Understanding Extended Duration Warranties, Performance Warranties, and Liquidated Damages in Construction Contracts

This presentation by Gene Rash and Rolly Chambers from Smith Currie & Hancock LLP explores the critical aspects of extended duration warranties, performance warranties, and liquidated damages in construction contracts. It covers general legal principles, the risk of nonconforming items, and the financial implications for contractors and clients. The discussion includes strategies for mitigating risks associated with longer term warranties and the importance of understanding sustainable building performance in the context of modern construction agreements.

gretel
Télécharger la présentation

Understanding Extended Duration Warranties, Performance Warranties, and Liquidated Damages in Construction Contracts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Extended Duration Warranties, Performance Warranties, and Liquidated Damages in Construction Contracts – What are the Risks? Presented by: Gene Rash & Rolly Chambers Smith, Currie & Hancock, LLP May 7, 2013

  2. Presenter Biographies Gene Rash and Rolly Chambers Partners in Charlotte, NC office of Smith Currie & Hancock, LLP Smith Currie & Hancock, LLP (http://www.smithcurrie.com) 60 attorneys devoted exclusively to construction and government contracts Focus on construction business legal matters Offices in Atlanta, Charlotte, Ft. Lauderdale, San Francisco & Washington, D.C. 2

  3. Extended Duration and Performance Construction Warranties • What will we cover? • General legal principles for construction warranties • Extended duration construction warranties • Construction performance warranties • Performance liquidated damages and construction warranties 3

  4. Extended Duration and Performance Construction Warranties • Why be concerned about construction warranties? • Construction warranties shift significant risks to clients • Financial risk of repairing nonconforming items • Clients may misunderstand the risks involved • You can help by recognizing construction warranty risks and exploring risk mitigation strategies 4

  5. General Principles for Construction Warranties • What is a warranty? • Promise that particular statement of fact is true and may be relied upon by other contracting party • “Standard” construction warranty • Materials and equipment new and of good quality • Work free from defects in workmanship • Work conforms to requirements of contract • No express time limit 5

  6. General Principles for Construction Warranties • Contractor will repair defects for 1 year after substantial completion • AIA, ConsensusDocs, EJCDC • Supplementary conditions may have additional warranty language • Contractor warrants Work “will be free from defects in materials and workmanship for a period of one year from substantial completion” 6

  7. General Principles for Construction Warranties • Performance bonds and warranties • Incorporate principal’s construction contract, including warranty obligations • Surety’s warranty obligations derive from principal’s warranty obligations • Warranty obligations extend beyond completion • Warranty obligations extend beyond final payment 7

  8. Extended Duration Construction Warranties • Construction warranties > 1 year • Owner shifts repair risk to contractor for longer term period • Public owners increasingly looking for extended duration warranties • Extended duration warranties stretch owner’s construction dollars 8

  9. Extended Duration Construction Warranties • Highway construction contracts • State DOT’s face reduced funding • Reduced funding impacts DOT q.c. testing and inspections • DOT’s require longer duration warranties to cover risk of correcting quality problems • Pavement warranties can be 3, 5, 7 years 9

  10. Extended Duration Construction Warranties • Building construction contracts • Extended warranties for building components (e.g. roofs, HVAC equipment, etc.) • Warranty durations may be 5,10, 20 years • If contractor goes out of business during extended warranty period, then performance bond surety will be liable 10

  11. Extended Duration Construction Warranties • Extended duration warranties impact contractor bonding • Difficult to estimate future financial obligations to cover extended warranty repair work • Long term warranty obligations extend long after contract funds are paid – surety concern • Sureties raise underwriting standards for longer term coverage 11

  12. Extended Duration Construction Warranties • Are there ways to mitigate risks of extended duration warranties? • Assign manufacturer’s long term warranty to owner • Obtain warranty bond separate from performance bond to cover extended warranty obligations • Limitations through terms of performance bond • Limit duration of performance bond • Exclude long term warranty language 12

  13. Construction Performance Warranties • Contract warranties that concern performance of completed project • Sustainable (“green”) building • Project will perform at certain level of energy consumption • Clean energy projects (solar, wind turbine) • Project will perform at certain level of output 13

  14. Construction Performance Warranties“Green” Building • Sustainable buildings are certified to meet standards for energy and environmental performance • LEED, Energy Star, green building codes • Federal, state, and local governments • Increasingly incorporate sustainable building standards in construction contracts • Want construction warranties that completed project will perform to “green” building standards 14

  15. Construction Performance Warranties“Green” Building • AIA Guide for Sustainable Projects (2011) • Disclaims warranty that project design and construction will perform to “green” building standards • Owner maintenance and operations after completion affect project’s performance • But … • >20% of U.S. cities over 50,000 in population had green building programs in 2009 15

  16. Construction Performance Warranties“Green” Building • Federal design-build project - warehouse • Required design to achieve energy consumption at least 40% below a given baseline (performance) • Required warranty of project design “through the statute of limitations and statute of repose” (extended duration) • Required design-builder to furnish performance bond 16

  17. Construction Performance Warranties“Green” Building • Federal design-build project - warehouse • Government’s remedies for breach • Equitable adjustment (deductive change) • Contractor repair or replacement of defective item at contractor expense (re-design) • Risk mitigation techniques • Performance bond covering construction work but excluding design • Design-build performance bond limiting liability for design (e.g. ConsensusDocs 470 (rev. 2011) 17

  18. Construction Performance WarrantiesClean Energy Projects • Solar cell and wind turbine power projects • Developer financing depends on selling a given level of output • Investors and lenders want assurance from developer • Developer shifts performance risk to project designer and contractor with performance warranties 18

  19. Construction Performance WarrantiesEPC Projects • EPC Contracts • Engineering, Procurement, and Construction • Type of design-build contract • Commonly used for constructing clean energy or industrial projects • EPC Contracts include performance warranties and construction warranties • If project fails to perform to warranted level, then EPC contractor is obligated to bring performance to the warranted level 19

  20. Construction Performance WarrantiesEPC Projects • Are there ways to mitigate risks of performance warranties in EPC contracts? • Errors and omissions insurance from designer for design defects • Performance warranty insurance from manufacturer of project components (solar cells, turbines, etc.) • Manufacturers warrant output performance of solar cells or turbines for long term – 12, 15, 25 years • Manufacturer partners with insurance company • Developer can obtain coverage directly 20

  21. Construction Performance WarrantiesPerformance Liquidated Damages • EPC contracts may provide for both construction delay and performance liquidated damages • Performance LD’s do not involve delays in construction • Performance LD’s involve delays in achieving a warranted level of output • Developer assesses performance LD’s while output is below warranted level 21

  22. Construction Performance WarrantiesPerformance Liquidated Damages • Are there ways to mitigate risk of performance LD’s? • Limitation of damages clause can cap an EPC contractor’s or performance bond surety’s liability for performance LD’s 22

  23. Extended Duration and Performance Construction Warranties • Extended duration and performance construction warranties shift significant risks to contractors and their sureties • Trend to include such warranties is likely to increase • Recognizing financial and legal risks and attempting to mitigation them is crucial 23

  24. Contractual Risk Allocation Provisions QUESTIONS? If you do not have the opportunity to have your question addressed during the session, you may contact the presenters directly: Gene Rash & Rolly Chambers Company: Smith, Currie & Hancock, LLP Phone: 704-334-3459 Email: gfrash@smithcurrie.com Email: rlchambers@smithcurrie.com Address: 1023 W. Morehead St., Suite 301 Charlotte, NC 28208 24