1 / 14

Short Term MPL – Western Area PCCG Meeting 3 rd December 2008

Short Term MPL – Western Area PCCG Meeting 3 rd December 2008. Background. SA Government recognises Penrice operations provide important economic benefits to the State No current viable alternatives in SA to high grade limestone

iago
Télécharger la présentation

Short Term MPL – Western Area PCCG Meeting 3 rd December 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Short Term MPL – Western AreaPCCG Meeting3rd December 2008

  2. Background • SA Government recognises Penrice operations provide important economic benefits to the State • No current viable alternatives in SA to high grade limestone • Short term constraints to overburden storage options (schist and aggregates) • Long term overburden storage options yet to be resolved • Important that the process of consultation on issues & MOP/MARP continues

  3. Why is the MPL needed now? • Removal of overburden schist is required in the short term to maintain supply of L/Stone to Osborne & ABC • PIRSA has concluded that there is an urgent short term need for additional overburden storage area • Short term mine operational constraints: • OB removal rates much greater than OB aggregate sales • Current in pit storage already used for low grade limestone • Production constraints (mining cycle, grade control) • Crusher location • Water storage • Unreasonable to expect Penrice to store schist in pit in short term prior to mining • Substantial rehandling costs $4-5 million • Will add to the constraints for operation of pit • Need space for LG limestone storage • The impacts of storage on an MPL managed

  4. Goals for interim arrangement • Investigation and justification of long term overburden storage options to be completed. • Discussion and resolution of environmental issues including visual impact of current operations needs to be concluded. • Environmental performance of current operations to be improved • Development of agreed MOP/MARP for whole site • Ongoing compliance monitoring • Supply of Osborne Stone to ABC and Osborne must continue

  5. How will goals be achieved? • Provide Penrice with limited MPL • Setting rigorous regulatory framework, conditions on all tenements, rehabilitation bond. • Ongoing operation of community consultation

  6. PIRSA’s proposal Will be limited compared to original application: • reduced area (south side of Jaeckeli Creek only, approx ½ original area) • limited term (end September, 2009, usually for minimum of 7 years) • limited volume (2 million tonnes, original application was for about 8 million tonnes) Will also revise conditions for existing MPL and ML

  7. Reduced Area

  8. Proposed licence conditions • First schedule • general conditions for all licences • Second Schedule • environmental outcomes to be achieved • Some specific limitations and requirements

  9. First schedule • Limits activities to “overburden storage” • Requires an approved MARP to operate • Requires immediate and annual reporting of compliance • Allows independent auditing of compliance • Requires $20 million public liability insurance • Ensures public access to key documents (MARP and MARCR)

  10. Second Schedule- Environmental Outcomes • Visual amenity • final rehabilitated landform and vegetation must “integrate and harmonise” with surrounding landscape • Must be self sustaining • Link to Barossa Development Plan • Noise, dust– no nuisance • Unauthorised access – prevent injuries to public • Protection of aboriginal heritage

  11. Second Schedule- Environmental Outcomes (Contd) • Native vegetation • No clearance in Jaeckeli Creek • Must develop a management plan to enhance Jaeckeli creek habitat • Soil- must preserve all existing topsoil • Stormwater - must manage runoff

  12. Second Schedule- other conditions • Limits total overburden storage to 2 million tonnes • Validates PCCG • Must address public complaints • Requires that a study of overburden storage options be completed within 3 months

  13. Next Steps • MPL offer subject to receiving and considering advice from Planning Minister (expected week commencing 15 Dec) • Mining Minister decides whether to grant MPL • Penrice have requested this happen before Christmas to permit commencement of operations early 2009 • If MPL granted, Penrice must, before operations commence: • prepare MARP for the site (criteria to measure outcomes) • gain MARP approval from PIRSA • pay rent in advance • pay rehabilitation bond • Review of MOP/MARP for whole site will continue • MOP reviews required by Mining Act • MARP review provided by license/lease condition

  14. Any questions?

More Related