1 / 12

Capital Improvement Projects 2014 A Snapshot of Current Construction Activity in the

Capital Improvement Projects 2014 A Snapshot of Current Construction Activity in the City of Irvine. Replacement of deteriorated asphalt roadway, sidewalk, curbs, median landscape and irrigation Replacement of 140 mature Camphor trees Target Completion Date – April 2014.

Télécharger la présentation

Capital Improvement Projects 2014 A Snapshot of Current Construction Activity in the

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Capital Improvement Projects 2014 A Snapshot of Current Construction Activity in the City of Irvine

  2. Replacement of deteriorated asphalt roadway, sidewalk, curbs, median landscape and irrigation Replacement of 140 mature Camphor trees Target Completion Date – April 2014 Rehabilitation of Campus Drive

  3. Installation of gateway signage and new landscaping along both directions of I405 at Jamboree Target Completion Date – September 2014 I405 Landscaping and Monument Signs at Jamboree Road

  4. Add additional lane on northbound Jamboree south of Barranca Target Completion Date – July 2017 Widening of Barranca Parkway at Jamboree Road

  5. Add additional travel lane on westbound Barranca adjacent to The District Shopping Center Target Completion Date – April 2014 Barranca Parkway at The District

  6. Install a fuel pipeline connecting John Wayne Airport to existing Kinder Morgan pipeline in the City of Tustin Target Completion Date – To Be Determined John Wayne Airport Jet Fuel Line

  7. Installation of infrastructure to transmit usage data directly from the meter to the SCGC Target Completion Date – May 2015 Southern California Gas Company Advance Meter Project

  8. Lowering Sand Canyon under the railroad to provide a grade separated crossing Realignment and widening of the roadway from four to six lanes Target Completion Date – November 2014 Sand Canyon Grade Separation Project

  9. Add additional travel lane in each direction between Burt Road and northbound freeway on/off-ramps Additional lanes to southbound freeway off-ramp and northbound freeway on/off-ramps Target Completion Date – July 2014 Sand Canyon/I5 Widening Project

  10. Construction of three pedestrian overcrossings at Irvine Blvd, Trabuco, and Roosevelt. Provides continuous path along the Jeffrey Open Space Trail for bicyclists and pedestrians Target Completion Date - August 2014 Jeffrey Open Space Trail

  11. 5-year proposal to build 688 acres of amenities Sports Park Bosque Area Upper Bee Canyon Improvements Wildlife Corridor Golf Course Agricultural Area Trail Improvements Orange County Great Park – 688 Acres

  12. Questions? Brian King, Public Works Administrator bking@cityofirvine.org (949) 724-7308

More Related