An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. Progress Reports in ECE 4334 Chad A. B. Wilson, Ph.D. Director of Technical Communications Across the Curriculum

  2. An overview of today’s presentation on Progress Reports The Purpose The Format The Writing

  3. Your supervisor or client uses Progress Reports to help make decisions Lets your client, associate, or boss know where a project stands. Informs readers about work that has already been accomplished, problems that have been encountered and plans to solve them, as well as work that is not yet completed. Updates readers about budgetary and scheduling issues. Explains and justifies changes to either. What is your boss most interested in?

  4. Use lower-case Roman numerals A longer formal Progress Report will generally look like this: Report Body Project Summary (Purpose, Background) Work Accomplished to Date Work Remaining Problems Encountered Appraisal of Progress to Date Front Matter Letter of Transmittal Cover/Title Page Abstract Table of Contents List of Tables and Figures Back Matter References Appendices Use regular Arabic numerals

  5. Dear Dr. Trombetta: Enclosed you will find the latest progress report for the Energy Conversion project. The purpose of this project is to teach high school students about alternative/renewable energy through lab kits the team will create. This report goes into further detail regarding the purpose of the project and briefly summarizes past progress while focusing on the progress the team has made since October 25, 2008. Along with the projects goals and milestone progress, I have also included the projected schedule along with the current budget. As of November 13, 2008, the team has completed two additional milestones. Currently, there are six milestones completely finished with two additional milestones coming close to completion. The first milestone was achieved with an operational dynamo generating 1.5 V and 5.6 [mA] with a 10 [Ω] load. The second milestone was attained by using 1 V and 10 mA to charge a battery and power up a DC motor. The third and fourth milestone incorporated a windmill and a watermill separately to spin the dynamo to create 1.5 V. Lastly, the fifth milestone was reached with a working solar panel that generated 1.5 V and 200 mA and the sixth milestone integrated all of the components of the system to operate a load. I am pleased to report that the team is very close to completion and still within budget. The team assures you that the project will be completed on schedule and within budget by November 22, 2008. Sincerely, Chad A. B. Wilson, Ph.D. Director of Technical Communications Across the Curriculum University of Houston A letter of transmittal will generally accompany a formal progress report

  6. Title pages provide typical information Project title Type of document (e.g., Progress Report for the period…) Team number and members Course number and title Semester Date of submission

  7. Abstracts share the vital information Abstract The goal of the Energy Conversion project is to teach high school students the concept of creating electrical energy from mechanical energy. The team will create lab kits that will simulate how wind, water, and sun are used to obtain electrical energy in order to help the students understand the energy conversion process. As of November 13, 2006, the team has completed six milestones, which include: designing and building a dynamo that creates 1.5V and 10 mA, charging a battery on 10 mA and 1 V for duration of 15 minutes, operating a DC motor with the stored energy in the battery as well as testing for the minimum voltage requirement for the motor which was found to be 0.4 V and 60 mA, testing solar panels configurations to drive a DC motor, and completing a windmill design that spins the dynamo sufficiently to provide 1.5 V of electrical energy. Furthermore, the team has finished building the watermill and has tested the device; however, the goal of producing at least 1.5 V was not met as it produced 0.85 V. Also, the integration of the complete system has been modified to light an LED rather than to drive a DC motor. The team has conducted a pre-assessment test on the students and is currently assisting the students through the first phase of the project, which is building the dynamo. Presently, the team is under budget by approximately $608 and remains on schedule to complete the project by November 22, 2008.

  8. Common pitfalls with abstracts • Not fully summarizing the entire report • Not focusing on the important parts of the report • Assuming too much knowledge • Providing too much background information • Including tables, figures, equations, acronyms, or citations • Not proofreading

  9. Use headings to guide your reader Introduction, Background, and Goals Milestones Progress Description Milestones Accomplished Milestones in Progress Milestones Remaining Engineering Constraints Scheduling Budget Conclusions

  10. Introduction, Background, and Goals Introduction and Background Suppressing vibration in flexible structures with smart materials is a topic of interest in mechanical engineering. Since flexible structures are lightweight, under damped, and are increasingly being used in aerospace and other industries, the need for active vibration control of these structures is imperative. Smart materials offer a solution to this problem because their properties can be significantly changed by applying external stimuli and it is easy to integrate them into existing structures. Given the importance of this topic in mechanical engineering, Team 4 designed and built a control system to demonstrate the benefits of using smart materials to control vibration of flexible structures. Dr. Gangbing Song, the sponsor of this project and mechanical engineering professor at University of Houston, will be able to use this project to let his students see for themselves how a piezoelectric sensor can be used as an actuator when voltages are sent to it. The student will be able to select between four resonant frequencies for the beam to vibrate at as well as select any other desired frequency from 0.1[Hz] to 600[Hz] in 0.1[Hz] increments. This project also demonstrates how piezoelectric materials can be used as sensors to suppress the vibration utilizing two different structure control methods (Positive Positioning Feedback and Sliding Mode Control). When using these control methods to suppress the vibration of the beam, the student should be able to recognize the beam coming to a rest more quickly than letting the beam come to rest naturally. In addition to using smart materials to vibrate and suppress the beam, an adjustable rail-mounted laser is included that allows the student to detect the frequency of the beam at desired points as well as its peak-to-peak displacement. This information is displayed with a graph on an LCD screen for the user to see. The system is also operable from a remote location via a network port on the microcontroller. Figures 1 shows how the completed system looks. Always include an overview diagram!

  11. Overview

  12. Figure 2:Project overview depicts the block diagram of component integration to microcontroller unit (Referenced from progress report presentation prepared by Lahiru Jinadasa)

  13. Figure 2: System Overview: A simple overview of how the experiment is conducted.

  14. Before you can fully understand progress reports, you need to understand the differences between Goals Milestones Tasks

  15. The basic terminology Goal: What it is you are trying to accomplish; the bottom line. Milestone: An intermediate accomplishment. It is specific, concrete, verifiable, and important to the project. Tasks: The things you do to get the job done. Customer: Who you are doing this for in the first place. Deliverable: What the customer wants.

  16. Milestones act as deliverables on the way to the goals These should be quantifiable or demonstrable Research? Testing? Demonstrations? Demonstrate that circuit configuration fulfills X functions. Demonstrate interaction between transmitter and computer. Demonstrate that computer program serves X functions. Validate communication between satellite and program. Show that X fulfills X functions.

  17. Tasks are the actual work that must be done to complete those milestones Collect journal articles regarding detection methods Research microcontrollers to determine best one for satellite communication Draft literature review Plan circuit layout Create testable circuit board Write detection program

  18. Example of Goals, Milestones, and Tasks for a specific project Goal: Build an autonomous robot that traverses a maze until it locates a STOP sign. Milestones: • Demonstrate a working vision system that recognizes a stop sign. • Complete a microprocessor algorithm that enables the robot to turn at an intersection. Tasks: • Order parts. • Researching microprocessor possibilities. • Assembling parts.

  19. An example of project milestones Demonstrate a working ADC (Analog to Digital Converter) using MCSH12 Motorola Chip, and interface it with the wireless transceiver chip. This ADC will be tested by applying an analog signal to the port of the chip, and monitor the digital output on the computer screen to make sure the signal is converted to digital. Also, the input pin of the transceiver chip will be tested to check if the interface is working as required. Design and implement a working impedance matching circuit that will enable us to connect the PZT sensor signal with the microcontroller chip. This circuit will be tested by checking if the PZT sensor is compatible with the microcontroller. Demonstrate a working receiver and interface it with a computer. This receiver will be tested by receiving the signal transmitted over the required distance. This signal should also be seen on the computer screen using the hyperterminal. Demonstrate ability to receive the signals and the ability to generate a signal and send it back by programming Labview software to suit our application. These abilities will be tested by vibrating the PZT sensor and seeing the equivalent signal on the screen and sending back a signal to vibrate the PZT. Accomplish the final product by implementing the microcontroller, transceiver, and PZT on one board, and attach them with the small structure building model. This milestone will be accomplished when the building is impacted by a force, and the resultant voltage signal is shown in Lab view. The Methodology section will then explain how each of these tasks will be reached.

  20. 3. Progress Description 3.1 Milestones Accomplished 3.1.1 Milestone 1: Demonstrate an operational dynamo that will create 1.5 [V] The design and testing of the dynamo was completed as indicated in the previous progress report (Torres 2006: 4-6). The original vertical axis dynamo design was altered several times, and the end result was a horizontal axis dynamo that produced 1.5 V and 5.6 mA with a 10 Ω load. The final design was tested at different speeds and showed an increasing linear relationship with the output voltage. The dynamo satisfied the team’s desire to reach 1.5 V. 3.1.6 Milestone 6: Demonstrate integrated systems charging battery or driving load The team encountered a problem with the system as it became integrated. The integrated system consists of the energy capturing device, dynamo, rechargeable battery, and a DC motor as a load. When each of these components were tested individually, each one functioned properly and was assumed to continue to work when the system was configured together; however, in the process of converting from AC to DC, the current obtained after the rectifier was 40 , which is very minimal and thus is not able to drive a DC motor or fully charge a battery. With the amount of current and voltage the dynamo is producing, the team has decided to use an LED as a load instead of a DC motor. Despite the fact that the dynamo is not able to produce enough current to drive a DC motor or charge a battery, the students will still be able to use the solar panels to charge a battery and use a DC motor as a load. Furthermore, the lab manuals have been finished and distributed to all of the students along with the required materials to build the dynamo.

  21. Engineering Constraints There were three engineering constraints that our group had to be cautious of while working on this project. Health and safety was of concern since constructing many of the components for the project involved the use of potentially hazardous tools such as soldering irons and wire cutters. Care had to be taken with these tools so that an injury does not occur to any group members. Reliability of the electrical components integrated with the system was another constraint especially during the fabrication stage of our project. Unintentional misuse resulted in chips or ports on the microcontroller being burned out. Work on the project was hindered because of waiting to replace those parts. There was also an economic constraint. The electronic components being used for this system were very expensive including the microcontroller and graphical LCD especially. Great care had to be taken so that while prototyping we did not damage them.

  22.  There will always be issues and constraints that prevent the project from progressing or not operating efficiently in any give engineering project. The constraints that we have faced are forms of economic restrictions, manufacturing stability and durability of the product. Economical Constraint/Restrictions   A project; whether it is in engineering or any other field, will frequently be faced with economical constraints. It is always our objective as well as a priority to finish a project within budget. Due to limited budget, we had to constantly concentrate on reducing the cost of the robot. We were encouraged to use parts from the old robots that were used in the previous years. However, there are very high possibilities to obtain damaged parts that would delay the project’s progression. Due to a tight budget, we could not buy more reliable and efficient parts that could improve the timing as well as the efficiency of building the robot. Manufacturability Constraint  Manufacturability would be another constraint that hindered the progression of our project, since we could not build the desired as well as a competitive design to make the project more dependable and reliable. Since we did not have the necessary tools, we could not manufacture the design concepts that could make the robot more robust. A project also requires enough time to be spent on designing as well as manufacturing. Time constraints also play a big part in delaying the project’s progression by not spending enough time on the project since all the group members (students) have other academic courses to dedicate time to or work a specific amount of hours at their jobs. This can cause the task to have delays and not be completed as efficiently as possible within the available time. Durability Due to sensitivity of the microcontroller, extra caution had to be performed before making any contact with it. For instance, we have to make sure that the person handling the microcontroller is properly grounded to prevent any damage from electric static discharge. We also can into the situation where the microcontroller was defective upon receiving it from the manufacturer.

  23. Engineering Constraints  There are three main constraints for the project, which are economic feasibility, reliability, and safety. Extreme angular precision comes with a high price; this must be taken into account to determine the most cost effective motor that can deliver the required amount of torque and the highest angular precision for the given budget. Since this apparatus must run multiple trials per experiment for many experiments to verify any obtained results, it must be reliable enough to avoid excessive repairs. Also, the apparatus must be reliable enough to perform consistently. Finally, since there are many electrical leads, some of which are to be connected to a wall outlet, safety is a significant concern. All hazardous electrical leads must be properly covered and concealed so as to help prevent any unfortunate accidents.

  24. 4. Engineering Constraints The following are constraints that might arise during the implementation of the project: 4.1 Health and Safety Due to the nature of the project the students will be required to handle several tools that might injure them if not used with proper care. Per the customers’ request, the students are required to solder solar panels together which will expose the students to lead and high temperatures that can burn them. The students will also use tools such as a hand saw and a drill to complete the building process of the dynamo and the capturing devices. Despite the students handling dangerous tools, they will be lectured on the importance of safety to avoid any injuries. 4.2 Economic The customer has limited the team to $50 per kit as he plans to produce 20-25 lab kits for the current semester. Given this constraint, the projects created had to be designed with material that would be cheap and easy to find. 4.3 Reliability Since the client intends to use these lab kits in the following semesters, the designs created must be made with material that is easily attainable and affordable.

  25. Figure 7 - Project revived schedule Scheduling and Budget Follow numbering guidelines for figures and tables.

  26. Table 1: Team 3 Budget Figure 3 Project schedule Table 2 Budget

  27. The Conclusion should summarize and appraise your progress Summarize the goal of the project and your progress toward completing it If possible, assure the reader that the problems are being taken care of and that the project will be completed on time. If they cannot be solved, then reassess and recommend changes.

  28. Use Figures and Tables where appropriate To convince the reader that the project is being executed appropriately is to include pictures (a copy of the design schematic, a photograph of the prototype, and so on): work them into the main body of the text place the pictures immediately after the discussion of the item they illustrate.

  29. References and Appendices Include full bibliographic information for any sources mentioned in your proposal, including the background or literature review sections. Use documentation guidelines appropriate for your field—ASME, IEEE, etc. If in doubt, use CME. Include all information that is not absolutely necessary for understanding the project but could be helpful: • Preliminary data • Lengthy equations

  30. Reference all materials you did not create or write Use IEEE referencing system Remember: we assume you are the author of everything in your document unless you state otherwise

  31. A few writing notes: • Bad: CBSE(Component-based software engineering) • Good: Component-Based Software Engineering (CBSE)

  32. “We’ll just go with the flow and use the 10 kOhm resistor because it won’t break the bank like the fibrillated googlewazer.” “The 10 kOhm resistor is much less costly than the fibrillated googlewazer, and a negligible change in the cutoff frequency results from its use in the design.” “The XYZ widget is very popular because it’s small and cheap, and we like it a lot.” “We believe that this new design will work really well and that the project will be a big success.”, or “I feel that the XYZ widget is the best on the market.” From http://www.egr.msu.edu/classes/ece480/ goodman/WritingMistakes.pdf

  33. Summary Provide specifics – avoid relying on vague, overly general statements about the work you've done Choose technical detail wisely: not too little, not too much List each problem only in conjunction with a solution Make good use of figures/ examples Maintain a positive, encouraging tone