An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Team gay avenue Project battLEDship MELODY KIDD KELLY MCFARLANE SCOTT MATSUO RAPHAEL RAMOS

  2. battLEDship

  3. Re-creation of the classic board game Battleship • Materials: • Surface-mounted LEDs • Reflective sensors • Arduino Mega 2560 OVERVIEW

  4. ACCOMPLISHMENTS

  5. OTHER ACCOMPLISHMENTS • Schematic design for PCB • Important milestone that was not added • Foundation block needed before the group can continue to design and connect parts together • This design plays a huge role into how the hardware will be connected

  6. UPCOMING DEADLINES

  7. SCHEMATIC DESIGN Overview schematic of Arduino Mega 2560

  8. SCHEMATIC CONT. Overall layout of LED schematic

  9. SCHEMATIC CONT. 0 0 0 0 – 0 0 0 0 – 0 0 0 0 board numbercolor (R,G,B)row (1-10)column (1-10)

  10. SCHEMATIC CONT. Close up schematic of LED

  11. SCHEMATIC CONT. Overall schematic layout of phototransistor

  12. SCHEMATIC CONT. 0 0 0 0 – 0 0 column (1-10) board number

  13. SCHEMATIC CONT. Close up schematic layout of phototransistors

  14. ISSUES/CONCERNS • Due to how long it’s taking for LEDs to arrive: • All milestones that deal with the LEDs are delayed • Cannot do any testing between the sensors and LEDs • Milestone originally created for best case scenario; Everything will need to be adjusted to make up for delay. • Hardware implementation: rely heavily on schematic design of PCB

  15. CONCLUSION • Due to a minor delay, the team is currently behind schedule on building the project • As soon as LEDs arrive, testing and assembling will begin to determine how LEDs and sensors must be connected to achieve our goal for the project.