abcdefghij. Financial Partnerships Unit. Financial Partnerships Unit. Obtaining Design Quality in PPP Projects. David Fox Turner & Townsend Group. Obtaining Design Quality in PPP Projects. Scottish Executive Seminar 30 November 2004. Ensuring Design Quality in the PPP Process.

igor-barber
Télécharger la présentation

Financial Partnerships Unit

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. abcdefghij Financial Partnerships Unit Financial Partnerships Unit Obtaining Design Quality in PPP Projects David Fox Turner & Townsend Group

  2. Obtaining Design Quality in PPP Projects Scottish Executive Seminar 30 November 2004

  3. Ensuring Design Quality in the PPP Process • What is driving the Design Quality? • Education and Quality Standards • Output vs Prescription (Mandatory/Non Mandatory Requirements) • Use of Model Documentation • Consultation as a Design Tool in Procurement • Affordability is King • Exemplar Designs

  4. What is Driving Design Quality - Many Conflicting Needs • Requirements of the EA and Users • Mandatory Design Standards • Competitive Tension • Affordability • Whole Life Assessment • Transferred Risk • Risk of Performance Deductions

  5. We have: Building Regs Planning Regs SE Standards British Standards DFES We need: Generic Space Standards Education Environmental Standards Education Accommodation Standards Education and Quality Standards- They are not robust enough

  6. Output vs Prescription - We need the correct balance • We need Clear Accommodation/Service Requirements • Prescription gives certainty but retains the risk • Use Mandatory and non Mandatory Requirements • Mandatory - Output standards designed for full period • Non Mandatory - Detail sets the Evaluation Standards • Get the Standard right through Regular Mid Tender Meetings

  7. Use of Model Documentation • Allows Bidders to Major on Project Specifics • Familiar Documents let Bidders concentrate on Designs • Models reflect Government Risk Profile • Bidder Friendly Documentation • Prioritised to Meet Client Requirements • Commercially Realistic

  8. Output Specification Structure • Designed to reflect Executive Risk Profile • Accommodation Requirements • Accommodation Schedules • FM Requirements • Minimising Disruption/Constraints • Design Standards • Room Data Sheets • More than one way to skin this cat • Designed to focus on Council Priorities

  9. Exemplar Designs • DFES/PfS Designs – Sets standards but unaffordable • Project Reference Designs • Following Consultation confirms Affordable practical solution • Specification ties in with exemplar and OBC - confirms affordability • Users must understand the context and the process • Careful programming : Spec.-design-consultation-affordability • Role of Reference Design in Procurement Process • Not mandatory but standard against which quality evaluated • Good Bidder Consultation ensures understanding and no surprises

  10. Consultation as a Design Tool • Regular Bidder Meetings are a Must • More Comprehensive Expectations in a non Mandatory Form • Council Standing Orders can be an Issue • Mould Designs to suit Requirements • Ensure All bids meet Requirements • Detailed Development when Preferred Bidder • Groups will not all be Correct First Time • Don’t Corrupt the Competition

  11. Affordability is King • Major movement in build costs • Robust PSC - Build a Comprehensive Picture • The Use of Sample Designs • Ensure Spec. Reflects Award – Benchmark costs • Clearly Set Out Affordability Targets • Maintain Competitive Pressures • High level of Consultation • Affordability Targets are Sacrosanct

  12. Ensuring Design Quality in the PPP Process • Influence the Drivers to work on your behalf • Education and Quality Standards - If not available adopt best practice • Fundamentals of Project Feasibility • Output vs Prescription - Get the Balance right • Reference Designs or provide reference projects • Use of Model Documentation - Project Specifics • Consultation is a Design Tool • Managing Affordability