This report summarizes the progress of the MTA beam line installation during Week 5 from August 31 to September 7, 2007. The shielding underneath the hatch area is complete, and restacking was finalized on September 4. We are enhancing safety requirements with cover plates and retrofitting where necessary. Electrical work is ongoing with load cable installation projected to finish by Monday. Mechanical installation is making strides with all magnets in place. Additionally, alignment processes and LCW work have commenced, and vacuum work has progressed with completed stands.
E N D
MTA beam line installation Weekly ReportSeptember 07, 2007Period covered:August 31st to September 7th (Week 5) Shutdown’07 Week 5 F.G. Garcia MTA – Week3
MTA Weekly Report – Week 5 • Shielding underneath hatch area is complete • Restacking complete on 09/04 • Finalizing some safety requirements: • Added cover plates to aid S&S • Retrofit cover plate over the utility penetration • Re-used the slug of concrete to plug in the beam pipe penetration • Electrical Work • Cable pull ongoing • Load cables estimate to finish by Monday • Immediately start pulling instrumentation cables Next week: Continue with cable pull. • Mechanical Installation • All magnets have been stationed in place • Next step will be alignment! • Moving along with MW stands (45% complete). Shutdown’07 Week 5 F.G. Garcia
MTA Weekly Report – Week 5 • Alignment • Outside corner of the concrete blocks were shot by surveyors Next week: Rough alignment starts Monday, Sep 10th • LCW work • Copper pipe installation complete (Linac side) • Brazing/installing taps Next week: Contractors will be moving to the MTA side • Vacuum work • Making as much progress as possible with the assortment of the spool pieces and flanges • Ion pumps stands are complete • Beam pipe support stands are complete Shutdown’07 Week 5 F.G. Garcia