1 / 7

Use of Manual SCED Executions and Offsets and the Calculation of GTBD

Use of Manual SCED Executions and Offsets and the Calculation of GTBD. David Maggio ERCOT, Real-Time Market Integration. Use of Manual Executions and Offsets.

hali
Télécharger la présentation

Use of Manual SCED Executions and Offsets and the Calculation of GTBD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Use of Manual SCED Executions and Offsets and the Calculation of GTBD David Maggio ERCOT, Real-Time Market Integration

  2. Use of Manual Executions and Offsets • During the first two months following the transition to the Nodal Market, there have been periods in which ERCOT Operators have had to utilize manual SCED executions and offsets • Off-cycle SCED executions are typically used to help the following: • Exhaustion of Regulation • Frequency issues (i.e. Resource Start-up and Shut-down or a unit trip) • Congestion issues (i.e. following the activation of a new constraint) • Manual SCED offsets are typically used to help the following • Exhaustion of Regulation • Accounting for Large Schedule Changes (i.e. DC Tie Schedules)

  3. Trend of Manual Execution and Offsets Since Go-Live

  4. Use of Manual Executions and Offsets • The amount of manual SCED executions and offsets has decreased significantly since the middle of December • Improvements to the Generation-to-be-Dispatched (GTBD) calculation may decrease the need for Operators to use offsets • Using the short-term load forecast (STLF) as opposed to the medium-term load forecast (MTLF) • Considering of DC Tie schedule changes • ERCOT Operators will still likely need to take these manual actions as a result of the scenarios previously mentioned

  5. Calculation of GTBD • The Generation-to-be-Dispatched (GTBD) value is used by SCED as the Generation Requirement • The sum of Resource base-points should equal to GTBD honoring all constraint functions (Energy Offer Curves, system congestion, etc…) • GTBD is calculated as: (Sum of Generation) + K1*(10*65.3*(Scheduled Freq. – Actual Freq.) – K2*(net non-conforming load – net filtered non-conforming load) + K3*(5*Predicted Load Ramp Rate)

  6. Market Trials Tuning of GTBD • The K factors were tuned with AREVA Staff as part of market trials during the Full-System Market and Reliability testing • The factors were chosen based on what numbers appeared to give ERCOT the best frequency control • The resulting K factors used at Go-Live were: • K1 = 2 • K2 = 0 • K3 = 1.2 • The was concern about using a single 4 second snapshot of non-conforming for GTBD, so K2 was left at 0

  7. Continued Tuning of GTBD • Following the transition to the Nodal Market, some changes were to both the K factors and the calculation of GTBD • On December 10th, K1 was changed from 2 to 0 • Like K2, there was concern with using a 4 second snapshot of frequency deviation to determine a 5 minute SCED base-point • On January 26th, the GTBD calculation was changed to calculate the predicted load ramp rate using the STLF (5-minute granularity) as opposed to the MTLF (1-hour granularity) • The MTLF is not able to capture intra-hour load changes. • On January 26th, K3 was changed from 1.2 to 1.1 • This change was made as a result of the GTBD calculation change of the 26th

More Related