Chapter 3: Linear Programming Modeling Applications

DESCRIPTION

Chapter 3: Linear Programming Modeling Applications. Jason C. H. Chen, Ph.D. Professor of MIS School of Business Administration Gonzaga University Spokane, WA 99223 chen@jepson.gonzaga.edu. Linear Programming (LP) Can Be Used for Many Managerial Decisions:. 1. Manufacturing applications

1 / 66

Télécharger la présentation

Chapter 3: Linear Programming Modeling Applications

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. Chapter 3:Linear Programming Modeling Applications Jason C. H. Chen, Ph.D. Professor of MIS School of Business Administration Gonzaga University Spokane, WA 99223 chen@jepson.gonzaga.edu

  2. Linear Programming (LP) Can Be Used for Many Managerial Decisions: • 1. Manufacturing applications • Product mix • Make-buy • 2. Marketing applications • Media selection • Marketing research • 3. Finance application • Portfolio selection • 4. Transportation application and others • Shipping & transportation • Multiperiod scheduling

  3. For a particular application we begin with the problem scenario and data, then: • Define the decision variables • Formulate the LP model using the decision variables • Write the objective function equation • Write each of the constraint equations • Implement the model in Excel • Solve with Excel’s Solver

  4. Manufacturing ApplicationsProduct Mix Problem: Fifth Avenue Industries • Produce 4 types of men's ties • Use 3 materials (limited resources) Decision: How many of each type of tie to make per month? Objective: Maximize profit

  5. Resource Data Labor cost is $0.75 per tie

  6. Product Data

  7. Material Requirements(yards per tie)

  8. Decision Variables S = number of silk ties to make per month P = number of polyester ties to make per month B1 = number of poly-cotton blend 1 ties to make per month B2 = number of poly-cotton blend 2 ties to make per month

  9. Profit Per Tie Calculation Profit per tie = (Selling price) – (material cost) –(labor cost) Silk Tie Profit = $6.70 – (0.125 yds)($20/yd) - $0.75 = $3.45 per tie

  10. Objective Function(in $ of profit) Max 3.45S + 2.32P + 2.81B1 + 3.25B2 Subject to the constraints: Material Limitations(in yards) 0.125S < 1,000 (silk) 0.08P + 0.05B1 + 0.03B2< 2,000 (poly) 0.05B1 + 0.07B2< 1,250 (cotton)

  11. Min and Max Number of Ties to Make 6,000 < S < 7,000 10,000 < P < 14,000 13,000 < B1 < 16,000 6,000 < B2 < 8,500 Finally nonnegativity S, P, B1, B2 > 0

  12. LP Model for Product Mix Problem Max 3.45S + 2.32P + 2.81B1 + 3.25B2 Subject to the constraints: 0.125S < 1,000 (yards of silk) 0.08P + 0.05B1 + 0.03B2 < 2,000 (yards of poly) 0.05B1 + 0.07B2 < 1,250 (yards of cotton) 6,000 < S < 7,000 10,000 < P < 14,000 13,000 < B1 < 16,000 6,000 < B2 < 8,500 S, P, B1, B2 > 0 Go to file 3-1.xls

  13. Go to file 3-1.xls

  14. Marketing applicationsMedia Selection Problem: Win Big Gambling Club • Promote gambling trips to the Bahamas • Budget: $8,000 per week for advertising • Use 4 types of advertising Decision: How many ads of each type? Objective: Maximize audience reached

  15. Data

  16. Other Restrictions • Have at least 5 radio spots per week • Spend no more than $1800 on radio Decision Variables T = number of TV spots per week N = number of newspaper ads per week P = number of prime time radio spots per week A = number of afternoon radio spots per week

  17. Objective Function (in num. audience reached) Max 5000T + 8500N + 2400P + 2800A Subject to the constraints: Budget is $8000 800T + 925N + 290P + 380A < 8000 At Least 5 Radio Spots per Week P + A > 5

  18. No More Than $1800 per Week for Radio 290P + 380A < 1800 Max Number of Ads per Week T < 12 P < 25 N < 5 A < 20 Finally nonnegativity T, N, P, A > 0

  19. LP Model for Media Selection Problem Objective Function Max 5000T + 8500N + 2400P + 2800A Subject to the constraints: 800T + 925N + 290P + 380A < 8000 P + A > 5 290P + 380A < 1800 T < 12 P < 25 N < 5 A < 20 T, N, P, A > 0 Go to file 3-3.xls

  20. Go to file 3-3.xls

  21. Finance applicationPortfolio Selection: International City Trust Has $5 million to invest among 6 investments Decision: How much to invest in each of 6 investment options? Objective: Maximize interest earned

  22. Data

  23. Constraints • Invest up to $ 5 million • No more than 25% into any one investment • At least 30% into precious metals • At least 45% into trade credits and corporate bonds • Limit overall risk to no more than 2.0

  24. Decision Variables T = $ invested in trade credit B = $ invested in corporate bonds G = $ invested gold stocks P = $ invested in platinum stocks M = $ invested in mortgage securities C = $ invested in construction loans

  25. Objective Function (in $ of interest earned) Max 0.07T + 0.10B + 0.19G + 0.12P + 0.08M + 0.14C Subject to the constraints: Invest Up To $5 Million T + B + G + P + M + C < 5,000,000

  26. No More Than 25% Into Any One Investment T < 0.25 (T + B + G + P + M + C) B < 0.25 (T + B + G + P + M + C) G < 0.25 (T + B + G + P + M + C) P < 0.25 (T + B + G + P + M + C) M < 0.25 (T + B + G + P + M + C) C < 0.25 (T + B + G + P + M + C)

  27. At Least 30% Into Precious Metals G + P > 0.30 (T + B + G + P + M + C) At Least 45% Into Trade Credits And Corporate Bonds T + B > 0.45 (T + B + G + P + M + C)

  28. Limit Overall Risk To No More Than 2.0 Use a weighted average to calculate portfolio risk 1.7T + 1.2B + 3.7G + 2.4P + 2.0M + 2.9C< 2.0 T + B + G + P + M + C OR 1.7T + 1.2B + 3.7G + 2.4P + 2.0M + 2.9C < 2.0 (T + B + G + P + M + C) finally nonnegativity: T, B, G, P, M, C > 0

  29. LP Model for Portfolio Selection Max 0.07T + 0.10B + 0.19G + 0.12P+ 0.08M + 0.14C Subject to the constraints: T + B + G + P + M + C < 5,000,000 (total funds) T < 0.25 (T + B + G + P + M + C) (Max trade credits) B < 0.25 (T + B + G + P + M + C) (Max corp bonds) G < 0.25 (T + B + G + P + M + C) (Max gold) P < 0.25 (T + B + G + P + M + C) (Max platinum) M < 0.25 (T + B + G + P + M + C) (Max mortgages) C < 0.25 (T + B + G + P + M + C) (Max const loans) 1.7T + 1.2B + 3.7G + 2.4P + 2.0M + 2.9C < 2.0 (T + B + G + P + M + C) (Risk score) G + P > 0.30 (T + B + G + P + M + C) (precious metal) T + B > 0.45 (T + B + G + P + M + C) (Trade credits & bonds) T, B, G, P, M, C > 0 Go to file 3-5.xls

  30. Go to file 3-5.xls

  31. Employee Staffing ApplicationLabor Planning: Hong Kong Bank Number of tellers needed varies by time of day Decision: How many tellers should begin work at various times of the day? Objective: Minimize personnel cost

  32. Total minimum daily requirement is 112 hours

  33. Full Time Tellers • Work from 9 AM – 5 PM • Take a 1 hour lunch break, half at 11, the other half at noon • Cost $90 per day (salary & benefits) • Currently only 12 are available

  34. Part Time Tellers • Work 4 consecutive hours (no lunch break) • Can begin work at 9, 10, 11, noon, or 1 • Are paid $7 per hour ($28 per day) • Part time teller hours cannot exceed 50% of the day’s minimum requirement • (50% of 112 hours = 56 hours)

  35. Decision Variables F = num. of full time tellers (all work 9–5) P1 = num. of part time tellers who work 9–1 P2 = num. of part time tellers who work 10–2 P3 = num. of part time tellers who work 11–3 P4 = num. of part time tellers who work 12–4 P5 = num. of part time tellers who work 1–5

  36. Objective Function (in $ of personnel cost) Min 90 F + 28 (P1 + P2 + P3 + P4 + P5) Subject to the constraints: Part Time Hours Cannot Exceed 56 Hours 4 (P1 + P2 + P3 + P4 + P5) < 56

  37. Minimum Num. Tellers Needed By Hour Time of Day F + P1> 10 (9-10) F + P1 + P2> 12 (10-11) 0.5 F + P1 + P2 + P3> 14 (11-12) 0.5 F + P1 + P2 + P3+ P4 > 16 (12-1) F + P2 + P3+ P4 + P5> 18 (1-2) F + P3+ P4 + P5> 17 (2-3) F + P4 + P5> 15 (3-4) F + P5 > 10 (4-5)

  38. Only 12 Full Time Tellers Available F < 12 finally nonnegativity: F, P1, P2, P3, P4, P5> 0

  39. LP Model for Labor Planning Min 90 F + 28 (P1 + P2 + P3 + P4 + P5) Subject to the constraints: F + P1> 10 (9-10) F + P1 + P2> 12 (10-11) 0.5 F + P1 + P2 + P3> 14 (11-12) 0.5 F + P1 + P2 + P3+ P4 > 16 (12-1) F + P2 + P3+ P4 + P5> 18 (1-2) F + P3+ P4 + P5> 17 (2-3) F + P4 + P5> 15 (3-4) F + P5 > 10 (4-5) F < 12 4 (P1 + P2 + P3 + P4 + P5) < 56 F, P1, P2, P3, P4, P5> 0 Go to file 3-6.xls

  40. Go to file 3-6.xls

  41. Transportation application and othersVehicle Loading: Goodman Shipping How to load a truck subject to weight and volume limitations Decision: How much of each of 6 items to load onto a truck? Objective: Maximize the value shipped

  42. Data

  43. Decision Variables Wi = number of pounds of item i to load onto truck , (where i = 1,…,6) Truck Capacity • 15,000 pounds • 1,300 cubic feet

  44. Objective Function (in $ of load value) Max 3.10W1 + 3.20W2 + 3.45W3 + 4.15W4 + 3.25W5 + 2.75W6 Subject to the constraints: Weight Limit Of 15,000 Pounds W1 + W2 + W3 + W4 + W5 + W6< 15,000

  45. Volume Limit Of 1300 Cubic Feet 0.125W1 + 0.064W2 + 0.144W3 + 0.448W4 + 0.048W5 + 0.018W6< 1300 Pounds of Each Item Available W1< 5000 W4< 3500 W2< 4500 W5< 4000 W3< 3000 W6< 3500 Finally nonnegativity: Wi > 0, i=1,…,6

  46. LP Model for Vehicle Loading Objective Function Max 3.10W1 +3.20W2 +3.45W3 +4.15W4 +3.25W5+2.75W6 Subject to the constraints: W1 + W2 + W3 + W4 + W5 + W6< 15,000 (Weight Limit) 0.125W1 + 0.064W2 + 0.144W3 +0.448W4 + 0.048W5 + 0.018W6< 1300 (volume limit of truck) Pounds of Each Item Available W1< 5000 (item 1 availability) W2< 4500 (item 2 availability) W3< 3000 (item 3 availability) W4< 3500 (item 4 availability) W5< 4000 (item 5 availability) W6< 3500 (item 6 availability) Wi > 0, i=1,…,6 Go to file 3-7.xls

  47. Go to file 3-7.xls

  48. Blending Problem:Whole Food Nutrition Center Making a natural cereal that satisfies minimum daily nutritional requirements Decision: How much of each of 3 grains to include in the cereal? Objective: Minimize cost of a 2 ounce serving of cereal

  49. Decision Variables A = pounds of grain A to use B = pounds of grain B to use C = pounds of grain C to use Note: grains will be blended to form a 2 ounce serving of cereal