240 likes | 446 Vues
Gas Treatment Plant. Chris, Stephanie, Mariam, Kyle Mentor: Jerry Palmer. Report Outline. Previous Questions Block Flow Diagram Detailed PFD's (stream #, components, P&T) for each process Energy sinks/loads, Equipment sizing, Cost in Aspen estimator for one process -- Hydrocarbon recovery .
E N D
Gas Treatment Plant Chris, Stephanie, Mariam, Kyle Mentor: Jerry Palmer
Report Outline • Previous Questions • Block Flow Diagram • Detailed PFD's (stream #, components, P&T) for each process • Energy sinks/loads, Equipment sizing, Cost in Aspen estimator for one process -- Hydrocarbon recovery
Previous Questions 1. Sending 97% Nitrogen and 3% methane from Nitrogen rejection stream to NH3 plant. 2.Using thermal swing adsorber instead of a pressure swing adsorber. To prevent the loss of feed gas in the bed during depressurization and also,the short time cycle in PSA can cause rapid re-pressurization that will lead to transient variation in the feed and product flow which will affect the operation of the plant 3. Using only one turboexpander for Hydrocarbon recovery.
Basis : 310 MMSCFD Revenues Midrex : 103 kmol/day (Transfer Cost) Syn Gas:111 kmol/day (Transfer Cost) Nh3 PLant : 50.4 kmol/day (Transfer Cost) CHP :195.4 kmol/day (Transfer Cost) Pipeline:4.8 kmol/day ($3.80/MSCFD) LNG: 5000 BBL/day ($10.40/BBL) NGL: 48990 BBL/day (~$22/BBL)
Aspen Estimate-Demethanizer in Hydrocarbon Recovery Size: Tower: • Vessel Diameter: 8.5 ft • Vessel Height 66 ft • Liquid volume: 11,249.5 gallons • 33 Trays • 24 inches between trays Condenser: • Area: 22,980.6 ft^2 Reboiler: • Area: 7,803.94 ft^2 • Tube length: 20 ft Reflux Pump: • Liquid flow rate: 1808.3 GPM • Efficiency: 70
Aspen Estimate-Demethanizer in Hydrocarbon Recovery Equipment Cost: • Tower: $3,059,300 • Condenser: $419,000 • Reboiler: $268,000 • Reflux Pump: $17,200 Total equipment cost for one Demethanizer Column: $3,763,500
Aspen Estimate-Demethanizer in Hydrocarbon Recovery Energy: • Tower: 28.03 MMBTU/hr • Condenser: 22.7 MMBTU/hr • Reboiler: 5.3 MMBTU/hr • Reflux ratio: .35
Aspen Estimate-Demethanizer in Hydrocarbon Recovery Cost: • Total operation cost: 19,031,900 $/year • Total capital cost: $12,567,400
Energy Loads and Sinks • PFD-001: Compression = 6888 HP Heating = 1.7MMBTU/HR • PFD-002 and PFD-003: Estimated total of 139MMBTU/HR • PFD-004:Air Cooling =3.4MMBTU/HR Compression = 880HP Heating = 44.6MMBTU/HR • PFD-005: Refrigeration = 56.3 MMBTU/HR • PFD-006: Heating = 8 MMBTU/HR • PFD-007: Compression = 1260 HP Refrigeration = 58 MMBTU/HR • PFD-008: Compression = 920HP
Major Equipment Costs • 6 molecular sieve Adsorbers installed $ 6,690,000 • 24 Tray Nitrogen Rejection Column Installed $2,300,000 • Absorbing and Stripping Columns for MDEA treatment, approximately 25 trays each intstalled $2,500,000