Design and Construction of Main & Crescent Bridges at Palm Jebel Ali, Dubai
The Main and Crescent Bridges project, located in Palm Jebel Ali, Dubai, involves the design and construction of key transportation infrastructure. The project, managed by Nakheel, spans a contract amount of approximately $350 million and entails a construction period from April 2007 to November 2010. The project features several bridges with dimensions of up to 1,450 meters and multiple lanes to accommodate heavy traffic, and utilizes advanced construction techniques such as prefabrication and steam curing.
Design and Construction of Main & Crescent Bridges at Palm Jebel Ali, Dubai
E N D
Presentation Transcript
Design and Constructionof Main & Crescent Bridges 9th Oct. 2008
Location Palm Deira The World Palm Jebel Ali Palm Jumeirah Dubai Waterfront
C1 L=380m 3Lanesx2 C3 L=380m 2Lanesx2 C4 L=380m 3Lanesx2 M1 M3 L=1,200m 4Lanesx2 L=1,450m 4Lanesx2 Site Layout A = 11,600,000 m2 Frond Trunk PC Yard Site Office Nakheel Site Office
Contract Project Name Main and Crescent Bridges Project, Palm Jebel Ali Construction Period 2007.4.1 ~ 2010.11.30 (44months) Contract Design & Build (Lump Sum) Contract Amount US$ 350,286,921 (AED 1,285,553,000) Employer NAKHEEL Consultant PARSONS PTG Halcrow International Partnership Designer COWI 3rd Party Checker
Main Bridge 23.5m 23.5m
Crescent Bridge 19.35m 19.35m
Work Programme 32%
PC Production / PC Yard Layout Stock yard 2 1 5 3 Office 4 6 Workshop PC Yard area : 700m x 200m 1 2 3 Seg Transporter Steam Curing Chamber Rebar Jig Casting Cell (Mould) 4 5 6 Launching Girder Batch Plant Steel Shop Gantry Crane
PC Production / PC Yard Overview Gantry Crane Batching Plant Workshop Casting Mould Match Casting Steam Curing Rebar Jig Manipulator
M1 M3 1500m 850m 800m 1600m PC Erection / Transport Transporter Carrying Path - Self weight of transporter : 44ton - Carrying capacity : 170ton - Length : 27.1m - Width : 4.68m - Carrying speed : 3km/hr Hydraulic cylinder 27.1m Transporter
PC Erection / Launching Girder Lateral View Winch Group 127m (1023 ton) Plan View Typical Section Image of Launching Girder
Progress / Manpower Daily Manpower On Site Manpower Nationality 719 Manger / Engineer 90 Bangladesh 219 India Supervisor / Foreman 55 84 Operator 48 Thailand Electrician / Mechanic 25 32 Pakistan 35 Philippines Worker / Etc. 1,128 271 China / Etc. 1,353 1,353 Worker Camp Tool Box Meeting Refreshing Shelter
Progress SEGMENT PRODUCTION YARD SEGMENT TRANSPORTATION SEGMENT ERECTION MAIN BRIDGE 1 SPAN 24
Progress CON’C BATCH PLANT CRESCENT BRIDGE 1 ABUTMENT BORED PILE BRIDGE PIER HEAD