An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. February 2012 Generation Resource Energy and Regulation Deployment Performance QMWG 3/2/2012

  2. NON-IRR GREDP – Energy Deployments Resources below 85% threshold * Resource was testing and used a resource status that caused it to be scored for GREDP

  3. NON-IRR GREDP – Energy Deployments Bottom intervals by score Bottom intervals by error

  4. NON-IRR GREDP – Regulation Deployments Bottom 10 Resources during Regulation intervals Bottom intervals by score Bottom intervals by error

  5. IRR GREDP Resources below 95% threshold Bottom intervals by score Bottom intervals by error

  6. IRR Failures

  7. GREDP Scenario Analysis * January performance of frequency excluded intervals for NON-IRRs was 99% (74406 passed/75123 scored). The Std Dev was 2.98 MWs. * January performance of frequency excluded intervals for IRRs was 91.4% (2184 passed/2389 scored). The Std Dev was 5.3 MWs.

  8. Manual HDL/LDL Override Summary QMWG

  9. Daily Summary Graph • For this analysis, we captured unique HDL/LDL overrides • An override is considered unique if that same Resource did not have an override within the last 10 minutes • There were 21 total unique overrides in February • As compared to 13 in January and 13 in December

  10. Daily Summary Table

  11. Reasons for Manual HDL/LDL Overrides • An override is considered unique if that same Resource did not have an override within the last 10 minutes • The “Other” reason given was QSE requested testing • Congestion concerns were a result of inaccurate Resource telemetry