ISO Tariff Language Update for Generator Interconnection Capability Identification

fritz-oconnor avatar
6 diapositives · 156 Views · Nov 06, 2014

This document clarifies the establishment of resource capability for existing generators in the context of interconnection agreements and approvals. It outlines a hierarchy to identify interconnection capability, emphasizing the importance of summer and winter MW quantities expressed in agreements or approvals. The proposed language aligns with ISO implementation of grandfathering provisions. Definitions and examples using summer ratings are provided for interconnection capability identification.

ISO Tariff Language Update for Generator Interconnection Capability Identification - slide 1
01 / 6ISO Tariff Language Update for Generator Interconnection Capability Identification
1 / 17

Télécharger la présentation

ISO Tariff Language Update for Generator Interconnection Capability Identification
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Tariff Language Clarification regarding the Establishment of Resource Capability for Existing Generators Al McBride Project Manager – System Planning

  2. Hierarchy to Identify Interconnection Capability • The proposed hierarchy language is unchanged from earlier ISO presentations and committee discussion regarding the appropriate hierarchy • The proposed hierarchy language is consistent with the ISO implementation of the grandfathering provision

  3. Hierarchy to Identify Interconnection Capability • The interconnection capability of the generator shall be: • The summer and winter MW quantities expressed in the Interconnection Agreement (“IA”), where available • If there is no expression of MW quantities in an IA then the interconnection capability will be the summer and winter MW quantities expressed in the I.3.9 or 18.4 or 10.4 approval for the generator • If both IA and I.3.9 exist and differ then the lower will govern • If the above quantities do not exist, the interconnection capability will be the higher of the following: • The highest recorded summer and winter Claimed Capability Audit – Establish test result for the generator; or • The maximum claimed capability for the generator as recorded in a CELT report

  4. Interconnection Capability - Definitions

  5. Interconnection Capability Identification: Examples using Summer Ratings *Summer Demonstrated Capabilities are stated at 90degF for temperature-corrected units

  6. Questions