Learn about project control systems, asset conservation, types of controls, balancing control, handling changes, and more. Understand the importance of maintaining a balance in project control and implementing effective control strategies to ensure project success.
E N D
PROJECT CONTROL • Project Control Defined • Types of Control Systems • Need for Balance in Control Systems • Control of Creative Efforts • Changes and Change Control
Project Control Defined • CONTROL: The act of reducing the difference between plan and reality • The last element in the plan-implement-monitor-control cycle • Uses the information from the monitoring process to get and keep a project on track
Control Can Be Complicated • Performance, cost, and schedule issues all have a human element • Symptoms are obvious, but root causes never are • “Messes” vs. “problems” • Hard to separate random events from systemic difficulties
Two Fundamental Purposes of Project Control • Regulate project results through alteration of activities • Efficiently use and protect organizational assets
Asset Conservation Has Three Aspects • Physical Assets • Maintenance, inventories, security protection • Human Resources • Managing acquisition, development and performance of people • Financial Resources • Budgets, audits, financial ratio analyses • The concept of “due diligence”
Purpose of Control • To make the actual meet the plan • The Process • 1. Identify key performance areas • 2. Set standards • 3. Measure performance • 4. Compare • 5. Take corrective action
Three Types of Controls • Cybernetic controls • “Steering” • Key feature: automatic operation • Go-no go controls • Most common project control • Test that predetermined specifications have been met • Post controls • After the fact
More on Go-No Go Controls • Based on project plans, budgets, schedules • Can be periodic or milestone-driven • Both are essential • “Phase-gated” criteria are hurdles that must be passed to go to next project stage • Common terms: “exit criteria,” “milestone decisions,” “system maturity models”
Components of Post Control Process • Benefits future projects more than the present one • See Project Auditing in Chapter 12 • Four parts • Project objectives • Milestones, checkpoints, budgets • Final report on project results • Recommendations
Some Desirable Control System Features • Flexible, able to adapt to unforeseen events • Cost effective (control value > control cost) • Useful and ethical • Accurate, precise, timely • Simple and maintainable • Fully documented
Critical Ratio • Critical ratio = actual progress X budgeted cost scheduled progress actual cost • I.e., CSI = SPI X CPI, as in Chapter 10 • Indices and ratios greater than 1.0 are favorable
Effective Control Systems Must be Balanced • Balance means • Measuring both tangibles and intangibles • Looking at both long-term and short • Keeping flexibility in the system • Addressing human factors • Focusing on correction, not punishment • Optimizing control, not maximizing it
A Question of Balance • Too little control? • Too much control? C Control $ C Mistakes Amount of Control
Control of Creative Activities • Controlling “knowledge work” is difficult • Three tools • Progress reviews • Reassigning people • Control of resource inputs
Controlling Changes and Scope Creep • Changes can drive higher costs and stretched out schedules • So controlling them is an essential project management task • A formal change system is a must for project control
Five Principles of a Formal Change Program • All contracts specify formal change process • All changes require formal change order • All change orders approved in writing by client and project organization • Project manager is always consulted • The approved change order becomes part of the master plan
Changes and Change Control • Remember the last step of the control process: Take corrective action, so that the actual matches the plan • Two Types: Business and Technical Changes
Business Changes • Business-related • Driven by such things as: • Spec relief • Deliverables changes • Funding shifts • Schedule changes • Acts of God • Subcontractor changes
Technical Changes • Technological issues, such as: • New technologies • Laws of physics • Competitor response • Changes in client requirements (real or political)