1 / 17

Pixel : LS1, Run2 and Fase 2

Pixel : LS1, Run2 and Fase 2. Slides per Clara 17 September 2014 G. Darbo– INFN / Genova Indico agenda: https ://agenda.infn.it/conferenceDisplay.py?confId= 8420. 2014 Activities – 2015 Plan. 2014: CSN1 funded (Feb and May) R&D Phase 2 activities for ATLAS & CMS inner trackers.

Télécharger la présentation

Pixel : LS1, Run2 and Fase 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pixel : LS1, Run2 and Fase 2 Slides per Clara 17 September 2014 G. Darbo– INFN / Genova Indico agenda: https://agenda.infn.it/conferenceDisplay.py?confId=8420

  2. 2014 Activities – 2015 Plan • 2014: CSN1 funded (Feb and May) R&D Phase 2 activities for ATLAS & CMS inner trackers. • Development of 3D and Active Edge sensors with FBK – 3 Batches (ATLAS/CMS) • Bump-bonding: development of Indium bumps (6” sensors) and produce modules • Develop a technology for pixel detector hybridization using C (dielectric) instead of R (bump-bonding) coupling • Completion of CO2 test plant (combined ATLAS / LHCb) • 2015: Activities and line of funding • Continue with 3D Sensor plan: produce modules, test in lab and TB, irradiate, procure sensors for next FBK run. • Bump-bonding: for testing FBK sensors and to develop for future RD53 requirements • CO2 cooling: contribute to ATLAS stave R&D, thermal simulation and test with CO2 plant • Multi-module R/O: use leading experience of ROD designer (BO) to develop a 16 module table-top road for architecture study and for test-beam application. • Upgrade to USBPix3: most diffused single module system based on USB. Upgrade also for use if HV/HR-CMOS • HV/HR-CMOS: presented a new project in CSN5 (BO, GE, MI)

  3. 3D Sensor Program - 2014 Planned 3 run at FBK in 2014 – Funded by CSN1 in Feb • No.1: DRIE process setting up for thin columns. Process in completion. Found that 5-6 µm are the best suitable column diameter. • No.2: test planar process with SiSi DWB and Epi substrates. Layout completed, mask submission, wafer expected in 6 weeks. • No.3: 3D single side process with SiSi DWB and Episubstrates. Layout in discussion. Compatible layout with other foundries (CNM) to simplify common test of devices. Note: • A second 3D run is foreseen at the end of 2015 / early 2016 – layout matching RD-53 layout. Schedule presented in Feb’14. Still up to date. Need approval from MEMS3 committee of 3rd batch!

  4. FBK: Status of Batches • Batch 1: study of columns In measurement • Batch 2: study SiSisubtrates Mask submitted 3.8 um 158 um 5.6 um ATLAS CMS • Batch 3: 3D sensors Layout study and Simulation of a 3D pixel cell Test structures for Si-Si qualification

  5. CCPD Hybridization Process Recipe Spin SU-8 photoresist Pattern pillars by mask Spacer define the distance between chips Target to D = 5 µm, C ~ 4 fF for 18 µm pad diameter. Proper qualified glue • HV/HR-CMOS chip coupled capacitively to R/O chip (CCPD – Capacitively Coupled Pixel Detector) instead of “classic” bump-bonding • Develop a technique to insert uniform, well defined thickness of dielectric between R/O and HV/HR-CMOS chips • Should be a cost effective, rad-hard process to transfer to industry • Test program in progress: • See preliminary results next slide • Activities will continue in the HVR_CCPD project in CSN5 (new experiment) • Involving BO, GE & MI • Also scientists outside ATLAS will participate. R/O CHIP R/O CHIP R/O CHIP DETECTOR CHIP Glue deposition Align & pressure

  6. Deposition of Pillars (spacers) 2-inch mask below with different Densities of spacers – FE-I4/FE-I3 Structures. SU8-2005 deposited on 2-inch wafer from Siegert Credits: V. Ceriale FE-I4 with matrix of SU8 spacers: 200 µm x 200 µm columns 4.7 µm high FE-I4 with matrix of SU8 spacers: 40 µm x 40 µm columns 4.7 µm high

  7. 2014 - CO2 Cooling Plant Attilio…

  8. Milestones

  9. Spare slides

  10. 3D Sensors – Proposed Process Single side 3D process New generation of 3D sensors • 6” wafer new process at FBK • Smaller pixel (event pileup) • reduce column distance (2x1016neq/cm2) • Thinner pixel (≤1.5ke threshold) • TCAD simulation: Optimal Q, Lower Cdet ,… • Bias voltage applied to back side (as IBL) Single side 3D process on: • Si-Si DWB (Direct Wafer Bonding) • Epitaxial wafers n++ col Charge Amp. Bump-bond P+Epi layer / P+ High Ω•cm wafer 100÷150µm Epi – SiSi DWB P++ Low Ω•cm wafer Thin-down -Vb metal p++ col • TCAD capacitance simulation • Layout: 2 n-columns in 25x150 µm2 • Total capacitance for dcol=5µm • 100 µm thick  71 fF/pix • 150 µm thick  88 fF/pix • It was 200 fF/pix for IBL

  11. DRIE for Ohmic Columns 3.8 um 158 um 5.6 um 7.6 um

  12. DRIE for Junction Columns LEFT CENTER RIGHT

  13. Planar test batch ATLAS CMS • p-typeSiSi DWB wafersfrom ICEMOS • 100-mm and 130-mm HR activesensorthickness • p-spray & p-stop isolation • Layout ready, masksordered • To start now, to be completedin 6-7 weeks Test structures for Si-Si qualification

  14. Wafers Sets – To Bump-Bond 3D Double Side Batch Planar ATLAS/CMS “Batch 2” CMS Single chip (24x) (1E, 2E, 3E, 4E) • In program 4 sensor batches that would need BB in 2014/15: • 3D double side – October - Funds (MI) assigned for 2014 • Planar ATLAS/CMS Batch 2 – November – Funds (FI/PI) assigned 2014 • 3D and Active edge batches coming 2015 – no funds yet. In 2015 request ATLAS FE-I4 (13x) ATLAS CMS CMS Quads (6x) (2E, 3E) MEDIPIX2 (4x) NA62 test chip (20x) Test structures for Si-Si qualification

  15. SU8-2005 Results Profile scan direction • 1.26 µm of bow. Column highs are very uniform: 4.7 µm over 2 cm • Results obtained with a spinning rotation of 2500 rpm and SU8-2005

  16. Future Plan: M-Module R/O • Le caratteristichedellaschedasono: • Completacompatibilità firmware e software con il ROD/BOC IBL ROD/BOC in one card • Possibilità di operaresenzacrate (table-top) • Connessioneottica o elettrica di 16 FE-I4 • Possibilità di connessioneesterna via GbitETH, S-Link (Modalitàcompatibile con FW/SW IBL) • Possibilità di utilizzo per test GBT/FELIX, con uscitaPCIe e protocolliInfiniband, rapid-io, 40-100 GBe • Costi: • Prototipaggio e fabbricazione di due schede10 k€ • Realizzazione di 5 schede per ilaboratoriitaliani15 k€ • Componenti off-shelf per ilsistema10 k€ Attività BO-GE Prototipi 2015 Produzione 5 schede 2016

  17. Got Funded • 3D • Funded 3 batches at FBK: • Mechanical test – approved by MEMS3 committee – order placed (3x2200 €) • Simple planar to qualify substrates – approved by MEMS3 – order placed (6x2200 €) • 3D batch, single side, on hold waiting batch 2. • Substrates • Ordered 55 wafers from IceMOS (SiSi wafer bonded) – material is on shipment • Looking for Epi wafers – indirect contact with SHINETSU – offer received (25 wafers – 11.9 kCHF) – doubts on specifications (epi-layer thickness spread: 104÷156 µm!) • Bump-bonding • Funded 20 k€ for BB at Selex + 7 k€ for FE-I4B • Bump-bond 3D sensors in production at FBK – old design IBL-like • Develop In-bumps for high density – incomplete funding (cut the dummy wafers). • HV-CMOS hybridization • FE-I4B plus consumables to test hybridization • CO2 cooling • Funded TRACI CO2 cooler

More Related