Colbert County Budget Solutions John Bedford, P.E. County Engineer 2012 ACEA Convention

Colbert County Budget Solutions John Bedford, P.E. County Engineer 2012 ACEA Convention. Colbert County, Alabama. Located in Northwest AL, ALDOT Second Division Bordered by the Tennessee River to the North Population: 55,000 Road Miles: 430 Plant Mix, 200 Chip Seal, 30 Gravel

holt
Télécharger la présentation

Colbert County Budget Solutions John Bedford, P.E. County Engineer 2012 ACEA Convention

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Colbert County Budget Solutions John Bedford, P.E. County Engineer 2012 ACEA Convention

  2. Colbert County, Alabama Located in Northwest AL, ALDOT Second Division Bordered by the Tennessee River to the North Population: 55,000 Road Miles: 430 Plant Mix, 200 Chip Seal, 30 Gravel Unit System – 6 Commissioners, 32 Employees (18 – Maintenance Crew, 7 – Mechanic Shop, 7 – Office Staff)

  3. Road Department Revenues 4-Cent - $1,340,500 7-Cent - $1,275,000 Severance Tax - $100,000 Public Hwy - $150,000 (Equipment Budget)

  4. Road Department Expenses Salaries and Benefits - $1,329,500 Insurance - $526,900 Road and Bridge Maintenance Expense - $350,975 Fuel - $110,000 Misc. - $735,725 (All other Dept. Expenses, Federal Match, Herbicide, Signs, Overhead, Etc.)

  5. Telling Our Story Avoid “You never told me ...” or “What the @#%!” Road and Bridge Maintenance Reports Monthly Commission Reports Newspaper Articles Keeping the Commission and the Public Informed Results: Objective: Tools:

  6. Road and Bridge Maintenance Report First Completed in 2008, Updated in 2012 Overview of Road System List of Roads in Each District, including Surface Type, Length and Width Costs of Resurfacing 1 Mile Cost of Failing to Maintain Roads Gas Tax Distribution Formulas County Populations Possible Sources of New Revenue ACEA Materials and Data Local Legislature Contact Info

  7. Monthly Commission Reports Status of Current Projects Maintenance Operations Being Performed Personnel Issues Discovery of New Concerns

  8. Newspaper Articles We have built a very good relationship with our local paper. (Times Daily) They run a small story anytime we have a project starting, letting public know about traffic changes. Will run a follow up story when complete, highlighting what the project accomplished and if/how it saved money or improved travel. Encourage the public and local politicians to seek additional funding. Have run several stories for us focusing on the lack of funding and system maintenance needs.

  9. Where Should We Focus? We had to decide what was the greatest limiting factor for use of County roads. Obviously, a bad road can still be used but a closed or posted bridge isolates entire areas of a County from travel or industry. With the importance of bridges in mind and the strict guidelines for use of funding on roads, we decided that our main focus would be on bridges.

  10. Money Saving Approaches EBIT Inspections/Consultations Wooden Bridge Decks Stringer Additions False Bents Pile Encasements

  11. EBIT Inspections ALDOT Load Rating Personnel noticed that stringer detail was not shown correctly during a visit. Recommended investigating reinforcement in deck. After we determined reinforcement and ALDOT re-evaluated stringers, we were able to go from a 10 ton posting to no posting at all.

  12. EBIT Inspections On another occasion, we asked EBIT to evaluate our “abutment” walls. They agreed that they were actually “retaining” walls and we were able to remove the posting from the bridge.

  13. Wooden Bridge DecksFour Bridges - $280,000 Replaced Deck on 4 Ton Bridge - $70,000 Replaced 4 Ton Bridge with Culvert - $200,000

  14. Stringer AdditionsTwo Bridges - $32,000

  15. False BentsOne Bridge - $24,500

  16. Pile EncasementsTwo Bridges - $32,000

  17. What About Roads? Limited use of Federal funding on roads originally built with Federal funds. Surface Treatments with Federal Funding – This year we initiated our first Federal Aid resurfacing project using a “G” “D” surface treatment as the final layer. Strip Patching – Aside from Federal Resurfacing, Surface Treatments are the only pavement we put down. Partnering With Other Counties – We bought liquid asphalt from Lauderdale and Lawrence Counties for years before we could buy a tank of our own. Recently we have swapped out our shoulder machine with Franklin County for some FDR work.

  18. Questions ? Contact Info.John Bedford, County Engineer256-381-2120jbedford@colbertco.org