1 / 5

Review Context and Purpose

Review Context and Purpose. Selection of OMT Design for the EVLA X-band Receiver. Mark McKinnon. EVLA Project Manager. Context. X-band OMT identified as a significant technical risk to the EVLA project at the EVLA Risk Management Workshop held in Dec 2006

gmicheal
Télécharger la présentation

Review Context and Purpose

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Review Context and Purpose Selection of OMT Design for the EVLA X-band Receiver • Mark McKinnon • EVLA Project Manager

  2. Context • X-band OMT identified as a significant technical risk to the EVLA project at the EVLA Risk Management Workshop held in Dec 2006 • Likely that the extension of other EVLA OMT designs to X-band would be too large and could not be cooled with a CTI model 22 refrigerator • Existing cryogenics and electrical infrastructure on EVLA antennas cannot support the larger model refrigerator (CTI 350) that might be required by a large OMT • Model 350 refrigerators for X-band not in EVLA project budget • X-band OMT has the highest cost impact of any item on the EVLA risk register • Alternative OMT designs pursued to mitigate risk

  3. Cost Impact of Adding Model 350 Refrigerator • Model 350 refrigerator (30 x $7K) $210K • He compressor (30 x $7K) 210 • 5/8" SS tubing (He supply & return) 25 • New fuses in antennas & control bldg 20 • Replace SEC transformer & wiring 75 • Charcoal traps (30 x $1.2K) 36 • Cryo. tech (1 FTE-yr, loaded salary) 50                                   Total   $626K Note: costs do not include those of the selected OMT

  4. Schedule and Budget • Schedule • X-band receiver production scheduled to commence in Jan 2010 • Receiver production rate: about one per month • Completion scheduled for end of FY2012 (i.e. Sep 30, 2012) • Budget • Total M&S budget for X-band receiver is $561K • $54K expended as of August 31, 2009 • Budget currently deemed adequate for any OMT design that might be selected (but not for additional cryogenic and electrical infrastructure that might be required) • If absolutely necessary, sufficient funds are available in project contingency to cover additional infrastructure costs

  5. Review Purpose • Review and compare the designs for the X-band OMT • Review possible impacts on the cryogenic and electrical infrastructure of the EVLA antennas • Select a path forward for the selection of the OMT • Identify any remaining issues associated with the preferred OMT design

More Related