Re-Inventing DuctSox Installation

Re-Inventing DuctSox Installation. 3x1 Suspension System. Pat. Pending. 3x1 Suspension System. 1 Row Tension Cable. 3x1 Hanger. Cable Snaps. Pat. Pending. D-Clasp. 3x1 Suspension System. 36”. Hanger Spacing: 36” Cable Snaps Centered Between. 18”. 3x1 Benefits. Aesthetics

hinda
Télécharger la présentation

Re-Inventing DuctSox Installation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Re-Inventing DuctSox Installation 3x1 Suspension System Pat. Pending

  2. 3x1 Suspension System 1 Row Tension Cable 3x1 Hanger Cable Snaps Pat. Pending D-Clasp

  3. 3x1 Suspension System 36” • Hanger Spacing: 36” • Cable Snaps Centered Between 18”

  4. 3x1 Benefits • Aesthetics • Inflated Look • Stylish Components • Performance • Less Inflation Pop • Easy Installation • Single Cable • Less Knee Brackets

  5. Deflated vs. Inflated Inflated Deflated

  6. 3x1 Component Options • Standard • Grey & Solid • Color • Powder Coated Finish • Chrome (3x cost) • Style • Holes, Slotted Style Solid (std) Holes Slotted Color Gray (std) Black Charcoal White Custom

  7. Deflate - Inflate Detail Inflated Deflated

  8. 3x1 Installation • Install 1 Row Tension Cable • Install DuctSox by connect 12 o’clock cable clips first • Connect 3x1 Hanger to DuctSox, positioned over cable • Back Clip • Front Clip • Secure hanger to Cable • Secure DuctSox Position • Inlet DuctBelt and Anchors • Clamp Last Cable Snap with Cable Clamp C A B

  9. D-Clasp Connection • D-Clasp Connect to Hangers Only One Way. • Position D-Clasp Outside of Hanger • Slide Top Edge Into Slot in End of Hanger. • Tip D-Clasp Downward Into Place Securely Pat. Pending

  10. Cable Lock Detail Position Cable into Vertical Slot. Shape reduces binding on cable – allows hanger to slide easily. Plug locks cable into place. Pat. Pending

  11. Cost Analysis

  12. Cost Analysis

  13. Cost Analysis • Est. Installation Times: • H-Track: 14.5 Hrs • 2 Row Cable: 8.5 Hrs • 3x1 Cable: 5.4 Hrs • 3x1 w/ Xm: Compared To: • 2 Row H-Track: -18.8% • 2 Row Cable: +13.1% !! Excluding Knee Brackets

  14. Bracket Comparison Supports Supports Double Row 3x1 System 8 4 10 4 12 2

  15. 3x1 Suspension System Re-Inventing DuctSox Installation • Better Aesthetics • Smooth Inflation • Easy Installation