1 / 45

Work Zone Impacts

Work Zone Impacts . Module 5. What is a WZ Impact Assessment ?. WZ Impact Assessment is the process of understanding the safety and mobility impacts of a road construction or maintenance project. Basic Concept . Determine impacts of project? Acceptable? If yes, no problem

hana
Télécharger la présentation

Work Zone Impacts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Work Zone Impacts Module 5

  2. What is a WZ Impact Assessment? WZ Impact Assessment is the process of understanding the safety and mobility impacts of a road construction or maintenance project

  3. Basic Concept • Determine impacts of project? • Acceptable? If yes, no problem • Unacceptable? (Significant project) • Can strategy be found to mitigate impacts to acceptable level? • Yes – develop TMP • No – determine best strategy • Advise stakeholders of possible problems

  4. WZ Impacts Considerations • Maximizing Safety • Road Users • Workers • Maximizing mobility and accessibility • Road user costs • Emergency services • Businesses • Constructability • Building projects effectively and efficiently

  5. Benefits of Assessing Impacts Identify and understand all impacts of the project Identify “significant projects” and determine suitable TMP Aid in identifying and evaluating alternative strategies Monitor and manage WZ impacts during construction

  6. Mobility Impacts • Mobility Issues • Delay • Reduced quality of life issues • Significant Projects – agency definition • Reduced Speeds • Queues and complete stoppages • Freight Interference • Travel time reliability – biggest concern • Delayed deliveries • Unanticipated costs • Emergency response

  7. Causes of Recurring Congestion

  8. Non-recurring Congestion

  9. Safety Impacts • Road user exposure to hazards • Will staging create safety hazards greater than existing? • Worker exposure to traffic • Staging allow for positive protection? • Geometrics during phases • Availability of law enforcement • Speed reduction necessary/considered?

  10. Business Impacts • Access • Temporary entrances • Signing • Pavement • Advance notification of phase changes • Keep owners informed • Work Schedules • Christmas shopping season • Weekends

  11. Residential Access Impacts • Keep residents informed as project begins and progresses • Neighborhood association meetings, newsletters, mailings, etc. • Maintain access if possible

  12. Incident Response Impacts • Ensure access to all areas for emergency vehicles • Hospitals nearby? • Trauma centers? • Plan to provide access within work site • Identify alternate routes • Pre-sign for use during incidents?

  13. Transit Impacts • Transit route through project? • Bus stops • Alternate routes available • Include in PR information

  14. Pedestrian Impacts • MUTCD Part 6D: • If project affects the movement of pedestrians, adequate pedestrian access and walkways shall be provided.

  15. Impact Assessment Proactive versus reactive Use early in the TMP Development process to identify and estimate the magnitude of the impacts Assess impacts on regional basis Use assessment to help evaluate various strategies for mitigating impacts Possibly use assessments to justify TCP revisions after award of project

  16. Goal A good impact assessment process should keep agency from being surprised after project is underway – when it is too late to consider strategies to reduce impacts.

  17. Mobility Impact Assessment Tools • Historical knowledge – “Lane closures do not cause backups on this segment of road…” • Various levels of tools for more detailed analysis • Sketch Planning Tools • Travel Demand Models • Traffic Signal Optimization Tools • Macroscopic Simulation Models • Mesoscopic Simulation Models • Microscopic Simulation Models

  18. WZ Analysis Tool Model Spectrum

  19. Transportation Model Approaches macro meso micro

  20. MacroscopicDelay Estimation Tools • Basic Concept • Special-purpose delay estimators for work zones • Examples: QuickZone, DELAYE, QUEWZ-98 • Strengths • Relatively easy-to-use, rapid analysis • Weaknesses • Limited capability beyond modeling simple “pipeline” analyses • High-level analysis macro

  21. MacroscopicRegional Planning Models • Basic Concept • Steady-state liquid flow • Examples: TRANPLAN, EMME/2, TransCAD, others • Strengths • Can handle very large networks (metro areas) • Weaknesses • Not time sensitive • Complex models, relatively expensive to build and maintain macro

  22. Mesoscopic • Basic Concept • Particle Flow • Vehicles are located on roadways but not specific lanes • Examples: DYNASMART-P, DYNAMEQ • Strengths • Can model sub-regional areas in major metropolitan areas • Weaknesses • Not detailed enough for some operational strategies (e.g., complex signal control) • Model complexity is high, data and calibration resources are significant

  23. Microscopic • CORSIM, VISSIM, and others • Model individual vehicle movements • Requires extensive resources to establish and calibrate • Usually reserved for large and complex projects unless existing model can be utilized

  24. Work Zone Analysis Primer • Aid in selection of the correct tool to use in the analysis • Provide guidance to reviewer to ensure appropriate tool was selected for project

  25. Work Zone Modeling and Simulation • Volume IX • Case studies • Aid for analysts

  26. How Should Results of Assessment Be Utilized? • Formulate policies • Identify strategies that will minimize impacts • Identify critical issues to address in development of TMP • Alternate route availability • Effects on businesses and residents

  27. Results Used to Formulate Policy

  28. Ohio DOT MOT/PLC Policy

  29. TMP Development Process Identify Early in Process Analyzing Strategies

  30. MNDOT Specific – Fig. 1

  31. Impacts Assessment at Project Level • Consider WZ impacts in the assessments that are performed during alternatives evaluations. • Allocate sufficient funds • Address impacts of multiple projects

  32. Work Zone Impacts Assessment During Preliminary Engineering • Compile project /WZ Scope Information for Alternatives • Assess WZ Impacts of Alternatives at a Screening Level • Analyze Potential Impacts (optional) • Identify WZ Management Strategies • Perform Plan/Program Level WZ Impacts Assessment • Compile Planning-Level Work Zone Strategy

  33. Compile project /WZ Scope Information for the Alternatives • The major categories of information that may be needed include the following: • Project Scope • Roadway/Traffic Characteristics • Other Influencing Factors

  34. Identify WZ Management Strategies • Issues To Be Addressed In Identifying WZ Management Strategies: • TTC Strategies • TO and PI Strategies. • Coordination Strategies with Other Projects. • Costs for the Management Strategies

  35. How to Incorporate WZ Impacts Assessments During Design • Compile Preliminary Engineering Materials • Reassess WZ Impacts • Develop/Recommend Final Construction Staging and TMP • Advertise and Award Contract

  36. Work Zone Impacts Assessment During Construction Assess the impact of any proposed changes prior to the start of work Implement the TMP. Actively monitor and manage work zone impacts during construction. Revise the TMP and implement appropriate revisions, if necessary. Document any findings or lessons for use in performance assessments.

  37. Example ChecklistDDOT

  38. Example ChecklistDDOT Guide

  39. Example ChecklistDDOT Guide

  40. Example ChecklistDDOT Guide

  41. Michigan TMP Template

  42. Michigan TMP Template http://www.ops.fhwa.dot.gov/wz/resources/final_rule/mdot_tmp_template/mdot_tmp_template.pdf

  43. Review and Discussion • When should the Impacts Assessment take place in the TMP process? • Does your state have a procedure in place to assure impacts are factored in to the project planning and design?

More Related