Nextef Status of h igh gradient experiment

Nextef Status of h igh gradient experiment. May 13-15, 2008 2 nd Collaboration meeting on X-band Accelerator Structure Design and Test Program T. Higo, KEK. Nextef progress Establishing power generation and transport in 2007.

jasia
Télécharger la présentation

Nextef Status of h igh gradient experiment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nextef Status of high gradient experiment May 13-15, 2008 2nd Collaboration meeting on X-band Accelerator Structure Design and Test Program T. Higo, KEK

  2. Nextef progressEstablishing power generation and transport in 2007 2nd collaboration meeting on X-band

  3. Nextef inside shield roommost basic components are now in line. 2nd collaboration meeting on X-band

  4. Nextef planning 2008 2009 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 Establish system with KX03 T18_VG2.4_Disk #2 TD18_VG2.4_Quad TD18_VG2.4_Disk T18_VG2.4_Disk #3 T18_VG2.4_Disk #4 ????? C-band test at same place 2nd collaboration meeting on X-band

  5. What are needed for Nextef • Enough power, 55MW, 300ns at accelerator structure, CLIC_VG1, for 100MV/m • Square RF pulse with variable width • Operation and each RF pulse analysis at 50Hz • Stable operation with BRD < 1BD/hr at most • Proper control program based on the well-defined processing protocol • Identification of breakdowns, distinguishing either at structure or outside 2nd collaboration meeting on X-band

  6. Nextef Nominal RF power line Low loss waveguide ACC-IN 2-klystrons  120MW, 300ns klystron—3dB 2.3m 3dB— LLWG 1.5m LLWG 5m LLWG—ACC Str5.0m WR90 flanges ~36sets*7mm SUS Loss Kly.Str. ~23% Delay ~ 50ns ACC Structure S+N Two klystrons 2nd collaboration meeting on X-band

  7. Nextef operation without structure RF shape at 50MW, 300ns, 50Hz Refl_load ACC-Refl ACC-IN S+N S+N S+N_refl Shape rise and fall and flat top Refl_load 2mV / 89mV = ±0.4mW / 11mW = ±4% Base line jitter or actual? Refl. From load 2nd collaboration meeting on X-band

  8. Nextef recent typical operation Blue ~ ACC-IN[MW], Pink = Load Vacuum, Green = Combiner vacuum Stable operation at 50MW level Rarely but sometimes vacuum jump near combiner 3dB, with big reflection to klystrons Load vacuum jump with reflection from load 2nd collaboration meeting on X-band

  9. Readiness of components • Nextef: Refer to Matsumoto’s talk • Klystrons are tested at 60MW for 300nsec pulse, which makes the combined power of 120MW. • 3dB hybrid or WR90 waveguide components are sometimes arcing at 50MW level now. This needs to be conditioned out or identified to distinguish from the events due to accelerator structure. • Loads are subject to damage due to high pulse energy operation. Proper loads are to be used for the loads downstream of accelerator structure. 2nd collaboration meeting on X-band

  10. Nextef: Nominal observables along waveguide SLAC 3dB DC made by BINP Ra F & Rs VAC WR90 ACC structure IP 30l/s Guard window TE01-type T Lounine Load (based on SLAC design) Ohtsuka Load 2nd collaboration meeting on X-band

  11. Beam-line setup 2nd collaboration meeting on X-band

  12. Nextef: observables along beam axis AM PM PM GV ACC str GV FC Qmass FC FC 2nd collaboration meeting on X-band

  13. Preparation status of sensors • RF pulse: crystals • Combined, ACC-input are being monitored as feed RF power. • F, Rs, Ra and T will be detected with crystals. Each pulse will be analyzed with 7000 series Tektrooscillo. Oscilloscope data taking is under development at KT-1. • VAC : cold cathord gauges • CCG monitors are working at various places of WR90 and two points of beam line • Dark currents: Faraday cups, analyzer magnet and profile monitors • DC current measurement wit FC is our typical. • Transient response of FC is yet to be confirmed. • AM should work without problem. • The response of profile monitor is not checked after many years idling. • Acoustic sensors • Sensors are those from SLAC and used at XTF. • VME modules are under preparation for operation. • Photomultiplier and scintillator • A few lead-shielded sets are prepared. • Q-mass • Operation should be checked. 2nd collaboration meeting on X-band

  14. Various detection tools are to be integrated into Nextef control system Klystron LLRF CCG Data storage KEKB Inj. control Modulator INTLK Safety Mod. PLC Discri S/H & DC Amp System control PC Python, Linux Pictures are recorded now. Digital data should be recorded. X-ray TDS3034B (300MHz) TDS3054B (500MHz) RF crystal CT DL7480 (500MHz) History 4MW/ch Various signal X-ray Buy for Nextef? Etc. Etc. Acc PLC VME Acoustic (SLAC) Now being prepared Acoustic DPO7054 (1GHz, every pulse) FPGA (100MHz) Etc. Etc. AM FC

  15. Nextef to be done for breakdown detection system • Tektro 7054 pulse-to-pulse analysis • Take experience at KT-1 • Establish the threshold and other parameters • RF pulse at all points • Identify the breakdown position in Nextef system • Digital data taking and analysis as needed. • VME modules • Restart operation program similar to XTF • Use as positioning of arc in the system or in the structure. • FC, AM, PM, PMT, Q-mass operations • Basic performance should be confirmed. With actual signal or with other source? • Red-marked items should be from the beginning of CLIC_VG1 test. 2nd collaboration meeting on X-band

  16. Conclusion • Nextef power rating is now ~50MW, 300ns, 50Hz level with less than 1BD/hr. • We need to establish the detection system in May with KX03. • In breakdown detection and analysis at the input power level of 50MW or more. • We want to start CLIC_VG1 before summer shutdown of KEKB. • Some incompleteness of the system should be tolerated, as long as essential features, such as power evaluation, processing protocol and identification of breakdown, are confirmed. • We try to operate the Nextef as effectively as possible within the KEK regulation. • Hopefully run during shutdown but we admit it not easily be realized. 2nd collaboration meeting on X-band