Alamos National Lab Oak Ridge National Lab Thomas Jefferson National Lab

  2. The SNS Controls Team at ORNL Your local hosts: John Cleaves Richard Epps Bill DeVan John Munro Delphy Nypaver Ron Battle Coles Sibley Bill Stone Herb Strong Ernest Williams Paul Wright Pam Gurd

  3. Spallation Neutron Source Aerial/Site Plan

  4. Spallation Neutron Source Aerial/Site Plan

  5. Schedule Overview Activity FY99 FY00 FY01 FY02 FY03 FY04 FY05 FY06 1.1.9 R&D Turnover to operations BOD MCR MCR Operational 1.9.2 Global Systems BOD Start Commissioning 1.9. 3 Front End Controls Start Commissioning BOD 1.9.4 Linac Controls Start Commissioning BOD 1.9.5 Ring Controls Start Commissioning BOD 1.9.6 &7 Target & Instrument Controls Complete Target Commissioning BOD Start Cooldown Complete Cooldown 1.9.8 & 1.9.10 CF & CHL Controls Turnover to operations BOD MCR 1.9.9 PPS Legend R&D Design, Procure, Fabricate Integrated Controls Systems Master Schedule Installation & Testing Test Support Software development

  6. Status of the Project • Good News • Funding of $1.4B approved (incl $60M for Controls) • FY01 Funding of $278M approved (incl $9.5M for Controls) • 1.4 million yard of dirt moved, first concrete poured • Unresolved Issues • Pre-operations funding • Some controls staffing problems at BNL and LANL • Who is the President (and is he from Tennessee…)???

  7. An aside…

  8. We plan a system fullyintegrated under EPICS, including… • Accelerator Systems • Front End, Linac, Compressor Ring, Beamlines • ~ 50,000 channels, 160 IOCs • Front End already running under EPICS (at Berkeley) • Target System • Large and complex liquid Mercury Target • 1000 channels, 6 PLCs • Test facility already running prototypical EPICS system • Conventional Facilities • 2500 channels, 10 PLCs, 150 screens • To be done in EPICS by Sverdrup in Tullahoma • Training in January

  9. Control System Construction is distributed among all Collaborating Laboratories ICWG include JLAB 1.3 1.4 1.5 1.6 1.7 1.8 1.9 Cryo Front End Linac Ring Target Instruments Facilities Controls (JLAB, ORNL) (LBNL) (LANL) (BNL) (ORNL) (ORNL, ANL) (ORNL, CM) 1.9.3 1.9.4 1.9.5 1.9.6 1.9.7 1.9.8 1.9.10 1.9.9 Front End Linac Ring Target Instrument Facilities Cryo Personnel Controls Controls Controls Controls Controls Controls Controls Safety 1.9.2 “Global” Controls: (Network, Timing, Protection, Control Room, Labs, Applications, System Software) 1.9.1 Integration & Management

  10. Total Controls ManpowerConstruction and Operations

  11. Where we are now • Controls Group Staff of 10 here at ORNL • EPICS Systems running Target Test Facility here and Front End Systems at Berkeley • Application Development Environment here at ORNL • Distributed CVS – accessible by all the partners • Prototypical Environment running in lab here • MVME 2100 PPC, EPICS 3.13.3, Tornado II, DM2K • ControlLogix PLC • ControlNet over EtherNet Driver

  12. The SNS Control Room

  13. Some things we have agreed upon… • Site-wide Device and Signal Naming Convention • ControlLogix PLCs (Allen-Bradley) • ControlNet over EtherNet Driver • Standard Cabinets • PowerPC IOCs (MVME 2100) • VME64x (Bid on the street) • Including Utility Board • Linux Environment where appropriate • Oracle, but…

  14. … and some we have not. • Display Manager • DM2K (The current “official” standard) vs EDM • Database creation • Will use Oracle, but the process is uncertain • Capfast?? • Templates? • We hope this meeting will help with these decisions

  15. Some EPICS Developments are needed • Large Array Support • Needed for Diagnostics • Long PV Names • We could bump up against the current limit • Variable String Size • Multipriority Channel Access • Needed for Diagnostics and Machine Protect • SNS will fund some of these Core developments, but we will need help from the community…

  16. Summary • Jobs available • Many issues the EPICS Community can help us with. • Jobs available • We hope to contribute to EPICS • Jobs available • We look for help and advice from this meeting • Jobs available

  17. Front End – A Highly Complex System with Several Major Subsystems and Critical Functions The Front End has relationships with all systems: rf, high voltage, diagnostics, alignment, controls, magnets, power supplies, pulsed power, physics, vacuum, Cesium, radiation. Create 65-mA H- ion beam Ion Source/LEBT Accelerate beam to 2.5 MeV RFQ Chop beam into mini-pulses LEBT/MEBT Match 52-mA beam into DTL MEBT

  18. 402.5 MHz, 2.5 MW klystron 805 MHz, 5 MWklystron 805 MHz, 0.55 MW klystron Layout of Linac RF with NC and SRF Modules DTL CCL RFQ (4) (6) (1) 86.8 MeV 2.5 MeV 972 MeV SRF, ß=0.61 186 MeV SRF, ß=0.81 379 MeV HEBT (33) (59) (2) from CCL 1 59 (92 total) 1 33

  19. Ring Lattice 2000P-03550/jhb

  20. WBS 1.9 Scope includes control of all major subsystems as well as Personnel Safety and “Global Systems.” SNS Integrated Control System OPIs IOCs (1.8.3.4) ROUTER FILE SERVERS (EPICS FILE SERVER, ARCHIVERS, ETC.) (1.9.2.4) (1.9.2.4) (1.9.2.4) (1.9.2.4) (1.9.2.4) MAIN CTRL. RM. EQUIP. FRONT END CTRL. RM. EQUIP. RING CTRL. RM. EQUIP. OTHER LOCAL CNTL STNS TIMING SYSTEM MASTER (1.9.2.2) BEAM PERMIT SYSTEM (1.9.2.3) CABLES (1.9.2.2) RACEWAYS (1.8.X) 1.9.2.1 CONTROL SYSTEM NETWORK (EQUIPMENT AND NODE CABLING) 1.8.4 POWER AND COMMUNICATIONS SYSTEMS (BACKBONE CABLING) CABLES (1.9.2.3) RACEWAYS (1.8.X) CONVENTIONAL FACILITIES IOC’S (1.9.8). PPS IOC (1.9.9) FAST PROTECT OUTPUT HARDWARE (1.9.2.3) FRONT END CONTROL SYSTEMS (1.9.3) LINAC CONTROL SYSTEMS (1.9.4,10) RING CONTROL SYSTEMS (1.9.5) TARGET IOC’S (1.9.6) EXPERIMENT CONTROL SYSTEMS (1.7) PPS PLCs (1.9.9) C.F. PLCs (1.8.x) RACEWAY SYSTEM (1.8.x), TYPICAL CABLE SYS. (1.3.x) CABLE SYS. (1.7.x) CABLE SYS. (1.5.x) PLCs CABLE SYS. (1.6.8) CABLE SYS. (1.4.x) CABLE S (1.8.x) CABLE S (1.8.x) (1.9.6) PERSONNEL PROTECTION SYSTEM SENSORS &CONTROL ELEMENTS, ETC. (1.9) FRONT END SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.3) LINAC SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.4) RING SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.5) TARGET SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.6) EXPERIMENT SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.7) CONVENTIONAL FACILITIES SENSORS & CONTROL ELEMENTS, CONTROLLERS, ETC.(1.8) EQUIPMENT PROTECTION SYSTEM HARDWARE (1.9.2.3) TIMING SYSTEM SLAVE HARDWARE (1.9.2.2)

  21. Subsystem interfaces arevaried and complex Ethernet – TCP/IP Channel Access Protocol PC IOC VXI IOC VME IOC PC IOC VME IOC Negotiated Exception Examples: Cryoplant Conven. Facilities Default Interface Examples: Injector Default Interface Examples: Beamlines Vac. Sys. Default Interface Example: HPRF PLC PLC Negotiated Exception Examples: LLRF Diagnostics “Packaged” PLC System PLC Embedded PLC System Equipment Equipment Equipment Equipment PLC Equipment IOC = Input.Output Controller PLC = Programmable Logic Controller PC = Personal Computer

  22. Proposed Baseline for full operations (26) 2 Management GL Secretary 4 8 12 Hardware Design Eng Tech Pool (7) Safety Eng (2) Techs (2) Software EPICS System Programmers (3) Application Engineers (7) Network, Sysadmin, Database (2) Total is 26* *APS is 29 for same scope

  23. The exact number of IOCsdepends upon Title II design. Ethernet - TCP/IP RF System Cavity System Control System HPRF IOC ControlNet PLC KA KA KB HPRF System KA KB LLRF IOCs LLRF IOCs KA KB Power Supply KA KB KA KB (50 Channels) PLC PLC X 5 X 6 Transmitter Transmitter (125 Channels) (125 Channels) Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron 11 Cavities

  24. Baseline Staffing Plan for Controls

  25. Ring Straight Section Functions • Separate functions in each straight • Four straights: 12.5 m; 2 x 6.85 m • Injection modules • Two-stage collimation • 3 (h=1)+1 (h=2) interchangeable RF cavities • Beam-in-gap kicker • Empty section for future use

  26. Spallation Neutron Source Aerial/Site Plan

  27. Control System Systems and Functions • Data Acquisition and Control • 160 distributed Input Output Controllers with 50,000 signals • Timing and Synchronization • Synchronizes choppers, kickers, rf systems and beam diagnostics • Time stamps all acquired data to microsecond accuracy • Machine Protection • Turns off beam in <20usecs for beam loss) or equipment failure • Control System Network • Isolated Control system network includes >20 switches • System and Application Software • Communications, databases, EPICS core software, “engineering applications” and the human interface • Control Room • Operator Consoles, Personnel Access control, network hub, computer servers, timing distribution etc

More Related