An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MDT Status report Stato costruzioni e milestones Commissioning al CERN Stato HV e LV Test beam 2004 M. Livan CSN1 Assisi 23-09-2004

  2. Stato produzione 31/8/04 CSN1 Assisi 23-09-2004

  3. Sarà spostata in avanti di 6 mesi Stato produzione 31/8/04 CSN1 Assisi 23-09-2004

  4. New RFI Milestones (not official) CSN1 Assisi 23-09-2004

  5. Stato produzione 31/8/04 CSN1 Assisi 23-09-2004

  6. MDT - Frascati Attivita’ di costruzione : • Completata produzione (94 MDT BML , restano 2 spares da costruire) • Montato sistema gas 96% delle camere • Turni per commissioning al CERN ripresi il 6 settembre • Integrate ad inizio settembre 5 stazioni • Stazioni integrate in totale 10 + 1 stazione con Mod0 Piano di Attivita’ fino a fine 2004 (concordato con gruppi RPC e CERN) : settembre 10 stazioni BML ottobre 10 stazioni BML novembre 10 stazioni BML dicembre 10 stazioni BML CSN1 Assisi 23-09-2004

  7. 4 persone x 5 mesi MDT - Frascati Piano di Attivita’ 2005 • Integrazione : 49 camere • Test cosmici : 94 camere • Installazione settore 13 (primavera) : 6 stazioni  5 persone x 3 settimane • Installazione restanti BML ( autunno ) : 88 stazioni  4 persone x 2.5 mesi CSN1 Assisi 23-09-2004

  8. BML (LNF): 3 fasi 1) Preparazione MDT Equipaggiamento finale Test Riparazioni (se necessario) Inserimento dati nel DataBase 2) Assemblaggio MDT-RPC Assemblaggio meccanico Test RPC Riparazioni (se necessario) Inserimento dati nel DataBase 3) Test con cosmici Presa dati Analisi dati Inserimento dati nel DataBase Infrastruttura e logistica organizzate dal gruppo CERN Manpower per MDT 1 Ing. Meccanico 1 Meccanico 1 Elettronico 1 Fisico Commissioning BML CSN1 Assisi 23-09-2004

  9. Schedule integrazione MDT-RPC CSN1 Assisi 23-09-2004

  10. BML-RPC Integration in BB5 CSN1 Assisi 23-09-2004

  11. BML-RPC Integration CSN1 Assisi 23-09-2004

  12. Stazioni completate CSN1 Assisi 23-09-2004

  13. Stato produzione 31/8/04 CSN1 Assisi 23-09-2004

  14. Stato produzione 31/8/04 CSN1 Assisi 23-09-2004

  15. BIL-R-M (Cs, Pv, Rm1, Rm3) • Cosenza • Fine filatura a ottobre • Pavia • 28 camere con gas, Faraday cage, mezzanini etc. • Gas test OK • 25 testate con cosmici in sede • 6 camere completamente equipaggiate • -> Spedite al CERN a fine Luglio • Fine assemblaggio a dicembre • Roma I • Fine assemblaggio: dicembre • Roma III • 40 camere con gas, Faraday cage, mezzanini etc. • Gas test OK • 35 testate con cosmici in sede CSN1 Assisi 23-09-2004

  16. BIL-R-M (Cs, Pv, Rm1, Rm3) • Programma di lavoro 2005 • Pavia e Roma I e Roma III • Conclusione dell’ installazione dei servizi in sede • Tutti i gruppi • Conclusione del commissioning delle camere al CERN (4 persone x 5 mesi) • Installazione BIL a partire da luglio (?) (4 persone x 2 mesi) CSN1 Assisi 23-09-2004

  17. BIL ( Cosenza, Pavia Roma I e III) Finalizzazione camere Roma Test previsti: Tenuta gas Alta tensione Noise Sensori (T, B) Test con cosmici (solo su alcune camere) Infrastruttura e logistica organizzate dal gruppo CERN Schedula a regime: 3 giorni lavorativi per camera lavorando in parallelo (critico) Manpower 2004 2 Tecnici 1 Fisico Manpower 2005 3 Tecnici 1 Fisico Commissioning BIL (Blg. 283) CSN1 Assisi 23-09-2004

  18. Camera equipaggiata a Pavia CSN1 Assisi 23-09-2004

  19. Blg. 283 CSN1 Assisi 23-09-2004

  20. Schedule Commissioning 283 Month Jul 04 Aug Sep Oct Nov Dec Jan 05 Feb Mar Apr May • Plan Ch. / Mon. 4 8 8 10 10 8 8 15 15 15 15 • Plan Total 4 12 20 30 40 48 56 71 86 101 116 • Done Ch. / Mon. 4 6 8 • Done Total 4 10 18 • Tech. 2 2 2 2 2 2 3 3 3 3 3 • Phys. 1 1 1 1 1 1 1 1 1 1 1 • Start up slower than foreseen Attualmente i lavori sono quasi on schedule - 18 Camere completate a fine settembre 4 camere completamente testate - mancano ELMB, RasMux, CSM, tools per piattaforme di allineamento CSN1 Assisi 23-09-2004

  21. Commissioning BIS-BIL Schedule presentata dal responsabile CERN alla ultima Muon Week CSN1 Assisi 23-09-2004

  22. Sistema LV • Test con camere connesse in parallelo a due a due effettuato ad H8 a partire dal 14 giugno, dopo aver sistemato le connessioni di terra. Al momento le 12 camere delle torri Barrel ed Endcap continuano la presa dati connesse in parallelo. • L’analisi dati non è ancora terminata. Una prima valutazione delle prestazioni del sistema e’ stata fatta paragonando gli spettri di due run presi prima e dopo la connessione in parallelo. CSN1 Assisi 23-09-2004

  23. First look at LV test runs Compare hodo runs: Run 600182, taken on June 7th Run 600364, taken on June 17th Sara Diglio & Manuela Cirilli BIL Saleve CSN1 Assisi 23-09-2004

  24. First look at LV test runs Compare hodo runs: Run 600182, taken on June 7th Run 600364, taken on June 17th Sara Diglio & Manuela Cirilli BIL Jura CSN1 Assisi 23-09-2004

  25. First look at LV test runs Compare hodo runs: Run 600182, taken on June 7th Run 600364, taken on June 17th Sara Diglio & Manuela Cirilli BML Saleve CSN1 Assisi 23-09-2004

  26. First look at LV test runs Compare hodo runs: Run 600182, taken on June 7th Run 600364, taken on June 17th Sara Diglio & Manuela Cirilli BML Jura CSN1 Assisi 23-09-2004

  27. First look at LV test runs Compare hodo runs: Run 600182, taken on June 7th Run 600364, taken on June 17th Sara Diglio & Manuela Cirilli BOL Saleve CSN1 Assisi 23-09-2004

  28. First look at LV test runs Compare hodo runs: Run 600182, taken on June 7th Run 600364, taken on June 17th Sara Diglio & Manuela Cirilli BOL Jura CSN1 Assisi 23-09-2004

  29. Sistema LV Dagli spettri si puo’ notare che i fronti di salita sono uguali per i due run, quindi non c’e’ deterioramento dei T0. Pero’ c’e’ anche un incremento degli hit fuori tempo, che puo’ essere dovuto alle differenti condizioni di fascio o a rumore, e in questo caso potrebbe essere stato causato da fattori esterni alle camere, o dalle connessioni in parallelo. L’analisi per stabilire la genesi degli hit fuori tempo e’ in corso. L’incremento comunque e’ modesto, e non tale da pregiudicare le prestazioni delle camere, che infatti rimarranno collegate in parallelo fino alla fine del testbeam. CSN1 Assisi 23-09-2004

  30. Sistemi HV e LV • -Elettronica HV: • approvazione Direttivo di ottobre.Gara conclusa a febbraio. -Consegna preproduzione entro maggio 2005 • Test rad-hard e B a metà 2005 • Ultime consegne entro metà 2006 • Parte del budget tedesco gia’ disponibile al Cern. • Elettronica LV: • approvazione Direttivo di novembre.Gara conclusa a marzo. -Consegna preproduzione entro giugno 2005 • Test rad-hard e B a metà 2005 • Ultime consegne entro metà 2006 • Cavo HV: • gara approvata da G.E a fine maggio e chiusa il 27 settembre. • Consegna: 40% a gennaio, 100% a marzo • Cavo LV: • Budget disponibile a fine anno. Gara al CERN inizio 2005

  31. Milestones CSN1 Assisi 23-09-2004

  32. Setup dell’area di test H8 Endcap Barrel BOS TGCs MBPL Magnet CSC BIL su supporto rotante CSN1 Assisi 23-09-2004

  33. Setup • Barrel: • 6 camere MDT (2 BIL, 2 BML, 2 BOL) • Lettura completa con elettronica di FE e 1 MROD • 6 camere RPC (4 BML, 2 BOL): ¼ della torre di trigger equipaggiata con le nuove PAD Boards, 8 matrici di coincidenza • 2 camere ulteriori (BIL su supporto rotante e BOS con MDT+RPC) • Endcap • 6 camere MDT (2 EI, 2 EM, 2 EO) • FE completo, 1 MROD • 3 camere TGC (2 doppietti e 1 tripletto) • Barrel ed Endcap equipaggiati con il sistema di allineamento completo CSN1 Assisi 23-09-2004

  34. Barrel Stand BIL Rotante BML BOL CSN1 Assisi 23-09-2004

  35. Misure e test effettuati • Test del LV MDT nella configurazione per ATLAS (2 camere/canale LV) • Allineamento del barrel: movimenti controllati delle camere con rotazioni fino a 8 mrad • Allineamento dell’endcap: calibrazione assoluta dei sensori • Scan in soglia per MDT ed RPC (rumore, risoluzione, efficienza vs soglia) • Integrazione dei subdetector in presa dati combinata • Integrazione con gli altri subdetector di ATLAS (Inner detector+Calorimetri) per il test beam combinato • Studi di tracciamento e ricostruzione (efficienza, risoluzione in sagitta, confronti con la simulazione Geant4). Sviluppo ed utilizzo al test beam del framework per l’offline di ATLAS CSN1 Assisi 23-09-2004

  36. Risultati preliminari Misure di impulso e sagitta Sagitta vs impulso CSN1 Assisi 23-09-2004

  37. Conclusioni • Assemblaggio delle camere quasi terminato • Installazione servizi adesso procede speditamente • Nuova schedula installazione (non ufficiale) con ritardo di circa 6 mesi • Schedule commissioning molto aggressiva ma fattibile • Nuova schedule integrazione MDT-RPC concordata fra CERN-Gruppi MDT e Gruppi RPC • Notevole contributo dei gruppi italiani al test beam (hardware, software, DAQ, presa dati analisi) CSN1 Assisi 23-09-2004