1 / 32

FDOT R/W Guidelines Use of License Agreements

FDOT R/W Guidelines Use of License Agreements. Michael F. Sexton, P.E., P.S.M. Sexton Engineering Associates, Inc. Jeffrey M. “Rusty” Sievers, P.E. GAI Consultants Shirley Martin GAI Consultants. FDOT Right-of-Way Instruments. Fee Simple Right-of-Way Perpetual Easements

fcombs
Télécharger la présentation

FDOT R/W Guidelines Use of License Agreements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FDOT R/W GuidelinesUse of License Agreements Michael F. Sexton, P.E., P.S.M. Sexton Engineering Associates, Inc. Jeffrey M. “Rusty” Sievers, P.E. GAI Consultants ShirleyMartin GAI Consultants

  2. FDOT Right-of-Way Instruments • Fee Simple Right-of-Way • Perpetual Easements • Temporary Easements • License Agreements

  3. FDOT R/W Design Bulletin 14-08

  4. FDOT R/W Design Bulletin 14-08 Use of License Agreements This bulletin establishes a Department policy to use license agreements as the default method for harmonization of driveway connections and removal of roadway features found to be outside of the right of way.

  5. FDOT R/W Guidelines Right of Way is real property or an interest therein, donated or acquired by purchase of condemnation, to accommodate transportation improvements. Fee simple is the strongest interest available to the Department and is sought for most permanent highway facilities.

  6. FDOT R/W Guidelines Fee (Simple) Title is the largest estate and most extensive interest that can be enjoyed in land. The Department will seek to acquire fee title to all lands on which a permanent structure or improvement is to be placed and maintained. Parcels acquired for mitigation or exchange should also be acquired in fee. Land includes airspace, surface or subterranean areas that may be acquired independently.

  7. FDOT R/W Guidelines Perpetual Easements (perpetual right to use over, under or through the property of another) are used when permanent structures or improvements are to be constructed and maintained on parcels where acquisition of fee title would be impractical, i.e., when acquisition of the fee would cause excessive severance damages due to green area or setback requirements or where underground structures are to be constructed which will not impair the surface use of the land.

  8. FDOT R/W Guidelines Temporary Easements (a temporary right of use over, under or through the property of another) are used when it is necessary to temporarily occupy a parcel for a specific purpose such as construction of improvements requisite of the project, construction of temporary detours, stock piling materials or parking equipment. A Temporary Easement may also be necessary when it is determined that reestablishing access causes a compensable impact to the use of the abutting land or causes a safety issue due to a change in grade.

  9. FDOT R/W Guidelines No improvement which requires maintenance by the Department beyond the term of the easement can be constructed on a temporary easement.

  10. FDOT R/W Guidelines License Agreements are used to gain access to adjoining properties for sloping, grading, tying in, harmonizing and reconnecting existing features of the licensor’s property with the highway improvements to be constructed. This work is for the benefit of the property owner.

  11. FDOT R/W Guidelines The Department does not compensate for license agreements. If the owner refuses to execute the agreement, the Department will not perform the work outside of Department right of way.

  12. License Agreements FDOT R/W Guidelines Licenses are not real property interests. A license, with respect to real property, is a privilege to go on the premises for a certain purpose but does not vest any title in the license.

  13. Procedures for Establishing R/W Requirements The procedures for addressing R/W requirements require engineering analyses, economic comparisons and professional judgments. Consultation with the District R/W Surveyor and District R/W Manage is required. One excellent method of providing the consultation is the “R/W Partnering” concept with all parties that have a vested interest participating in the decision making process.

  14. Procedures for Establishing R/W Requirements Alternate design studies will be required in many locations to determine if additional R/W should be purchased, a retaining wall constructed or modified slopes and barrier system should be considered.

  15. Procedures for Establishing R/W Requirements A reasonable estimate of R/W costs or damages expected must be obtained from the R/W Office in order to make such a design study. Alternate construction methods may be shown on the plans as preferred alternate methods.

  16. Procedure for Establishing R/W Requirements The most economical means of constructing the project should always be the objective. The designer must design the highway facility within the existing R/W, obtain a license agreement, or request acquisition of R/W to accommodate project elements.

  17. Process for Establishing Right of Way Requirements Establishing right of way requirements is a design process, but requires close coordination with other functions that have input to the project development and design of the project.

  18. Process for Establishing Right of Way Requirements Generally, the R/W needs-determination will involve Roadway, Bridge and Drainage Design, Permits, Utilites, R/W Appraisers, R/W Mapping and Legal Functions. The design project managers role as lead coordinator is especially critical.

  19. Procedures for Decision Making To assist in the decision process related to R/W requirements and instruments to be used, guidelines from the Office of Right of Way may be used during the joint review process. Close coordination with the District Right of Way Office and the Office of General Counsel is required during the decision-making process.

  20. Guidelines for Decision MakingFee Simple Ownership Fee Simple R/W purchase should be used when the following conditions exist: a. The planned improvements to the property owner’s land are required as a part of construction of the transportation facility. b. The improvement on that land must remain in place as a part of the facility; and, c. Periodic re-entry to the property is required for maintenance or repair.

  21. Guidelines for Decision MakingPerpetual Easement Perpetual Easements may be considered as an alternative to fee simple purchase in the R/W process if the owner may continue to enjoy some benefits of the property without impairing the Department’s use and the total acquisition costs to the Department are less than the cost of acquiring fee.

  22. Guidelines for Decision MakingTemporary Easements Temporary Easements should be used under the following conditions: a. When it is necessary to temporarily occupy a parcel for a specific purpose such as construction of improvements requisite of the project, construction of temporary detours, stockpiling materials or parking equipment. b. When it is determined that reestablishing access creates a compensable impact to the use of the abutting land;

  23. Guidelines for Decision MakingTemporary Easements (Continued) c. Where grading, tying-in, harmonizing, and/or connecting access point is required to maintain the safety and design of the facility. d. The contemplated improvements or uses of the property owner’s land are required only during the period of construction of the transportation facility;

  24. Guidelines for Decision MakingTemporary Easements (Continued) e. Removal or alteration of the improvements to the property owner’s land subsequent to construction would not be detrimental to the facility; and, f. After construction is complete, there will be no need for periodic re-entry onto the property by the Department for maintenance or other purposes.

  25. Guidelines for Decision MakingLicense Agreements A License Agreement is the default method for driveway harmonization; Use of a Temporary Construction Easement must be justified in terms of project integrity or cost or potential impact of the project on the property.

  26. Guidelines for Decision MakingLicense Agreements License agreements should be used only if the following conditions can be met: a. The improvements or changes contemplated have no compensable impact to the use of the property, and are for the benefit of the property owner; and b. None of the improvements are required for the construction, operation and maintenance of the transportation facility and removal of , or change to the improvements will not be detrimental to the facility.

  27. FDOT Driveway Connection Permit

  28. FDOT Driveway Connection PermitGeneral Provisions All approved connection(s) and turning movements are subject to the Departments continuing authority to modify such connection(s) or turning movements in order to protect safety and traffic operations on the state highway or State Highway System.

  29. FDOT Drainage Connection Permit

  30. FDOT Drainage Connection PermitPermit General Conditions The Department reserves the right to modify or remove the drainage connection to prevent damage or in conjunction with road improvements.

  31. License AgreementsPro’s and Con’s Discussion

  32. FDOT R/W Guidelines QUESTIONS?

More Related