1 / 27

Overview

Overview. Consolidation. Consolidation projects for SPS LIU-SPS Conclusions Acknowledgements B. Salvant with ABP colleagues B. Goddard and M. Meddahi T. Bohl with RF colleagues K. Cornelis with OP colleagues BI colleagues. Consolidation #1. SPS BTV rad-hard electronics

freira
Télécharger la présentation

Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview Consolidation • Consolidation projects for SPS • LIU-SPS • Conclusions • Acknowledgements • B. Salvant with ABP colleagues • B. Goddard and M. Meddahi • T. Bohl with RF colleagues • K. Cornelis with OP colleagues • BI colleagues LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  2. Consolidation #1 • SPS BTV rad-hard electronics • BA1 (injection), BA2/BA80 (North Area) • New cables foreseen during LS1 • Plans: • Like now but renovated (acquisitions possible) for 2014 • TT2 & TT10 BPM electronics • Operational since 2012 start-up • Request for CT/MTE beams implemented • Radiation-related issues being followed (as for PS-TT2) • SPS Closed-orbit (MOPOS): • Funding covers electronics (LIU details) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  3. Consolidation #2 • SPS BLM systems • Funding for new electronics (see LIU details) • SPS Wire-scanner systems • Funding for new mechanics (LIU details) • New: North area target instrumentation • Replace target boxes (TBIU/TBID) during LS1 • Funding missing • New SPS IN-OUT electronics -> PLC • MIL1553 eradication during LS1 (BE/CO priority) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  4. LIU-SPS work-units • Requests following 2011 SPS LIU review: Minutes: https://edms.cern.ch/file/1138788/1/MinutesBIReview-310311.pdf Relevant observables identified: • Intensity (Fast and DC) • Transverse beam size • BLMs (‘Diamond’ and ‘IC’ detectors) • Satellite observation • Gated Tune-meter • Head-tail instability observation • Closed-orbit and trajectory LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  5. Ring (DC) Intensity #1 Quantify total intensity transmission during SPS cycle • Specifications: • Intensity range: 1e8 to 1e14 • Sampling: 200Hz • Accuracy: 1% of measured value (>~1E11 charges) • Resolution: • 1E8 (1sec integration) • 1.5E9 (5msec integration) • Analogue rise-time (10%->90%): 3msec LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  6. Ring (DC) Intensity #2 • Status: • Present BCTs: • ~5E8 to 1.4E14 charges covered by two devices • Expensive maintenance cost (Bergoz) • Plans: • Install new detector(s) (LSS5) during 2012 T.S. (NA61 interlock funding) • Evaluate detector and electronics (2012) • Decide on longer-term strategy during 2013 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  7. Ring (Fast) intensity #1 Quantify bunch intensity and turn-by-turn transmission • Specifications: • Bunch by bunch (ie 25nsec/40MHz) (200MHz request not covered presently) • Turn by turn for at least 1000 turns • Intensity range: 1e9 -> 5e11charges/bunch • Resolution : 1% loss turn to turn (total intensity) • Accuracy: • Bunch intensity value known within 5% (max. 10% for low intensity beams) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  8. Ring (Fast) intensity #2 • Status: • Not able to distinguish bunches at 40MHz • Beam position dependency • Bunch length dependency • Plans: • Turn-by-turn acquisition ready (OP application pending) • Investigate position in SPS ring allowing for shorter cables (LSS5 candidate) • Investigate ICT techniques on the LHC (LS1) and then decide for SPS Bandwidth limit (50nsec LHC beam) Bunch length effect (RED curve) (DC blue) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  9. Ring (Fast) intensity #3 Qualification of beam satellites • Specifications: • Time resolution to be specified • Intensity resolution: 0.1% of ultimate bunch • Status: • Investigations into using synchrotron light • BSRT system not operational since several years • Would likely have to integrate over long time (wiggler).. • Plans: • See with BE/RF reusing WCM as detector (as in PS) • Attempt revamp of SPS BSRT during LS1 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  10. Wire-scanners #1 Quantify beam size at specific times in the SPS cycle including bunch-by-bunch (@40MHz) • Specifications: • 5% accuracy on beam size (above 1E11 charges) • Bunch by bunch acquisition (25 nsec slot) • Beam size consistency between IN and OUT scans (for same conditions in same cycle) • Scanners at optimal positions (beta-max H/V) • Mainly layout issue • Finding range for linear behaviour difficult (as seen in PS complex) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  11. Wire-scanners #2 • Status: • Mechanical (potentiometer) issues believed to be main error source • 40MHz acquisition available (MSWG April 2012 K. Cornelis) • Linearity (PM) issues to be followed (guidelines) • Plans for new wire-scanner system: • VIA to work on electronics (start October 2012) • PhD student to work on position determination • Install more precise (Fast Vacuum) BWS prototype in the SPS during LS1 (exact plane/location and time-scales to be discussed) • Launch series production allowing all others to be installed during LS2 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  12. Beam size evolution #1 Quantify evolution of transverse beam size during the SPS cycle • Specifications: • Detect 5% changes in beam size • Bunch by bunch (if possible) • 10 msec sampling intervals (if possible) • Status: • Two monitors with dipoles installed in the SPS (LSS5) • Issues seen on BGI system when last used (MSWG) • Plans: • New optics/electronics installed • Software design and BI commissioning during 2012 • Images integrated over 20msec • Hope to have systems operational during 2012 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  13. Ring beam size #3 Qualify betatron and dispersion matching in both planes at injection by measuring turn-by-turn beam size variations of circulating beam • Specifications: • Turn-by-turn for single bunch • Acquisition of 100 turn profiles • Two separate monitors needed • H, V and skew with zero and high dispersion • Status: • BTV screen with read-out installed (LSS5): • Issue with screen breakage to be understood • Plans: • Feasibility study in the LHC during 2012 • Beam tests in the SPS to be discussed • Study to be made for the SPS integration (LS1) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  14. Ring Beam Size #4 Gated beam size checks before extraction SPS for BQM • Specifications: • Acquisition covering ~1us integration windowsto quantify differences (head and tail of PS batches) • Single acquisition: 100 ms before 1st extraction • H and V planes (low Horizontal dispersion) • Connection to BIS (eventually) • Status: • SPS BSRT system not operational since several years • Plans: • Investigate possible system upgrade during LS1 • Provide single image (20msec) as of 2014 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  15. Ring Beam Loss #1 Quantify losses during the SPS cycle and interlock (dump/inhibit)for existing IC BLMs • Specifications per monitor: • Sum of loss signals over cycle • Evolution (@1KHz ?) of loss signals over cycle • Capture buffer 2000 samples (20usec) from time T • 3 integration times for interlocking (20usec, 1msec, 20msec) • Status: • Existing systems with software and hardware interlocks • Design electronics (rad-hard ASIC) during 2012 (HL-LHC funding) • Plans: • Expect to use fibres foreseen for new MOPOS • Lab and radiation tests during 2012/LS1 • Existing systems remain operational until at least LS2 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  16. Ring Beam Loss #2 Qualify Fast losses at SPS extraction (and injection) • Specifications: • 1 GHz sampling for 100’000 points (200MHz enough?) • Flexible acquisition start time (one measurement per cycle) • Status: • Diamond detectors (identical to LHC) installed: • MSE-41871 in SPS LSS4 (SC/RP refused installation on TPSG) • TPSG-61776 in SPS LSS6 • Acquisition systems (scopes) installed for functionality tests • Analogue signals to be better understood (also for LHC) • Plans: • Look for more suited acquisition systems • Continue studies and work towards operational integration • Injection detector installation during LS1 (SC/RP ..) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  17. TT10 Beam Loss #1 Quantify beam losses in TT10 • Specifications: • List of new monitors being prepared • 2usec resolution to resolve PS turns (CNGS/SFTPRO beams) (LINAC4 electronics) • Funding and expected resolution to be clarified • Plans: • Finalise monitor locations (2012) • Plan installation of cables etc (LS1/LS2) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  18. Closed-orbit and trajectory #1 Measurement of orbit and turn-by-turn positions for existing (mainly) shoe-box SPS BPMs (~250) • Specifications for all BPMs: • Orbit acquisition @1KHz (up to 60 sec cycles …) - Single gate per SPS turn • First 50 turns for (ALL?) injection(s) – Several gates per turn (MAX?) • Capture: 10k turns starting from selected time (Same gate as orbit?) • Accuracy: 0.5mm (excluding alignment errors) • Resolution orbit mode: 0.1 mm (0.4 mm for single bunches) • Resolution trajectory mode: 0.4 mm (1.0 mm for single bunches) • Position interlocking (extraction and ring) preferablywithoutgating LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  19. Closed-orbit and trajectory #2 • Statusfor existing system (MOPOS): • Allows single gate per SPS turn • Performance issues dominated by long cables • Also used for extraction position interlock LHC/CNGS in LSS4/LSS6 • Replacement systems not yet declared operational by OP • Long-term maintenance/reliability issues • Status for new system: • Radiation testing of electronics (PSI and CNGS) on-going (100krad required) • Investigating two solutions (fibres and coax-cable transmission) • Fibre solution (believed to give optimal performance): • Large fraction must be installed in LS1 with completion in LS2 • LIU funding (2MCHF) required (2012/2013 ++) • Coax solution (mainly for tunnel radiation concerns): • Influence for SPS Ring BLMs (upgrade relies on fibres available) • Limited upgrade possibilities LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  20. Closed-orbit and trajectory #3 • Plans (old and new system): • Replacement of 6 (BPA/BPD) ‘bad’ pick-ups for improved performance during LS1 • Temperature sensors being installed in SPS tunnel for logging (2012) • Electronics production during 2012/LS1 • Tunnel installation during LS1 • Beam testing: • 2012 - few spare channels in LSS4) • After LS1 – at least BA5 (pending EN/EL commitment) • Possibly 50% of SPS covered (in parallel to old system) LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  21. Bunch-gated Tune-meter Measure single bunch betatron tunes to quantify collective effects • Specifications: • Bunch-slot selection (25nsec resolution) • Single minimum - preferably several/all • Accuracy: • 10-4 for 1000 turns (reduced for single bunches?) • Resolution: • 10-5 for 1000 turns (reduced for single bunches?) • Status: • Old tune meter (BOSC) allows selecting LHC batch • OP diagnostics could be improved • LHC BPMs (LSS5) allow bunch-by-bunch position • Reduced accuracy/resolution tune measurements • Limited number of bunches*turns • Plans: • LHC BBQ prototyping to be done in the LHC LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  22. Head-Tail instability observation #1 • Qualitative observation of coherent oscillation modes • Specifications: • Selectable bunch (25nsec slot) • Bandwidth: • Sampling: 20GHz • Analogue: 6 GHz • At least 1000 consecutive turns (H & V) at selected time in cycle • Status: • Present system works (one selected plane) • Bunch length and intensity range issues (pickup and cables) • Plans: • Purchase more performing acquisition system • 2012 (will be difficult to test anything) • Wait until early 2014 ? (~250 KCHF) • Investigate alternative pickup and signal transmission systems LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  23. BI plan for the SPS consolidation LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  24. BI plan for the SPS-LIU #1 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  25. BI plan for the SPS-LIU #2 LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  26. Spending profile • Open Issues: • Missing ~800kCHF for SPS fibre installation LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

  27. Conclusions • Consolidation/LIU review very useful for the SPS (agreement on solutions/milestones etc) • Agreement to be reached about priorities and specifications • Need funding for renovated TBIU/TBID • Long time-scales for big systems (BLM/BPM) • BI to ensure operation of old systems until LS2 • Spending profile to be updated • Specifically for funding of fibres LIU & Consolidation activities for SPS Lars K. Jensen BE/BI

More Related