1 / 13

Glen Ridge Public School s

Glen Ridge Public School s. Construction Project Update Forest and Linden Avenue Schools July 23, 2012. Introduction.

jeri
Télécharger la présentation

Glen Ridge Public School s

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Glen Ridge Public Schools Construction Project Update Forest and Linden Avenue Schools July 23, 2012

  2. Introduction After nearly a year of study and discussion, the Board of Education has decided to launch major capital improvement projects at Forest Avenue School and Linden Avenue School. These projects are designed to provide our educators with the additional space and flexibility necessary to meet the evolving educational needs of our youngest students. Through prudent management of the district’s resources, we have a one-time opportunity to make these improvements without incurring debt. We could not undertake this initiative without the help and support of the community. We look forward to working and communicating with staff, parents and neighbors as we move forward.

  3. Statement of Need - Capacity FOREST AVENUE SCHOOL • Functional 201 students • Current 259 students • Overage 58 students LINDEN AVENUE SCHOOL • Functional 210 students • Current 278 students • Overage 68 students

  4. Statement of Need - Energy Conservation Energy Audit Results • Wings most energy inefficient spaces in the District • HVAC Wings

  5. Statement of Need - Use of Space FOREST AVENUE SCHOOL • All Classrooms Used All Day • Self-contained Special Education Classroom • Resource Room Special Education Program • Shared-Use Room: Resource Center/Reading Instruction • Shared-Use Room: Morning Pre-K/Afternoon Art LINDEN AVENUE SCHOOL • All Classrooms Used All Day • Self-contained Special Education Classroom • Resource Room Special Education Program • Shared-Use Room: Morning Art/Afternoon Counseling, Meetings, OT/PT

  6. Addressing the Needs FOREST AVENUE SCHOOL • Classroom • Small Group Instructional Room • HVAC Wing • Playground • Basketball Court Eliminated LINDEN AVENUE SCHOOL • Classroom • Small Group Instructional Room • HVAC Wing • Playground

  7. Cost Forest $729,000 Linden $789,000 TOTAL$1,379,000

  8. Tasks Completed • Educational Specifications • Architectural Drawings • Soil Testing • Arborist Evaluation • State Application

  9. Tasks Imminent • Confer with Mayor and Borough Manager • Borough Committees’ Approvals (Planning Board, Historic Preservation Commission) • State Approval • Bids • Neighbor Meetings • Ongoing Communication

  10. Construction timetable • Schematic Design Process: 3 Months - April 7, 2012 • Initiate Contract w/ Architect (DRG to draft and forward). • Secure quote for Survey of properties. • Secure quote for Site / Civil Engineering Services. • Secure quote for Soils Engineering and Analysis

  11. Construction timetable (cont’d) • NJDOE: • District to provide an Educational Specification to support additions. Include mission statement, purpose, proposed occupancy, room amenities, etc. • District to review proposed plan layouts provided by architect. Provide written comment for architect to make revisions. • Architect to develop final floor plans and elevations for state and local review. • Amend the currently approved LRFP via Board of Education Resolution. • Adopt the final “Educational Specifications” and “Drawings” via Board of Education Resolution. • Approve DRG to expedite application and all supporting materials to the NJDOE for Schematic Approval.

  12. Construction timetable (cont’d) • Local Planning Requirements: • Appear before Glen Ridge Planning Board for courtesy review as required by the NJDOE. • Appear before Glen Ridge Historic Preservation Commission. • Construction Documents Process: 2 Months - July 25, 2012 (REVISED) • Collect site survey / soils information. • Develop drawings and specifications. • Consult with attorney on front end requirements. • Send completed documents to DCA Trenton for review. • Tony Brun has approved for final educational adequacy and forward to NJDCA to initiate Local Review. • Local reviewer has agreed to meet next week to finalize the plans.

  13. Construction timetable (cont’d) • DCA Trenton Review: 3 Months (varies) - Oct 1, 2012 • DCA issues code review. • Architect responds • Preparing for bid • Advertise - Bid Period 1 ½ Months - November 15, 2012 • Construction 5-6 Months (varies) - May 15, 2013 • Long lead items • Windows - 16 weeks from order • Unit Ventilators - 10 weeks from order

More Related