An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utilities Management CSHE Los Angeles Chapter 2013 Annual Devin J Hugie, SASHE, CHFM, CHSP-FSM, CHEP

  2. Criticality • Criticality defined as “the immediacy of risk to patient safety or quality of care as a result of noncompliance with a joint commission requirement.” • 4 levels of Criticality: • Immediate Threat to Life (ITL) *PDA Until Resolved • Situational Decision Rules * Based on Specific situations at time of Survey. • Direct Impact Requirements * Noncompliance may create an immediate risk to patient safety or quality of care. • Indirect Impact Requirements * Based on planning and evaluation or care processes

  3. What Triggers ITL(Immediate Threat To Life) • Significantly compromised fire alarm system • Significantly compromised fire sprinkler system • Significantly compromised emergency power supply system • Significantly compromised medical gas master alarm panel • Significantly compromised exits • Other situations that place patients, staff or visitors at extreme danger

  4. Criticality of Findings & Immediacy of Risk • The amount of time for submitting the ESC (Evidence of Standards Compliance) is based on the criticality of the finding and the immediacy of risk as follows • Direct Impact Within 45 Days • Indirect Impact Within 60 Days • D- Documentation is required • C- “C” Standards, All others are “A” standards

  5. EC.02.05.01 Manages Utility Systems Risks • Design/Installs systems that meet pt care / op needs • Written inventory of components D • Identifies inspection / maintenance activities D C • Identifies intervals for inspecting, testing, maintain componentsD • Minimizes pathogenic biological agents in cooling towers, etc • Pressure relationships; air-exchanges, filtration efficiencies (the ventilation systems provides appropriate pressure relationships, air-exchange rates, and filtration efficiencies) • The hospital maps distribution of utility systems D • The hospital Labels emergency shut downs • The hospital has written procedures for responding to utility system disruptions D • The hospitals’ procedures address shutting off the malfunctioning systems and notifying staff in affected areas. • The hospitals procedures address performing emergency clinical interventions during utility systems disruptions. • The hospitals procedures addresses the following: How to obtain emergency repair services. • The hospital responds to utility system disruptions as described in its procedures

  6. EC.02.05.03 Emergency Electrical Power Provides Emergency power for • Alarm systems per LSC (NFPA 99) • Exit route and exit sign illumination • Emergency communication system • Elevators (at least 1 for non-ambulatory pts) • Equipment that could cause harm if fails • Areas where loss of power cause result in PT harm (Or’s)

  7. EC.02.05.05 Maintain Utility Systems • Tests components before initial use D C • Inspects/tests/maintains Life Support Utility Systems D • Inspects/tests/maintains inf Cont utility system components D • Inspects/tests/maintains Non-Life Support Utility components D C

  8. EC.02.05.07 Maintains Emergency Power Systems • 30 day intervals, test battery-powered lights for 30 seconds (if required for egress) D C • 12 months, tests battery-powered lights for 1.5 HRS or replace all batteries @ 12 months/random tests 10% (if required for egress) D C • SEPSS tested for 5 min monthly/annual full load D • 12/year tests emergency generator for 30 minutes D • Emergency generator tested @ 30% or exhaust temp or annual load bank: 25% for 30 min, 50% for 30 min, 75% 60 min • 12/yr tests all automatic transfer switches D • 36 months, generator tested for 4 continuous hours D • 36 month test uses 30% nameplate rating or temp • Per Occurrence: If test fails, implements measures to protect pts until repaired • Perform retest after repairs

  9. EC.02.05.09 Maintains Medical Gas and Vacuum Systems • Inspects, tests, maintains critical components per defined timeframes D • Tests for purity, correct gas, pressure when installed, modified, repaired D • Shutoff valves accessible and clearly identifies control areas EC.02.05.09 Monitors conditions in environment • Utility systems management problems, failure, use errors C

  10. EM.02.02.09 Utility Disruption Emergency Operations Plan identifies alternative means of providing: • Electricity • Water needed for consumption and essential care activities • Water needed for equipment and sanitary purposes • Fuel required for building operations or essential transport activities • Medical gas/vacuum systems • Utility systems defined as essential, such as • Vertical & horizontal transport • Heating & cooling systems • Steam for sterilization • Utility needs identified in the HVA

  11. New Areas of Focus On the increase are observations related to: • Electrical Panel Schedules • Room Pressure relationships • Fire Sprinkler lines used for support • Battery back up lighting in Generator rooms • Eyewash Stations

  12. Questions Thank You