The Ultranet 3rd Industry Briefing, held on December 19, 2006, provided updates on the progress of the Ultranet project by the Department of Education. The agenda included discussions on project history, current statuses, and pilot evaluation results. Notable achievements include pilot participation from 627 teachers across 22 schools, demonstrating enhanced learning environments and improved teacher collaboration. The briefing also outlined the next steps in the project, including finalizing specifications and the Request for Tender (RFT) framework, with key timelines moving into 2007.
E N D
Students@Centre – Ultranet3rd Industry BriefingTuesday, 19 December 2006DoE, 2 Treasury Place, Melbourne
Students@Centre - Ultranet Adam Todhunter Education Chief Information Officer Department of Education
Agenda • Welcome • Project history • Since the last briefing • Where are we now? • Progress of pilot • Progress of tender • RFT framework • Next steps • Process and timelines • Challenges ahead • Questions?
Project history • S@C developed a prototype web-based environment to support the implementation of the Blueprint for Government Schools • To provide an ICT framework to allow the whole school community to engage • Pilot was funded by Treasury in 2004 • Original S@C team has been strengthened • Project sponsor is Darrell Fraser(Deputy Secretary OSE)
Since the last briefing… • Labor Financial Statement commitment of $60.5m • Ongoing professional development in pilot schools • All pilot teachers logging on and marking student attendance online • More teachers planning units of work • Prototype demonstrations • Engagement of key stakeholders • Development of project and RFT documentation
Where are we now? • Pilot Evaluation Report has been completed • Business Case (draft) completed • Non-functional Requirements Specification • (draft) completed • Functional Requirements Specification ~50% • completed • Request For Tender ~65% completed
Progressofpilot • All pilot schools using the system • Schools marking student attendance rolls • Groups of students and parents accessing the Ultranet • TLF objects embedded in a shared repository • Teachers executing Term 4 2006 work using the Ultranet • Schools and DoE gaining up-to-date data on student attendance • Pilot evaluation completed
Evaluationmeasures • An enhanced learning environment for every student • Improved planning, preparation, sharing and delivery of learning materials by teachers • Improved capacity to track progress and manage learning pathways for every student • Improved reporting of student progress to parents, teachers and school administration
Evaluation summary • 627 teachers from 22 schools participated in the evaluation (12 pilot schools/10 matched schools) • Impact of the Ultranet was particularly noticeable in Primary Schools • Positive changes included access to technology, ideas and attitudes to technology and increased motivation to collaborate as a result of the Ultranet • Teachers and Administrators strongly expressed support and were enthusiastic about the potential of Ultranet
Progressoftender • Development of functional and non-functional specifications • Development of the Business Case • Development of the Request For Tender • Facilitation of a market testing exercise • Facilitation of workshops and focus groups
User groups Baseline User Volumes: ~ 3,000 ~ 40,000 ~ 550,000 ~ 1,000,000 Administrators Teachers Principals & Business Managers Students Training & Support Services Departmental & Regional Staff Parents/ Guardians 1,213 Primary = 1,602 311 Secondary/Primary-Secondary Vic Govt Schools 78 Special Development
RFT framework • Will comprise of 6 parts (A – F): • A – Conditions of Tendering • B – Specifications • C – Proposed Contract • D – Bidder’s Response • E – Ethical Purchasing Policy • F – Victorian Industry Participation Policy • Understand the VGPB Purchasing Policies • www.vgpb.vic.gov.au • www.tenders.vic.gov.au
Next steps… • Finalise Business Case by December 2006 • Finalise Non-functional Requirements • Specification by January 2007 • Complete Functional Requirements • Specification (draft) by January 2007 • Complete Request For Tender (draft) by • February 2007 • Release RFT (draft) by March 2007 • Release RFT (final) by May 2007
Process & Timelines Pilot 2006 Final evaluation Q4 2006 ERC1 bid Q1 2007 *Tender (draft version) release Q1 2007 *Tender (final version) release Q2 2007 *Tender evaluation Q2/3 2007 *Build / plan deployment Q4 2007+ *Commence deployment 2008+
Challenges ahead… • Managing organisational, operational and • people change • School readiness (i.e. infrastructure) • Migration of existing systems • School Interoperability Framework for the • Victorian Government • Evolving technology • Delivery timeframe • Interdependencies
Questions? • Questions and responses will be recorded and published on the Students@Centre website by: • Adam Todhunter – ECIO • Ben Cushing – Project Director • Anne Dalton – Probity Advisor • Future questions should be addressed through: • Adam Todhunter, ECIO
Students@Centre – Ultranet3rd Industry BriefingTuesday, 19 December 2006DoE, 2 Treasury Place, Melbourne