An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DIRCO AND ARF PERFORMANCE AND FINANCIAL REPORTas at end of December 2015 (Quarter 3)Presentation to Portfolio Committee 17 FEBRUARY 2016

  2. Table of Contents • DIRCO reports on: 1.1 Performance information Quarter 3 1.2 Financial report Quarter 3 2. ARF Quarter 3

  3. Introduction • South Africa hosted FOCAC Summit from the 04 to 06 December 2015 with outcomes such as: Chinese investments of US$60 billion of which South Africa will receive US$10 billion for infrastructure, industrialisation and skills development • On 12 December 2015 the Parties to the United Nations Framework Convention on Climate Change (UNFCCC) unanimously adopted the Paris Agreement and a package of supporting decisions covering climate actions in the pre-and post 2020 periods. This is the successful conclusion of a four year negotiation process under the Durban Platform for Enhanced Action

  4. Introduction • Concluded South Africa's term as G77 Chair with notable success in the following areas: • The adoption of the Paris Agreement at Paris Climate Change Conference (COP21/CMP11) in December 2015 • The adoption of the 2030 Agenda on Sustainable Development with a set of 17 Sustainable Development Goals (SDGs) and 169 associated targets • Changes in the international arena: • Rapid weakening of rand against major currencies • Slow down of growth of China and impact on the global economic outlook • Plummeting oil prices

  5. Programme 1: Administration

  6. Programme 1: Administration

  7. Programme 1: Administration

  8. Programme 2: International Relations

  9. Programme 2: International Relations

  10. Programme 2: International Relations

  11. Programme 3: International Cooperation

  12. Programme 3: International Cooperation

  13. Programme 3.2:Continental Cooperation

  14. Programme 3: South –South and North –South Cooperation

  15. Programme 4: State Protocol services

  16. MPATManagement Performance Assessment Tool

  17. Areas assessed and Scoring Four Management Areas • Strategic Management • Governance and Accountability • Human Resources Management • Financial Management Scoring

  18. Comparison

  19. Key Performance Areas (KPAs)

  20. Key Performance Areas

  21. DIRCO Financial report: Quarter 3

  22. Vote Expenditure per programme (R’000)

  23. Vote Expenditure continued… • Total expenditure for the Department as at the end of the third quarter amounts to R4,520billion or 69.4% of the adjusted appropriation. • This expenditure is 1.0% higher than the projected expenditure for the period. • The higher than projected expenditure was mainly under Programmes 2, Programme 3 and Programme 4. In terms of economic classification, the high spending is visible mainly under compensation of employees and goods and services. • The details of the variances are discussed under each Programme.

  24. Programme 1: Administration (R’000)

  25. Programme 1 – Econ Classification (R’000)

  26. Programme 1 continued…. • Total expenditure for the Programme as at the end of the third quarter amounts to R865.8 million or 62.7% of the programme’s total appropriation. This expenditure is 14.3% lower than what had been projected for the period. • Reasons for the low spending: • Foreign fixed assets management Dar es Salaam - the project is behind schedule due to delay in clearance of crucial material at port of entry.

  27. Programme 2: International Relations (R’000)

  28. Programme 2 – Econ Classification (R’000)

  29. Programme 2 continued…. • Total expenditure for the Programme as at the end of the third quarter amounts to R 2,656 billion or 75.8% of the programme’s total appropriation. • This expenditure is 2.9% higher than projected expenditure for the period due to the depreciation of Rand against major foreign currencies.

  30. Programme 3: International Cooperation (R’000)

  31. Programme 3 – Econ Classification (R’000)

  32. Programme 3 continued…. • Total expenditure for the Programme as at the end of the third quarter amounts to R396.8 million or 75.4% of the programme’s total appropriation. • This expenditure is 8.6% higher than projected expenditure for the period due to the depreciation of Rand against major foreign currencies.

  33. Programme 4: State Protocol and Public Diplomacy (R’000)

  34. Programme 4 continued…. • Total expenditure for the Programme as at the end of the third quarter amounts to R263.9 million or 72.6% of the programme’s total appropriation. • Expenditure for this programme is 43.5% higher than what had been projected for the period. • Higher than projected expenditure is attributable to the expenditure relating to the hosting of the African Union Summit and Forum on China-Africa Cooperation summit.

  35. Programme 5: International Transfers (R’000)

  36. Programme 5 continued…. • Total expenditure for the Programme as at the end of the third quarter amounts to R338.3 million or 46.1% of the Programme’s total appropriation. • The expenditure is line with the projections

  37. Projected expenditure for the year (R’000)

  38. 2015/16 Forex analysis as at 31 December 2015 (R’000)

  39. African Renaissance Fund (ARF)

  40. ARF Performance report - Quarter 3

  41. ARF Performance report - Quarter 3

  42. ARF Financial report – Quarter 3

  43. ARF Financial report - Quarter 3 2015/16 Approved projects: (a) Technical support of the third General Elections of Burundi R38 031 000 (b) Timbuktu Manuscript R 7 201 000 (c) Cuban Medical Brigade in Sierra Leone R 3 985 000 (d) Transportation of Humanitarian Assistance to Madagascar R 195 000 (e) African Capacity Building Foundation R 1 609 000

  44. Thank you