An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Recently Report LIU Qian

  2. Putting the common end into the moon box We removed this surface of rack when we were installing the common end. We didn’t move the moon box at all. If we want to do the alignment, we’d better not to move the moon box too.

  3. The coiled tube is tied on the rack Since the coiled tube is fat and strong, we leave this half to protect the fibers. Soft tape is used to protect the fibers Marc: We’ve received 6 C-clamps. They’ve been put on.

  4. MTP connecters are all connected (east side) Upper box Bottom box

  5. Distribution box (west) are installed West upper box We didn’t connect the west bundles to distribution box yet. (Will be done in this week)

  6. EC TOF fibers are all installed Sorry I didn’t take a camera when we finished the EC TOF installation. I’ll show the picture tomorrow. Yesterday all 48 EC TOF and fibers are all installed. The fiber is installed when the TOF is been installing. The extra-length of fibers will be “over-under-coiled” when they remove this support It is said they’ll move the east EC to barrel tomorrow, then they’ll remove the support.

  7. The USTC DAQ situation 1.Yesterday they connected all signal cables. 2. Today they are doing the self test, but not finished yet. 3. They’ve installed the monitor board which can control our UH module and moon box. Tomorrow they’ll check their low-voltage and high-voltage first, then try to pulse the laser and read out the signal.

  8. Next step • Connect all fibers except the west endcap fibers. (West endcap is not finished yet) • Find out why the Q resolution is so large using the USTC DAQ. (We’ve discussed this with USTC people, they said they’ve tried to read a stable signal, the resolution is good.) • Analysis the data.

  9. Thanks! LIU Qian