An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Transition to SuperJANET5 Roland Trice r.trice@ukerna.ac.uk

    2. MANs Meeting June 2006 SuperJANET5 Transition 2 Introduction Acceptance Testing Transition Timetable Transition Process

    3. MANs Meeting June 2006 SuperJANET5 Transition 3 Acceptance Testing Core testing complete Agilent testers Detailed reports from Verizon Quality audit at each C-PoP In person, by ULCCs senior engineers Time consuming but necessary Core network has been accepted

    4. MANs Meeting June 2006 SuperJANET5 Transition 4 Acceptance Testing Circuit acceptance tests C-PoP QA by the NOSC Connection of 4200s to the Junipers Testing using sweep-pings around looped circuits Not likely to be complete until 3rd week of July Acceptance Testing at the RNEPs Not practical for NOSC staff to supervise RNOs are asked to do so on UKERNAs behalf

    5. MANs Meeting June 2006 SuperJANET5 Transition 5 Acceptance Testing Check fibre installation against scope of work You should have full spec in your installation pack Tell Rolly & Eddie if you dont SuperJANET5 Network Rollout, RNEP Requirements The facilities you need to provide Acceptance Process for Regional Networks Circulated this week Details need revising

    6. MANs Meeting June 2006 SuperJANET5 Transition 6 Rack Layout

    7. MANs Meeting June 2006 SuperJANET5 Transition 7 Plan B

    8. MANs Meeting June 2006 SuperJANET5 Transition 8 RNO Acceptance Test Verizon will perform QA Auditor will liaise with RNO staff Audit in the presence of the RNO Both parties sign off the audit RNO should make sure that the audit IS done Confirm that your site is left safe and tidy Confirm that the audit is completed diligently

    9. MANs Meeting June 2006 SuperJANET5 Transition 9 RNO Acceptance Test RNO is not: Expected to verify each item on the check list Warranting that the installation is fit for purpose Please please please leave lawyers out of this If there are issues: Tell Rolly Who will tell Verizon Please sign off any snagging when it is complete

    10. MANs Meeting June 2006 SuperJANET5 Transition 10 Transition Timetable Changed to the originally published timetable Delays in circuit delivery Newts, wayleaves, asbestos, small digging teams Majority of circuits tested by 3rd week in July Critical mass necessary before testing Avoids repeated visits to C-PoPs There may need to be further changes to the timetable

    11. MANs Meeting June 2006 SuperJANET5 Transition 11 Transition Timetable Transition should begin on 18th July If you can go early, thats good Timetable on UKERNA web pages If its a piece of cake I will re-timetable to move three RNs a week Contingency slots every 2nd or 3rd week If its a trip to the dentist Thursday mornings will be used to clear the backlog Will decide in October

    12. MANs Meeting June 2006 SuperJANET5 Transition 12 Transition Timetable UKLight and non-RN connections will move during clearing If transition has not started before clearing Timetable Tuesday and Thursday transition slots Weekend or evening transitions are not on the agenda UKERNA reserves the right to move RNs during clearing

    13. MANs Meeting June 2006 SuperJANET5 Transition 13 Transition Timetable 18/07 NorMAN (possible) C&NLMAN (possible) 25/07 NNW (possible) EMMAN (possible) 1/08 SCOLOCATE, Contingency 07/08 Clearing Starts 08/08 EastNET, Contingency 15/08 EastNET, Contingency 26/09 NNW, Kentish MAN 03/10 EastMAN, LeNSE unicast, Contingency 05/10 LeNSE multicast 10/10 ClydeNET, C&NLMAN, Contingency

    14. MANs Meeting June 2006 SuperJANET5 Transition 14 Transition Timetable 12/10 LeNSE multicast contingency 17/10 AbMAN, Wales MAN, Contingency 24/10 FaTMAN, LMN, Contingency 31/10 SWERN, UHI, Contingency 07/11 NorMAN, MidMAN, Contingency 14/11 EMMAN, NIRAN, Contingency 21/11 YHMAN, TVN, Contingency 28/11 Contingency, Contingency 05/12 Contingency, Contingency 12/12 Contingency, Contingency

    15. MANs Meeting June 2006 SuperJANET5 Transition 15 Transition Arrangements Connect up as soon as circuits and routers ready PING tests to confirm circuit availability Set things up in advance Hot cut from SJ4 to SJ5 Once you have moved over, Baoyu will arrange to have the BAR decommissioned and removed within a month or so

    16. Questions?