1 / 13

Second Meeting of the Material Budget & Engineering Working Group

Second Meeting of the Material Budget & Engineering Working Group. feasibility of CO2 cooling with existing CMS pipework. Re-use cooling pipes. Cooling pipes are installed as bottom layer on the vac-tank. Covered by a vast amount of ECAL and Tracker cables.

jock
Télécharger la présentation

Second Meeting of the Material Budget & Engineering Working Group

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Second Meeting of the Material Budget & Engineering Working Group feasibility of CO2 cooling with existing CMS pipework Hans Postema (CERN)

  2. Re-use cooling pipes • Cooling pipes are installed as bottom layer on the vac-tank. • Covered by a vast amount of ECAL and Tracker cables. • Covered by a vast amount of Tracker optical fibres. • Re-installation of pipes will require an extremely long shutdown. Hans Postema (CERN)

  3. YB0 with cables Hans Postema (CERN)

  4. Inside the Vac-tank Hans Postema (CERN)

  5. YB0 and PP1 view Hans Postema (CERN)

  6. YB0, tower, balcony Hans Postema (CERN)

  7. PP1 to tower routing Hans Postema (CERN)

  8. All routes, Z+ view Hans Postema (CERN)

  9. Top view UX cavern Hans Postema (CERN)

  10. Summary of tubes • Between Tracker and PP1 3 m of tube with ID 10 mm, can easily be replaced • Between PP1 and Tower, 20 m of tube with ID 12 mm • Between Tower and Cooling station 20-40 m of tube with ID 14 mm • All tubes are soft copper with 1 mm wall thickness • Tubes can run either 10 m up or down with respect to the Tracker Hans Postema (CERN)

  11. CMS ladder dimensions 1mm ID Tube Q = 40 Watt Tube length = 2.5 meter 1 CMS ladder : 1.25 meter length Cooling

  12. CMS, use of existing tubes • CMS pipes = 14mmID • 18kW =>1 liquid line & 6 vapor lines • 1 loop assembly = 7 tubes • 6 loop assemblies = 42 tubes for 108 kW • 450 ladders per loop assembly • 3150 ladders in total • Shut-down and start-up difficult due to low allowed pressure of Cu-tubing 12.7bar = - 33’C 10 m static height: dP=1bar~2’C dT 120 g/s, 18kW 6 tubes 13.9bar Dcooling=1mmID Q=40W TCO2=-30’C MF= 0.26 g/s dP= 600 mbar dP@50m=150mbar~0.3’C dT 450x Liquid CO2 P=17.9 bar T=-38’C 14.5bar 1 tube 17.9bar 17.7bar Dcapillary=0.5mmID x 5m dP=3.2bar 120 g/s liquid = 200mbar

  13. Pressures • Elastic limit of soft copper 16 mm pipe corresponds to about 70 bar. • CO2 boiling point -20 C at 20 bar, thus moderate pressure during operation. • At +25 C, CO2 boils at 65 bar, this requires further investigation into a system with low pressure startup capability. Hans Postema (CERN)

More Related