1 / 30

AMS-02 Integration & Test Plans & Status

AMS-02 Integration & Test Plans & Status. Trent Martin. 24 January, 2007. Agenda. Integration Documentation AMS Assembly Area/Clean Room 867 STA & Flight Integration Hardware Status Pre-integration of STAs in the Flight USS prior to STA VC/CMR arrival

garson
Télécharger la présentation

AMS-02 Integration & Test Plans & Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AMS-02 Integration & Test Plans & Status Trent Martin 24 January, 2007

  2. Agenda • Integration Documentation • AMS Assembly Area/Clean Room 867 • STA & Flight Integration Hardware Status • Pre-integration of STAs in the Flight USS prior to STA VC/CMR arrival • Pre-integration of Detectors on the STA VC & Flight USS prior to Flight Cryomagnet arrival • Integration discussion items & plans for resolutions • Final Flight Integration

  3. Integration Documentation • All NASA developed AMS documentation can be found at • http://ams-02project.jsc.nasa.gov/html/Documents.htm • Includes payload Interface Control Documents and AMS-02 Assembly and Testing Integration Plan

  4. AMS 02 Integration at CERN Assembled AMS 02 Upper Part Lower Part AMS 02 Shipping

  5. KSC CERN / ESTEC • Beam Test • Experiment • Calibration • Thermal Vacuum • Test @ ESTEC AMS-02 KSC Processing AMS-02 Hurricane Cover SSPF 3 Operational Years ISS Launch

  6. AMS 02 Assembly Sequence for Pre-Integration and Flight Integration

  7. Upper USS & Magnet UPS Magnet CAB Technical Interchange Meeting July 23, 2004 R.Becker (MIT) USS-02 CVB 1) SCL delivers Magnet (Flight) or NASA delivers STA Magnet (Pre-Integration) 2) NASA delivers USS 3) USS main bolted to Vacuum Case (Magnet must be warm) & placed into rotation assembly stand

  8. Crate Installation using Jig Electronics Assembly Jig Installed Electronics mounted in sequence with detectors during pre-integration - Radiator Mounted Electronics Assembly Jig replaced with Radiator during flight integration when all crates are linked and form a self supporting structure

  9. ACC ACC VC VC • Finger brackets bolted to inner lower bore of VC • 16 Scintilator panels placed in inner bore resting on finger brackets • 3) Carbon composite cylinder and with compliant brackets mounted at upper and lower • inner edge of VC securing the paddles • 4) PMT’s, fiber couplers, and optical fibers mounted to Conical flange

  10. Tracker, Cooling, & Star Tracker 5) Tracker Electronics Crates Star Tracker 6) 3) 4) 1) Tracker Flange of VC Tracker Cooling Box VC 2) 1) Tracker Inner planes and upper conical flange lowered and secured 2) Lower conical flange mounted 3) Cooling loops, TTCS, & plumbing 4) Outer planes (1 & 5) 5) Crates & cabling* 6) Star Tracker camera 4)

  11. TRD & Upper TOF Upper TOF: 1) Upper TOF mounted to TRD TRD MLI TRD TRD GAS System 1) TRD with M-structure lowered onto USS & bolted 2) Gas system installed and plumbed to TRD 3) MLI enclosure 4) Crates & Cabling

  12. Lower USS Integration (5) Lower TOF 1) Reinforced with Jig, rolled underneath AMS & lifted into position. Struts adjusted and bolted in place 2) Crates and Cabling (6) RICH 1) RICH lowered, shimmed and bolted to lower USS 2) Crates and Cabling (7) ECAL RICH/Lower USS assembly lifted & lowered onto ECAL –then bolted in place Crates & Cabling These steps can be done in parallel with upper USS integration and only need to be done once (ie. No pre-integration)

  13. Upper & Lower Parts Integration Upper Part Lower Part • Lower part rolled underneath Upper • Lifted in place, shimmed, and bolted • Electrical connections made

  14. De-integration for Flight Magnet Temporarily remove mid-brackets and lower struts

  15. Temporarily Reattach Top Brackets to Upper USS Move Main Ram & Wake Radiators outward to allow installation of Flight VC & Magnet

  16. Radiators & Electronics • Zenith radiators with plumbing attached assembled in quadrants: bolted to TRD upper honeycomb and heat exchangers to Cryocoolers • Plumbing secured and insulated • Main radiators: jigs removed from self supporting crates and radiators bolted • Tracker Radiators: Jigs holding heat exchangers removed and radiators lowered and bolted to USS and exchangers Zenith Radiator Tracker Radiator Tracker Radiator RAM Radiator WAKE Radiator RAM Radiator

  17. AMS Assembly Area Clean Room 867 Everything in the AMS Assembly Area/Clean Room 867 needed to begin the STA integration will be ready no later than (NLT) February 2, 2007. • Operation as a Clean Room (air conditioning, filters, sealed & positive pressure) will be ready in May, 2007 • Rotation Assembly Stand (RAS) delivered, assembled, installed, and ready for use • Scaffolding delivered, assembled, and ready for use

  18. AMS Assembly Area Clean Room 867 • Information provided in the Resource Requirements checklists has been used to order common use supplies and to estimate facility requirements • Work area required – with & without crane access & special access • Crate storage area, volume, and environment • Tables & chairs • Storage cabinets & open shelves • Air bearing pallet requirements • Cleaning fluids/supplies & vacuum cleaners • Supply gases (He, CO2, N2, Compressed air, etc.) • Fans for ventilation/cooling of hardware & personnel • Power requirements • ??? • If you didn’t ask for it on the checklists, do NOT expect it to be provided!

  19. N AMS Assembly Area Clean Room 867 Remov-able Ceiling Panels Airlock Ceiling Panels are NOT Removable

  20. AMS STA Integration Hardware • STA VC integration with the STA Magnet (Cold Mass Replica - CMR) was completed in December at SM • STA VC Arrived in Terni/INFN for Sine Sweep Tests on January 10th • Test hardware was previously shipped to Terni and testing has been completed • Ship STA VC to ESTEC for Acoustic Tests - March ’07 * • Return to CERN for integration in USS – late March ’07 * • * Depends on results of STA VC/CMR sine sweep & acoustic tests

  21. AMS Flight Integration Hardware • Flight USS is complete and has arrived at CERN with the Primary Support Stand (PSS) and the Primary Lift Fixture (PLF) • Flight Vacuum Case is complete and will be shipped to SCL/SM when they have room in their facility to accommodate it (after Flight Cryomagnet tests are completed and the SFHe Tank is delivered and SFHe leak tested)

  22. Pre-integration of STAs in the Flight USS Prior to STA VC Arrival • STA Hardware Pre-integration in Flight USS • On-line integration of the STA Crates/Radiators on the USS will begin the week of February 5, 2007– before the STA VC arrives • This allows work to proceed even if the sine sweep & acoustic tests are delayed • 10T crane installation will be delayed until after STA Pre-integration is complete at beginning of March • If necessary, the USS/STAs in PSS will be moved away from crane installation • There are ~3-4 weeks available in March to use the flight USS & STAs for fit checks, cable & plumbing runs, measurements, etc.

  23. Pre-integration of STAs in the Flight USS Prior to STA VC Arrival • STA Hardware assembly in Flight USS (cont) • Integration of all STAs in USS to be completed by mid-April ’07 * • Even though the STA VC delivery to Terni slipped ~5 weeks and the RAS readiness at CERN slipped ~3 weeks, this is only ~2 weeks later than previously reported at AMS TIM on October 27, 2006 • Ship USS with STAs to Munich/IABG in April ’07 * • Static Tests • Modal Tests • Return USS with STAs to CERN in August ’07 * • * Depends on results of STA VC/CMR sine sweep & acoustic tests and USS/STA modal & static tests

  24. Interference between Flight VC/Magnet & Electronics Crates during Final Flight Installation • R. Becker/MIT, J. Kastelic & P. Mott/JS, & R. Stafford-Allen/SM to determine how much room is required to clear the Flight VC/Magnet as well as how much room is available by Jan 29th. • Provide estimate of additional length required for lower inter-radiator cables to M. Capell & A. Lebedev • Final cable routing must accommodate additional length • Be sure there’s no interference with hardware mounted outboard of crate jigs during pre-integration activities • Upper inter-radiator connections will be disconnected because the additional length will be too much additional weight • C. Lauritzen/JS to determine if there is any problem on the USS if the brackets are temporarily re-attached at a wider position by Feb 5th • M. Molina/CGS to determine if Radiator brackets are OK by Feb 5th • Consider using blocks/spacers under the brackets and reattaching the lower struts • K. Bollweg & J. Heilig will arrange trial test using STA Crates/radiators in late February

  25. Pre-integration of Detectors on STA VC & USS prior to Cryomagnet Arrival • All the detector groups have continued to evaluate the pre-integration proposal and have agreed that it should proceed according to the schedules thoroughly discussed at this TIM • Current estimate of Pre-integration start: August, 2007 • Pre-integration finish: December, 2007 • Optical fibers between ACC & VC for TAS will be installed • Constantly monitor the Cryomagnet progress and decide how much more flight hardware to pre-integrate • Current estimate of magnet delivery to CERN: February, 2008 • Do as little de-integration as possible – just in time to remove the STA VC and install the Flight VC & Cryomagnet in the USS

  26. Pre-integration of Detectors on STA VC & USS prior to Cryomagnet Arrival • Consider removing the STA VC, Tracker, and ACC from the USS as an assembly so parallel work can continue during Flight VC/Magnet installation • Use VC rotation fixture and wheels/brackets developed at SM • This could shorten deintegration by 2-3 weeks; thus allowing combined cosmic ray testing to be extended

  27. Final integration of Detectors on Flight VC & USS after Cryomagnet Arrival • All detectors must be integrated and functionally tested with the Flight VC and Cryomagnet at CERN by July, 2008 • Beam tests at CERN (~1 month reserved) • Thermal Vacuum Tests at ESTEC (~3 months reserved) • EMI Tests at ESTEC (~1 month reserved) • Delivery to KSC in December, 2008

  28. What we have… sort of.

  29. Where we must be by December 2008 at KSC...

More Related