Missile Defense Agency EVM Update

Missile Defense Agency EVM Update. Presented to NDIA/PMSC January 29, 2009 Dave Melton. CONTRACT PERFORMANCE SUMMARY REPORT JAN 09. Nov-2008. Dollars in millions except where noted. Data as of month-end. EVM Integration. Contract & Baseline Maintenance.

haruki
Télécharger la présentation

Missile Defense Agency EVM Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Missile Defense AgencyEVM Update Presented to NDIA/PMSC January 29, 2009 Dave Melton

  2. CONTRACT PERFORMANCE SUMMARY REPORT JAN 09 Nov-2008 Dollars in millions except where noted Data as of month-end EVM Integration Contract & Baseline Maintenance Earned Value Management (EVM) Data FY 09 / 10 Contract LOE % Budget (of Work VAC: DO's Program / Base % 6 mo CPI 6 mo Remaining and Schedule IBR: Most Recent Target (Overrun) / Contract (CBB) Complete CPI Trend SPI Planned) Budget Impact Risk and Projected Price Underrun ($ / %) Program 1 Dec-08 TBD $4.0B $3.6B 92% 1.04 ? 1.03 ($84) -2% 43% Minimal Yes / / Dec-07 Mar-09 $1.6B $1.4B 78% 0.92 ? 1.01 $0 0% 24% Minimal No / / Program 2 Aug-08 / TBD $656 $571 26% N/A N/A N/A ($12) -2% 18% Minimal No / Program 3 Oct-08 TBD $248 $234 62% 1.09 ? 0.96 ($4) -2% 16% Minimal No / / Program 4 Apr-08 TBD $1.3B $1.1B 82% 1.01 ? 0.92 $0 0% 25% Minimal Yes / / Program 5 Nov-09 Mar-09 $1.3B $1.0B 74% 0.94 ? 0.94 ($1) 0% 69% Minimal Yes / / Program 6 Dec-06 May-09 $16.1B $14.6B 87% 1.00 ? 0.97 ($1.2B) -8% 31% Minimal Yes / / Program 7 Apr-08 Feb-08 $6.3B $5.8B 15% 1.01 ? 0.94 ($11) 0% 31% Minimal Yes / / Program 8 Sep-08 Apr-09 $730 $664 85% 1.04 ? 0.97 $0 0% 54% Minimal Yes / / Program 9 Jul-08 Dec-08 $378 $316 67% / Program 10 0.96 ? 0.93 ($8) -3% 40% Minimal No / Program 11 Oct-06 TBD $1.9B $1.0B 75% 0.39 ? 1.05 ($373) -36% 25% Significant Yes / / Program 12 Oct-08 TBD $1.2B $1.1B 86% 0.94 ? 1.19 ($64) -6% 21% Moderate No / / Program 13 Nov-07 TBD $4.9B $4.7B 91% 0.87 ? 0.97 ($298) -6% 23% Moderate Yes / / Program 14 Aug-07 Mar-09 $117 $101 71% 1.23 ? 0.98 $0 0% 42% Minimal No / / DOB Projected Overrun TOTAL MDA Programs $40.7B $36.2B ($2.1B) / -6% Documentprimarilyreflects prime contractor EVM data and narrative information through month-end Nov 08. Where appropriate, DOBS has provided updated information through 5 Jan 09. * Oct 08 data is reported. Nov data is delayed due to CY08 close out activities

  3. Program 10 Details $50M $40M $30M $20M $10M $0M -$10M -$20M -$30M -$40M -$50M Jul-06 Jul-07 Jul-08 Jan-06 Jan-07 Jan-08 Jan-09 Nov-05 Mar-06 Sep-06 Nov-06 Mar-07 Sep-07 Nov-07 Mar-08 Sep-08 Nov-08 Mar-09 May-06 May-07 May-08 May-09 Cum CV Cum SV 10% Threshold MDA DOB VAC Key Cost/Schedule Variance Drivers • Cost: cum CV is -$7.1M. Driven by Hover Test Bed efforts, due to increased procurement costs, costs associated with late drawing release, inadequate subcontractor task planning, and increased program management oversight • Schedule: SV of -$1M is minimal and is due primarily to late delivery of Government Furnished Equipment (GFE) Projected Variance at Completion (VAC) • DOB VAC is -$8.3M. Calculation reflects increased efforts required to meet Hover Test Bed schedule Cost and Schedule Variance Chart Impacts • Hover Test schedule slipped due to Hover Test Vehicle power conditioning unit, Flight Software anomaly, IMU software review and most recent unfavorable weather testing conditions • Potential cost overrun of roughly $11.5M due to increased efforts to meet Hover Test Bed schedule. Path Forward • Hover Test completed XXX 2008 at the National Hover Test Facility • Re-planning program efforts

  4. Program 10 EV Budget Integration Chart

  5. Current Noteworthy MDA EVM Initiatives • DCMA Support • Overarching Memorandum of Agreement with DCMA • MDA Review of DCMA Report Quality • EVM Health • CPR/CFSR Quality Review • Other Quality Reviews (IMS, Award Fee, Contract Requirements) • IBR Process

  6. Current Noteworthy MDA EVM Initiatives • Overarching Memorandum of Agreement with DCMA • DCMA SSOM • LOE Versus Discrete Metrics • CPR/CFSR Reconciliation • IEAC (not metric driven) • IBR Support (Planning, Execution, and Follow-up)

  7. Current Noteworthy MDA EVM InitiativesMDA Quality Review of DCMA Reports

  8. MDA EVM Process – EVM Health • MDA EVM Health Factors help identify areas for management attention

  9. MDA EVM Process – EVM Health

  10. MDA EVM Process – EVM Health

  11. Program 5 EVM Contract Requirements: GREEN is downgraded to YELLOW. Contractor's CPR and CFSR are not compliance with DIDs. There is no CPR/CFSR reconciliation. Contractor has Y inadequate understanding of EVM contract requirements. Baseline Development / IBR / Baseline Maintenance: An IBR was conducted in Apr 08. Although contractor previously committed to a 6-month rolling wave IBR, the most recent IBR Y focused only on a small piece of the program. Analysis/ Integration: GREEN is downgraded to YELLOW. Insufficient cost/schedule integration. Contractor cannot produce/identify a critical path. Contractor cannot articulate Y estimates to complete, thus EACs are questionable. EV Management Systems: YELLOW is downgraded to RED. DCMA continues to produce Y additional CARs each month against contractor EVMS process. Training: GREEN is downgraded to YELLOW. Training is needed on the following: EVM contract requirements checklist, EVM analysis process particularly aspects of Format 5 Variance Y Analysis requirements, and the planning and scheduling process. MDA EVM Process – EVM Health

  12. Current Noteworthy MDA EVM Initiatives • MDA Review of CPR/CFSR Quality • CPR/CFSR thoroughness per DID • Comparison of CPR/CFSR to CDRL Requirements • Management Information Quality • CPR Format 5 Quality • Examples: forward looking analysis, EAC Range (Best, Worst, Most Likely) • CPR Format 4 • Accuracy

  13. Current Noteworthy MDA EVM InitiativesMDA Review of CPR/CFSR Quality SUMMARY OF CPR/CFSR REPORT QUALITY REVIEWS CPR CFSR MDA Overall CDRL DID Management Overall CDRL DID Management PROGRAMS Assessment Compliance Compliance Information Assessment Compliance Compliance Information Quality Quality Program 1 Program 2 Program 3 Program 4 Program 5 Program 6 Program 7 Program 8 Program 9 Program 10 Program 11 Program 12