An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Underground Storage Tank UpdateSmall Business & Local Government Assistance Brian Christian Andy Gardner Division Director Section Manager

  2. SBLGA Offers: • Technical Compliance Assistance • One to One Help • Compliance Tools • Free & Confidential

  3. SBLGA PROGRAMS • Site Visit Program • Regional Staff • Advisory and Advocacy Groups • The Advocate Newsletter

  4. Site Visit Program • Free to Business Owner • Conducted by contractor hired by the SBLGA Section • Completes a 62 point checklist • Owner receives a report – Enforcement does not

  5. Getting Help • Hotline • 1-800-447-2827 • M-F 8:00am-5:00pm • www.TexasEnviroHelp.org • Office & Site Visits

  6. SBLGA: Local Staff Availablemap of TCEQ regions • We have Staff available to assist in each of the 16 TCEQ Regions • Publication GI-002A has contact information for our region staff

  7. EnviroMentor Program • Technical Assistance • Volunteer Professionals • Consultants • Engineers • Lawyers • Operators

  8. Information Resources • The Advocate • Rule Change Outreach • Compliance Initiatives • Workshops & Seminars • Online & Print Publications

  9. UST Current Events • Federal UST rule changes • Operator Training • 3 year inspection cycle • Common violations • Penalty calculations • Stage I & II rule changes

  10. 40 CFR Part 280 • Rule changes proposed in Nov 2011 • Comment period closed in Apr 2012 • No news from EPA on when rules will be effective • Keep watching EPA & TCEQ websites for updates

  11. Operator Training • Deadline August 8, 2012 • Training offered on-line • Registration letters • Make sure TCEQ knows you took the training

  12. 3 Year Inspection cycle • Best option is to be in compliance before the investigation • Sign up for a site visit before the next investigation

  13. Common Violations • Not doing Inventory Control • No proof of tank test results – broken printer • No corrosion protection in sumps with water • No 3 year cathodic protection test • No documentation of tank material • No overfill documentation • No records

  14. Clean and Dry Flexible Connector

  15. Corrosion Protection

  16. Spill Containment 60 Day Inspection: • Removal liquid & debris in 96 hours • Document proper disposal of liquid & debris • Keep a log sheet to verify • Spill bucket & lids must be liquid tight

  17. Overfill Documentation • Visual Verification • Original Installation Records • 3rd Party Contractor • Photographs • Letter from 3rd party contractor

  18. Delivery Certificate • Current Delivery Certificate • Required to be renewed every 12 months, or within 30 days of change of ownership • Penalty for receiving motor fuel without current, valid delivery certificate isup to $500 per fuel drop

  19. Penalty Calculations • Many factors • Amount of throughput • Compliance History • Avoided Costs • Good faith reduction (25%) • Deferral for agreed order (20%)

  20. Stage II Vapor Recovery • ORVR declared to be in widespread use by EPA • Texas rules are finalized and decommissioning may begin on May 16th! • Deadline for removal is August 31, 2018 • Decommissioning Procedures

  21. Stage II Vapor Recovery • Notification required • Form 20689 – available on agency websites • 30 days prior to decommissioning AND • 24 – 72 hours prior to decommissioning • Decommissioning completion notice within 10 days • FAQs on website • Maintain Stage II system until it’s removed – testing, maintenance, daily logs

  22. Stage I Vapor Recovery • Rules proposed earlier this year • Improved consistency with federal Stage I requirements • Testing requirements • Throughput limits • Comments due May 12th

  23. Quick Review • 3 year inspections will continue • Site visit can help you prepare for an investigation • Submit Operator training documentation • Watch for federal UST rule changes • Look at your compliance records • Stage II decommissioning process on website • Stage I comments due May 12th

  24. How do I stay in Compliance? • RG-475 – PST Super Guide • SBLGA Hotline • SBLGA Website • Local SBLGA staff • Registered UST Contractor/Service Provider