PRESS 부품 표준원가계산 실습 1

120mm. 280mm. PRESS 부품 표준원가계산 실습 1. 1) PARTS SPECIFICATION. * PART NAME : PATCH * 재질명 : SPCC * 두께 : 0.7mm * 재질단가 : 423/Kg * 제품 실중량 : 0.108Kg * 투입중량 : 0.333Kg (4'X 8'SHEET 전체 WT 를 성형 가는 CAVITY 로 나눔 )

gaura
Télécharger la présentation

PRESS 부품 표준원가계산 실습 1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 120mm 280mm PRESS부품 표준원가계산 실습1 1) PARTS SPECIFICATION * PART NAME : PATCH * 재질명 : SPCC * 두께: 0.7mm * 재질단가 : \423/Kg * 제품 실중량 : 0.108Kg * 투입중량 : 0.333Kg (4'X 8'SHEET 전체 WT를 성형 가는 CAVITY로 나눔) * NET SIZE : 280 X 120 X 0.7 * BL SIZE : 323 X 157 X 0.7 * 4'X 8' SHEET 사용 ( 4'= 1219mm / 8'= 2438mm) 4'X 8'= 7 X 7 = 49 EA (SHEET에서 49EA 제품 성형 가능) * 7 = 1219 ÷ BL SIZE SHORTER * 7 = 2438 ÷ BL SIZE LONGER 2) 적용임율 * 임율 : 10,000 \ / HR (각 회사실정에 맞는 표준임율 설정)

  2. 주요 FACTOR

  3. 4 X 8 SHEET 1219 X 2438 X 0.7 X 7.85 - RM/WT = = 333 g 49 X 1000 333g X 423\/Kg = 140.86원 1000 (3) 표준원가계산 풀이(4'X8'SHEET 이용시) 1) 재료비 계산 ① 투입중량 RM/WT 산출 • - NET SIZE : 280 X 120 X 0.7 • - BLANK SIZE : 323 X 157 X 0.7 (DR : 4' X 8') • RM/WT 산출 : 4' X 8' SHEET 기준 ⇒ 1219/157 = 7.76 EA = 7 EA ⇒ 2438/323 = 7.54 EA = 7 EA TOTAL SHEAR'G CAVITY = 49 EA 1219 mm 2438 mm ② 제품 실중량(NET/WT) : 도면 중량 및 SAMPLE 중량 실측 = 108 g ③ SCRAP 중량(SCRAP W/T) : RM/WT - NET/WT = SCRAP W/T = 333g - 108g = 225g ④ 재료비 계산 - 투입재료비 = RM/WT X 재질단가 - SCRAP 재료비 = SCRAP/WT X SCRAP 단가 X 회수율 (100%) 225 X 80 \/Kg X 1.0 = 18 원 - 재료비계 = 투입재료비 - SCRAP 재료비 = 122.9 원

  4. SET UP 시간(MIN) X 60 LOT 수 * 준비시간 = 2) 가공비 계산 ① 공정설정 : SH ---> CUT ---> DR ---> TR ---> RE.FL ---> Pi ② 기계 TON 수 결정 SH : SHEAR'G 전용 MACHINE (SMC) CUT : SHEAR'G 전용 MACHINE (SMC) DR : 2 X 2 (PPFS + PPFL) X 두께 X ATNS = 2 X 2 (280 + 120) X 0.7 X 33 Kg/mm² = 36.96 TON ⇒ 60 TON 선정 * READ'G MACHINE 이 DR LINE 이므로 이하는 LINE UP 기준에 따라 60TON 선정 ③ 공정,기계 TON 수 결정되면 원가요소 선택 ④ 가공비 계산 {(C/T + 준비시간)}X (임율 X 작업자수 + 경비율) CAVITY X 3600