An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pilot ProjectIntra-hour energy exchange tests NEPOOL Markets Committee September 20, 2004 Harry Tom ISO-NE Markets Development

  2. Presentation Overview • Estimated Cost of Pilot Test Transactions • Limit Cost Exposure to Participants • Alternate Cost Allocation Method • Objectives of Pilot • Proposed Timeline of Pilot • Other items

  3. Estimated Cost of Pilot Test Transactions • Using Roseton and Sandy Pond proxy bus data from November 2003 • In accordance with Pilot Project Description: • Chose Tuesday/Wednesday • Scheduled flows between HE11-HE14 • Total Test energy of 1,600MWhs • The lowest net cost would have been $1,649 • The highest net cost would have been $10,907

  4. Limiting Cost Exposure to Participants • Estimated costs are based upon historical data (price effect of power flows not accounted for) • Limit cost of actual tests • Curtail Pilot transaction if price separation exceeds $50/MWh • Test power (1,600 MWhs) cost to be no greater than $80,000

  5. Alternate Cost Allocation Method GOAL – gain needed information from empirical testing with minimal impact on Participants PROPOSAL - broaden the allocation • Utilize method similar to Inadvertent Energy Revenue charges and credits • Allocate and charge to RTLO and RTGO over all locations • Incorporated into Pilot Project Description document

  6. Objectives of Pilot • Identify operations issues associated with intra-hour short term exchanges of energy • Evaluate tools and data needed to facilitate intra-hour exchanges • Observe the effect of intra-hour energy exchanges on all Proxy Bus prices • Collect information and issue report on Pilot tests • Evaluate information in context of any future activities with respect to intra-hour energy exchanges

  7. Proposed Timeline • Develop Pilot and seek Market Participant approvals – August 2004/September 2004 • FERC Filing – October 2004 • Conduct Pilot testing – December 2004 – January 2005 • Evaluate Pilot program – December 2004 – June 2005 • Determine next steps

  8. Other items • Provide information on Proxy Bus definition

  9. Questions