1 / 5

Golden Spread ERCOT Load

Golden Spread ERCOT Load. 7 Member Distribution Cooperatives 230 MW of Peak Load 104 Delivery Points (46 are at >60 kV) 108 Miles of Transmission Lines (all radial) Transmission Service Provided by: ONCOR AEP LCRA TNP. TRE Registration. DP & LSE for one Member Cooperative

jaunie
Télécharger la présentation

Golden Spread ERCOT Load

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Golden Spread ERCOT Load • 7 Member Distribution Cooperatives • 230 MW of Peak Load • 104 Delivery Points (46 are at >60 kV) • 108 Miles of Transmission Lines (all radial) • Transmission Service Provided by: • ONCOR • AEP • LCRA • TNP

  2. TRE Registration • DP & LSE for one Member Cooperative • No other registrations are required

  3. ERCOT Transmission Operations Requirements • 24 hour operations desk- WAN • Telemetry requirements for 5 delivery points • Outage Scheduler • BLT Coordination (6 currently being registered) • Synder Wind Farm (63 MW) connected to a 69 kV line • Receive and comply with ERCOT Dispatch Instructions • Potential Load Shed Coordination • Members loads are not listed in the ERCOT Load Shed Table • Currently ONCOR and AEP shed the load as a part of their plan

  4. Transmission Operations Delegation • Current TO’s serving GSEC Loads unwilling to sign and perform TO functions • Take on liability? • Make no earnings or return • Use valuable management time and resources • Potential Solutions • An ERCOT registered TO step up and respond to RFP • A PRR for a “TO Light” • Coalition of DSPs/TSPs develop a TO function • GSEC build an in-house TO

  5. Solution #4 – Cost/Benefit? • Uncertain of the cost, will be high • Take time to build • Back-up center • Very limited interaction with ERCOT Ops • Maybe a few times a year • Does this benefit justify the high cost • Will be rolled into TCOS and cause all ERCOT customers to pay for this cost.

More Related