SHRIRAM FOUNDRY LTD.MACHINE SHOP Oct. 2011
TEAM MEMBER:- • Mr. R.R.NERLEKAR.(I/C Pulley line) • Mr.S.R.HIREMANI.(I/C Hub Line) • Mr.G.M.SHAIKH (Tooling) • Mr.S.B.PATIL ( Quality) • Mr.P.P.Patil ( System)
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET FRONT HUB - 10001946 400 nos casting stock at our end & 144 ready for dispatch.Job in production.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET ROTTER - 10009996 Machine utilized for nut plate..
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET HUB – 10019717 Spline Total 62 nos CR rejected at 5/8 tapped hole.After remove the setting casting received.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET HUB – 100143439Rear Hub) 1st set up 256 jobs machined found 121 nos CR & 7 nos MR. To fulfill the customer schedule again production start.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CUMMINS – Nut Plate(400/100)
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET HUB – 10019759 96 nos ready for dispatch.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET FRONT HUB – 10020463(250 BHN) 108 no's CR & 11 no's CR.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONMET FRONT HUB – 10019817(ADB hub) 100 no's ready for dispatch & under production.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- Pulley 413.0(SG Iron) 32 no's CR.(one day production)
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- Pulley 800.2(Double decker) CR 57 nos, MR 05 nos.(3day production) CR 43 nos, MR 05 nos.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- Pulley 642.0 59 no's CR.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- Pulley 189.0
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- Nabe 2222845
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB 1946 6.5x200 TS DRILL 04 NOS. RS 2600/- TOOL COST RS. 41.24 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:-CONMET ROTTER 9996` Casting to Finish Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB – 9717 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB – 9759 Ø16.570 carbide drill Rs. 6500 /- 01 nos Tool Cost Rs. 45.20 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CUMMINS – NUTPLATE (100/400) Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB – 4343 Ø12.57x215 shr/57 01 nos rs. 1271 & SHR/450 01 NOS Rs. 1875 Tool Cost Rs. -50.86 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB – Hub 9817 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB – 20463 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONMET HUB – NEB HUB 2222845 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- Pulley 642 Ø13 carbide Drill Rs. 5240 Tool Cost Rs. 40.61 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- Pulley476 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- Pulley 413 Rough grooving resharp insert stock complited,new insert under trial cost planned 175 RS per job. A4 SMR Holder Rs. 4500/ Casting Problem CNMA 120412 Insert Breakage Tool Cost Rs. 208.00 A4 SMR Holder Rs. 4500/ Casting Problem CNMA 120412 Insert Breakage Tool Cost Rs. 219.20 Casting Problem CNMA 120412 TT 7310 Insert Breakage Tool Cost Rs. – 150.35 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- Pulley 145 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- Pulley 189 4ASMR -2525, 1 HOLDER & Ø11.1 CARBIDE DRILL RS. 8000 TOOL COST RS. 34.89 Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- Pulley 800.2 Rough grooving resharp insert stock complited,new insert under trial cost planned 230 RS per job. TDT 4 E .04 K-10 Insert New Insert & TTER Holder 1 nos Tool Cost Rs. 328.05 TDT 4 E .04 K-10 Insert New Insert & TTER Holder 3 nos / A4SMR Holder 1 nos Tool Cost Rs. 422.88 Note:- To calculate labor cost take 35% overhead on Basic+DA
MACHINE UTILISATION IN % (VTL – Oct 11) Pulley Pulley
MACHINE UTILISATION IN % (CNC – Oct 11) HUB Pulley
MACHINE UTILISATION IN % (CNC - Oct 11) ROTTER/NUTPLATE Pulley
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET HUB 4343 PRD- 323 NOS, IN H MR 2.17% ( 7), SF MR 0.93 % (3) PRD- 191 NOS, IN H MR 6.81% (13), SF MR 3.14 % (6) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET HUB 9716 PRD- 131 NOS, IN H MR-7.63% (10) –( IN THIS 5JOBS ARE REJECT IN HOLE 24.86 WALLSHIFT) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET HUB 9736 PRD- 443 NOS, IN H MR- 6.77% (30) ( IN THIS 8 JOBS REJECTED IN FACE OUT CUT & 12 JOBS REJECTED IN OD 159 OBLONG DUE TO TOOLING / HARDNESS PROBLEM ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET 10019817 PRD- 327 NOS,, IN H MR 4.89 % (16) ( IN THIS REJECTION 3 JOB REJECTED IN 6.52 DRILLING WALLSHIFT & 4JOBS IN HOLE 24.86 SHIFT & TOOL MARK MR) SF MR 1.53 % (5) PRD- 200 NOS,, IN H MR 1.5 % (3) SF MR 1.5 %( 3) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET HUB 9815 PRD- 546 NOS, IN H MR- 2.20% (12) ( IN THIS REJECTION 5JOBS REJECTED IN HOLE 24.86 TOOL MARK & OUT CUT MR) SF MR - 0.73% (4) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET ROTOR 9970 PRD- 136 NOS, IN H MR- 4.41% (6) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- CONMET ROTTER 9996 PRD- 538 NOS, SF MR 3.53% (19 ) BORE OVERSIZE S.J IRON FOR IST OPERATION, IN H MR 2.79% (15 ) PRD- 813 NOS, IN H MR 5.29% (43 ) Due to improper fettling – 10 nos,Due opt neg at spot face,Wall shift 5 nos. PRD- 610 NOS, IN H MR 1.64% (10) (IN THIS REJECTION 5 JOBS REJECTED IN HOLE 13.47 WALLSHIFT) SF MR 0.33% (2) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- PULLEY 266.1 16.85 %(15),Due PRD- 89NOS,, IN H MR to improper clamping 3 nos,size variation problem 6 nos. PRD- 231 NOS,, IN H MR 0.43 % (1), ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- Pulley 190.0 PRD- 421NOS,, IN H MR 0.48 %(2) SF MR 0.24% (1) PRD- 371 NOS, IH MR 0.27 % (1) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- ECC HUB 790/791/858.1/859.1 PRD- 684NOS,, IN H MR 5.40 %(37) SF MR 0.29 % (2) (36 NOS OF HUB 790.1 rejected in broaching angle fire.) PRD- 963 NOS,, IN H MR 0.42 %(4) SF MR 3.95% ( 38) REJECTED BY Padmavati Engg. PRD- 1129NOS, IN H MR 0.62 %(7) SF MR 1.06% (12) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- Pulley 771.0 PRD- 340NOS, ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- Pulley 145.3 PRD- 436 NOS,, IN H MR 1.61%(7) PRD- 372 NOS,, ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- housing 650 0619 PRD- 135 NOS,, IN H MR 1.48 % (2) PRD- 115 NOS,, IN H MR 1.74 % (2) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- Nabe Hub 2222845 /Nabe hub 5457 PRD- 418NOS, IN H MR 2.39 %(10) SF MR 1.44 % (6) PRD-208NOS, IN H MR 1.44 %(3) SF MR 0.96%(2) PRD- 116NOS,, IN H MR 1.72 %(2) ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- Nut plate 398187400/398187100 PRD- 979 NOS,, IN H MR 6.24 % (66 in this 39 jobs of part no 398187400 & 27jobs of part no 398187100 rejected in development.) PRD- 223 NOS, PRD- 1310 NOS, ***ACTION ON MAJOR REJECTION CAUSES