Mesyuarat Tahunan Jurutera Mekanikal 2016 5-7 th September 2016

INSIGHT INTO NEW TESTING , ADJUSTING, BALANCING & COMMISSIONING (TABC) SPECIFICATION OF AIR CONDITIONING AND MECHANICAL VENTILATION SYSTEM. Mesyuarat Tahunan Jurutera Mekanikal 2016 5-7 th September 2016. Contents. Why do we need to improve testing specification?

freddym
Télécharger la présentation

Mesyuarat Tahunan Jurutera Mekanikal 2016 5-7 th September 2016

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INSIGHTINTO NEW TESTING , ADJUSTING, BALANCING & COMMISSIONING (TABC) SPECIFICATION OF AIR CONDITIONING AND MECHANICAL VENTILATION SYSTEM MesyuaratTahunanJuruteraMekanikal 2016 5-7th September 2016

  2. Contents • Why do we need to improve testing specification? • Insight into new specification. • Conclusion

  3. Why Higher expectations from clients/user on the building system performance, extensive performance verification is required. Operational issues arises due to absence or inadequate testing and commissioning procedures. Scope of testing in current specification need to be revised to address above issues.

  4. Improved Specification Features Overall scope of testing and commissioning • Carried out in 5 stages i.e Pre-delivery, Delivery, Installation and Functional Performance Test, Post Occupancy Performance Assessment Enhance type of inspection and testing • Comprehensive and objective based test requirements and methods. Tools Improved measuring tools specification including accuracy and calibration requirement. Procedures • Inclusion of ITP plan submission and implementation. • New Post Occupancy Performance Assessment. New document structure • More structured and easy to use.

  5. Why do we need Testing, Adjusting, Balancing and Commissioning To verify that delivered materials are as per approved specification and good physical condition. To verify that the installation works are carried out in accordance with specification and good engineering practises. To verify that the performance in terms of functionality, safety, maintainability and operation ability of the installed equipment/systems meet the specified design intent through a series of tests and adjustments. To ensure that all test result are systematically recorded and verified prior to system commissioning. 1 2 3 4

  6. Testing, Adjusting, Balancing and Commissioning Phases Introduced into new specification Inspection and Testing Plan

  7. INSPECTION AND TESTING PLAN List out all TABC works required in the specification with specified scope and boundaries. WHAT ? WHO? Responsibility to conduct and verify test shall be clearly stated. TABC work schedules shall be integrated into main project schedules. WHEN HOW TABC method statements shall consists of TABC procedures, responsibility, necessary tools, measuring equipment and accuracy, consumables and acceptance criteria.

  8. Sample of ITP

  9. Pre Delivery Verify performance of major equipment against specification or regulation where on site performance verification is not feasible. Major equipment include Chillers and Switchboard Switchboard Factory Test Chiller Factory Performance Test

  10. Chiller Factory Performance Test 1 To verify published chiller capacity at rated or design condition. 2 To verify full load or part load performance at rated or design conditions. In accordance with relevant standard e.g AHRI 550/590 or MS 2449

  11. Chiller Factory Performance Test How to verify published data?

  12. Chiller Factory Performance Test Require testing at rated conditions Field testing at rated conditions is nearly impossible task

  13. Switchboard Test Routine tests on the switchboard shall be carried out before delivery to site. Test Results or Certificate duly certified by Competent Person as in Electricity Regulations 1994 shall be issued for every switchboard supplied and installed.

  14. Delivery Verify that delivered materials are as per approved materials and good physical conditions. Materials delivered to site shall be free from defects and adequately protected against harsh site conditions.

  15. Installation • To verify that the installation works are carried out in accordance with specification and good engineering practises. Cable Continuity Test Hydrostatic Pressure Test Duct Flushing Pipe Flushing and Water Quality Test Only for above 750 Pa (3.0 in wg) only Support and Hanger Load Test Duct Leak Test LV Motors, Switch Gears and Cabling Insulation Test Pipe Gradient Test

  16. Functional Performance • To verify that the performance in terms of functionality, safety, maintainability and operation ability of the installed equipment/systems meet the specified design intent through a series of tests and adjustments.

  17. Pre Functional Performance Ensure proper distribution of supply air as per load or design – 10% flow tolerance Air Balancing Water Balancing Ensure proper distribution of chilled/condenser water as per load or design – 10% flow tolerance Accuracy Test Ensure measurements accuracy prior to functional performance test

  18. Functional Performance 7 functional performance test series, 28 no of test 11 tests Chiller Plant 1 5 tests Air Handling Unit and Fan Coil Unit 2 3 tests Switchboard and Power Supply 3 Air Distribution 3 tests 4 Infiltration 1 tests Wall Insulation and Sprayed PU Foam Insulation Effectiveness 5 6 1 tests Mechanical Ventilation 4 tests 7

  19. Commissioning Process of achieving, verifying, and documenting that the performance of facilities, systems, and assemblies meets defined objectives and criteria. Handing Over Documents 1 - Test Report complete with fully verified Inspection checklist and Test Forms. - Air Balancing and Water Balancing Report. - Defects List - Operation and Maintenance Manual which includes - As-Built drawings - Schedule of System Familiarization Program to end users. System Familiarization Program 2 • - Overview of design concept and objectives • - Operation instruction & competency requirement • Maintenance procedures • - Critical operating parameters monitoring and • - Emergency response & safety procedures. • - Environmental protection procedures.

  20. A survey carried out to evaluate user experiences with the air conditioning and ventilation system from comfort, operation ability or any other related problems. Data will be used for continues improvement. Post Occupancy Evaluation

  21. Conclusion • This new testing, adjustment, balancing and commissioning (TABC) enhanced specification will contribute to comprehensive system performance verification. • Only covers mechanical system, other building systems and architectural design that affect our system performance. e.g space layout, major openings shall also be looked into. • Series of training to familiarize CKM designers and construction supervisory teams will be conducted in the near future. • Any feedback for future improvement are most welcome. Thank You