1 / 21

AMS-02 Ground Handling Equipment (GHE) and Assembly Operations for the GHE

AMS-02 Ground Handling Equipment (GHE) and Assembly Operations for the GHE. Ground Safety Review – Phase II September 8-10, 2008 Phil Mott. KHB 1700.7C Space Shuttle Payload Ground Safety Handbook SW-E-0002E Ground Support Equipment General Design Requirements

jilliank
Télécharger la présentation

AMS-02 Ground Handling Equipment (GHE) and Assembly Operations for the GHE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AMS-02 Ground Handling Equipment (GHE) andAssembly Operations for the GHE Ground Safety Review – Phase II September 8-10, 2008 Phil Mott AMS-02 GSR Phase II

  2. KHB 1700.7C Space Shuttle Payload Ground Safety Handbook SW-E-0002E Ground Support Equipment General Design Requirements NASA-STD 8719.9 formerly NSS/GO-1740.9B Standard for Lifting Devices and Equipment Documents Governing GHE Design AMS-02 GSR Phase II

  3. Primary Support Stand (PSS) • Used for payload integration and shipping • Two configurations: Low & High • Constructed with Aluminum 6061 • Covers are Alumalite (painted aluminum face sheet with plastic corrugate) • Factors of Safety • 2 on yield • 3 on ultimate AMS-02 GSR Phase II

  4. Primary Support Stand (PSS) – Low Configuration • Shipping Configuration • 195” x 125” x 117” high • Top Cover is removed as one piece AMS-02 GSR Phase II

  5. Primary Support Stand (PSS) – High Configuration • Assembly/Integration Configuration • 195” x 125” x 166” high AMS-02 GSR Phase II

  6. Primary Lifting Fixture (PLF) • Used to lift the PSS and AMS-02 • Welded steel A36 structure • WLL: 26,800 lbs • Factors of Safety • 3 on yield • 5 on ultimate • Initial proof load to 2X WLL • Annual load test to 1X WLL AMS-02 GSR Phase II

  7. Multi Purpose Lifting Fixture (MPLF) • Used to lift the Lower USS (LUSS) into place on the Upper USS and to lift the PAS into place for attachment • Welded steel A36 structure • WLL: 7000 lbs • Factors of Safety: • 3 on yield • 5 on ultimate • Initial proof load to 2X WLL • Annual load test to 1X WLL AMS-02 GSR Phase II

  8. Lower USS (LUSS) Shipping Fixture • Used to ship/move/install the Lower USS • Can be moved with forklift or crane/MPLF • Welded steel A36 structure AMS-02 GSR Phase II

  9. Other Hardware • Can be moved with forklift, crane, air pallet, hand carts, or by hand • All lifting hardware will meet NASA-STD 8719.9 AMS-02 GSR Phase II

  10. Assembly Operations AMS-02 GSR Phase II

  11. Arrival at KSC – Unload/Prep in the SSPF Airlock • Crane PSS/Upper USS-02. • Fork/Crane Lower USS-02 • Fork/Crane all other Hardware including CGSE AMS-02 GSR Phase II

  12. Arrival at KSC – Unload/Prep in the SSPF Airlock (cont) AMS-02 GSR Phase II

  13. Move Into SSPF – Footprint 7 • Crane or air pallet PSS/USS-02 • Crane, fork, or air pallet all other hardware AMS-02 GSR Phase II

  14. Unpacking • Remove the upper cover from the PSS using the MPLF or slings • Remove the side panels from the PSS • Remove the cover from the LUSS Shipping Fixture • Set up Cryosystem GSE (CGSE) AMS-02 GSR Phase II

  15. PSS Preparation for AMS-02 Assembly/Integration • Install Upper Columns and Beams on the PSS AMS-02 GSR Phase II

  16. PSS Preparation for AMS-02 Assembly/Integration • Raise the PSS/Upper USS-02 to the high position • Install supports AMS-02 GSR Phase II

  17. Installation of the Lower USS onto the Upper USS • Fork the Lower USS under the Upper USS in the PSS AMS-02 GSR Phase II

  18. Installation of the Lower USS onto the Upper USS (cont) • Lift the Lower USS into position using the MPLF • Position hydraulic jacks under the Lower USS for support and final positioning • Attach Lower USS to Upper USS with pins and bolts AMS-02 GSR Phase II

  19. Installation of the PAS • Weight of PAS = 220 lbs • PAS will be installed using the LUSS, overhead crane, and bottle jacks PAS EBCS AMS-02 GSR Phase II

  20. Installation of the PAS (cont) • Procedure similar to Lower USS installation – Details in work • Place PAS on top of LUSS Shipping Fixture • Place under payload using forklift • Raise and rotate using bottle jacks AMS-02 GSR Phase II

  21. Installation of the Keel • Weight of Keel = 67 lbs • Keel will be a 2 person manual lift and bolts installed by a 3rd person AMS-02 GSR Phase II

More Related